| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/19/2019 | $750K | — | — → — | $313/sf building |
| 01/24/2017 | $590K | — | Private party → DIMIX AND COMPANY LLC | $246/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 2 | 03/27/2025 |
| LAWRENCE ADJAH, ARCHITECT | 4 | 01/13/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| S R SOLAR DESIGN | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JAMES J DESTRA | General Contractor | 5 | 03/22/2026 |
| JOEL FISCHER | Electrical | 1 | 03/21/2026 |
| LAWRENCE ADJAH | Electrical | 1 | 03/21/2026 |
| REM & SONS LIC ELEC CONT | Electrical | 1 | 03/22/2026 |
| NEW YORK STANDARD MECH CO | Fire Protection | 1 | 07/08/2026 |
| J SYNERGY GREEN INC | General Contractor | 1 | 07/08/2026 |
| JEFF GLANSTEIN | Electrical | 1 | 03/21/2026 |
| NEW YORK STANDARD MECH CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 2 | 03/27/2025 |
| PRUDIGM ENGINEERING LLCU | 4304 | 4 | 01/13/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | J SYNERGY GREEN | 02/13/2025 |
| DOB NOW | Sprinklers | Signed-off | NEW YORK STANDARD MECH CO | 07/19/2021 |
| DOB NOW | Plumbing | Signed-off | NEW YORK STANDARD MECH CORP | 07/19/2021 |
| BIS | — | ISSUED | JAMES J DESTRA | 09/03/2021 |
| BIS | PL | ISSUED | W.G. PLUMBING & HEATING | 03/06/2006 |
| BIS | OT | ISSUED | SMEDCO INC | 01/25/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/25/2025 | Complete | GREEN LIGHT ELECL & MECH | — |
| 04/25/2023 | Complete | SELECT ELECTRICAL GROUP I | General Wiring |
| 02/10/2022 | Complete | REM & SONS LIC ELEC CONT | 3 meters, 3 new_meters |
| 07/01/2021 | Complete | JALEX ELEC'L CONTR. INC | General Wiring |
| 12/14/2019 | Complete | JALEX ELEC'L CONTR. INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/28/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/10/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/08/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/20/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/06/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/03/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 04/03/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 04/03/2025 | Final | NARESH MAHANGU | progress |
| 04/03/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 04/03/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 03/11/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 03/11/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 03/11/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 03/11/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 03/11/2025 | Final | NARESH MAHANGU | progress |
| 01/14/2022 | Sprinkler Systems | Naeem Anwar | special |
| 01/14/2022 | Energy Code Compliance Inspections | LAWRENCE ADJAH | progress |
| 01/13/2022 | Energy Code Compliance Inspections | LAWRENCE ADJAH | progress |
| 01/13/2022 | Sprinkler Systems | Naeem Anwar | special |
| 09/29/2021 | Energy Code Compliance Inspections | LAWRENCE ADJAH | progress |
| 09/29/2021 | Sprinkler Systems | Naeem Anwar | special |