| Owner | Filings | Most Recent |
|---|---|---|
| VM 4401 | 47 | 09/13/2026 |
| SKYLINE SCAFFOLDING GROUP | 9 | 07/08/2026 |
| VIK XS SERVICES | 8 | 07/08/2026 |
| METROPOLITAN LIC LLC | 1 | 03/22/2026 |
| MEGA CONTRACTING GP | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KONOSKI ENGINEERING PLLC | 8 | 08/12/2026 |
| S.M. BERGER ARCHITECTURE PC | 4 | 07/01/2026 |
| PROSPECT ENGINEERING P.C | 1 | 06/30/2026 |
| JILL E FUDO, ARCHITECT | 3 | 04/03/2026 |
| WW ENGINEERING PLLC | 2 | 02/25/2026 |
| PANTEC ENGINEERING | 2 | 10/14/2025 |
| THE H ARCHITECTS LLC | 1 | 04/14/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 10/28/2024 |
| OSPINO ENGINEERING PLLC | 2 | 07/23/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 26 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 6 | 03/21/2026 |
| AO CONSULTING AND DRAFTING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SKYLINE SCAFFOLDING GROUP | General Contractor | 13 | 07/08/2026 |
| MEGA CONTRACTING GP LLC | General Contractor | 6 | 07/08/2026 |
| VIK XS SERVICES INC | General Contractor | 2 | 03/21/2026 |
| MAGIC MECHANICAL INC | Fire Protection | 2 | 07/08/2026 |
| MAGIC MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| UPSTRATE INC | General Contractor | 2 | 07/08/2026 |
| UNITECH DESIGN | Scaffold | 1 | 07/03/2026 |
| ALPINE ENTERPRISES NY LTD | General Contractor | 1 | 04/09/2026 |
| A & E PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| DDS MECHANICAL FPS CORP | Fire Protection | 1 | 06/07/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METRIC CONSULTING AND INS | 1803 | 11 | 08/07/2026 |
| INTERNATIONAL GEOTEHCNICA | 1795 | 3 | 02/25/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Permit Issued | UNITECH DESIGN INC | 07/01/2026 |
| DOB NOW | Plumbing | Permit Issued | DDS MECHANICAL FPS CORP | 06/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | UPSTRATE INC | 04/13/2026 |
| DOB NOW | General Construction | Permit Issued | UPSTRATE INC | 04/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | A & E PLUMBING CORP | 03/18/2026 |
| DOB NOW | Sprinklers | Permit Issued | MAGIC MECHANICAL INC | 10/30/2025 |
| DOB NOW | Sprinklers | Permit Issued | MAGIC MECHANICAL INC | 10/30/2025 |
| DOB NOW | Construction Fence | Signed-off | MEGA CONTRACTING GP LLC | 04/15/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ALPINE ENTERPRISES NY LTD | 11/14/2024 |
| DOB NOW | General Construction | Signed-off | MEGA CONTRACTING GP LLC | 10/28/2024 |
| DOB NOW | Plumbing | Permit Issued | MAGIC MECHANICAL INC | 10/28/2024 |
| DOB NOW | Plumbing | Permit Issued | MAGIC MECHANICAL INC | 10/28/2024 |
| DOB NOW | Structural | Signed-off | MEGA CONTRACTING GP LLC | 10/28/2024 |
| DOB NOW | General Construction | Signed-off | MEGA CONTRACTING GP LLC | 10/28/2024 |
| DOB NOW | Supported Scaffold | Signed-off | SKYLINE SCAFFOLDING GROUP | 10/03/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | VIK XS SERVICES INC | 07/23/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | VIK XS SERVICES INC | 07/23/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/10/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/12/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 10/14/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/07/2026 | Signed-off | ALPINE ENTERPRISES NY LTD | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PUHY-EP312TSNU-A1 350,000 BTU · Vrf Outdoor ×2 PUHY-EP336TSNU-A1 378,000 BTU · Vrf Outdoor ×2 PUHY-EP384TSNU-A1 430,000 BTU · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | Permit Issued | MAGIC MECHANICAL INC | Sprinkler System |
| 02/25/2026 | Permit Issued | DDS MECHANICAL FPS CORP | 53 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/12/2026 | — | — | Water/Sanitary |
| 08/07/2026 | Permit Issued | MAGIC MECHANICAL INC | Storm, Water/Sanitary |
| 02/25/2026 | Permit Issued | A & E PLUMBING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2026 | Permit Issued | MAJOR ELECTRIC INC. | General Wiring |
| 06/19/2026 | Permit Issued | ATMOS ELECTRIC SVCE CORP | — |
| 05/06/2026 | Permit Issued | CMY ELECTRICAL CORP | General Wiring |
| 12/11/2025 | Complete | MAJOR ELECTRIC INC. | General Wiring |
| 02/18/2025 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| 07/07/2022 | Complete | TOP SHELF ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/28/2024 | Signed-off | SKYLINE SCAFFOLDING GROUP | Scaffold, Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/11/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/15/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/11/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 12/02/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/11/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/19/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/18/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/14/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/02/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/04/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/13/2026 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 07/13/2026 | Ventilation and air distribution system | — | energy_progress |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 06/25/2026 | Maintenance information | — | energy_progress |
| 06/25/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/25/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/25/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/25/2026 | Shutoff dampers | — | energy_progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/25/2026 | Mechanical Systems | — | special |
| 06/25/2026 | Final | — | progress |
| 06/25/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/25/2026 | Maintenance information | — | energy_progress |
| 06/25/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/25/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 04/02/2026 | Final | — | progress |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/03/2026 | Final | — | progress |
| 02/19/2026 | Energy Code Compliance Inspections | MICHAEL KARANTINIDIS, P.E. | progress |
| 02/19/2026 | Fire-Resistant Penetrations and Joints | MICHAEL KARANTINIDIS, P.E. | special |
| 02/13/2026 | Fire-Resistant Penetrations and Joints | MICHAEL KARANTINIDIS, P.E. | special |
| 02/13/2026 | Heating Systems | MICHAEL KARANTINIDIS, P.E. | special |
| 02/02/2026 | Public Assembly Emergency Lighting | MICHAEL KARANTINIDIS, P.E. | progress |
| 01/12/2026 | Sprinkler Systems | MICHAEL KARANTINIDIS, P.E. | special |