| Owner | Filings | Most Recent |
|---|---|---|
| MW CONSTRUCTION | 15 | 07/08/2026 |
| DNS FINE BUILDERS | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/21/2021 | $645K | — | Private party → MW 4355 EAST TREMONT LLC | $532/sf building |
| 06/13/2018 | $500K | — | Private party → Private party | $413/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AL FFRED ARCHITECTURE PLLC | 5 | 12/28/2022 |
| LIGHT HOUSE | 1 | 03/28/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| NEVM EXPEDITORS | 6 | 03/21/2026 |
| JYA EXPEDITERS GROUP. | 2 | 03/21/2026 |
| CB EXPEDITING | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WATSON'S PLBG, HTG, & BDG | Plumbing | 6 | 07/08/2026 |
| MW CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| DAVID MINZ | Electrical | 1 | 03/21/2026 |
| ENDRE BANYA | Electrical | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | MW CONSTRUCTION INC | 05/24/2022 |
| DOB NOW | Plumbing | Permit Issued | WATSON'S PLBG, HTG, & BDG | 02/15/2022 |
| DOB NOW | General Construction | Signed-off | MW CONSTRUCTION INC | 02/10/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/28/2022 | Permit Issued | WATSON'S PLBG, HTG, & BDG | Gas, Storm, Water/Sanitary |
| 03/28/2020 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/01/2023 | Permit Issued | TFK ELECTRIC CORP | General Wiring |
| 02/27/2022 | Complete | TFK ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/20/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/30/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 06/08/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/08/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/02/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/02/2022 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/02/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/02/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/02/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/29/2022 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 11/21/2022 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 08/02/2022 | Insulation placement and R values | PAUL MARINO | energy_progress |
| 08/02/2022 | Interior lighting power | PAUL MARINO | energy_progress |
| 08/02/2022 | Air barrier - visual inspection | PAUL MARINO | energy_progress |
| 08/02/2022 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 08/02/2022 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 08/02/2022 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 05/13/2022 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 02/02/2020 | Energy Code Compliance Inspections | SAMIR ABDALLA | progress |