| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/23/2021 | $1.3M | — | Private party → Private party | $673/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CL ENGINEERING P.C. | 2 | 04/01/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| HIGHQUALITY CONSTRUCTION VNW | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MES CONSTRUCTION CORP | Plumbing | 7 | 07/08/2026 |
| HIGH QUALITY CONSTRUCTION | General Contractor | 3 | 07/08/2026 |
| KJK ELECTRIC INC | Electrical | 2 | 03/21/2026 |
| ZHENG LI | Electrical | 2 | 03/21/2026 |
| SO PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| J&R DESIGN AND INSPECTION | 6637 | 2 | 04/01/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | MES CONSTRUCTION CORP | 06/10/2021 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 05/06/2021 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 04/15/2021 |
| DOB NOW | Plumbing | Signed-off | NICHOLAS SUIDA | 04/06/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2021 | Complete | KJK ELECTRIC INC | 3 meters, 3 new_meters |
| 04/13/2021 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/29/2021 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 03/29/2021 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 03/29/2021 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 03/29/2021 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 03/29/2021 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |