← Back
Multi-story retail building (2+)
44-31 DOUGLASTON PARKWAY
QUEENS · BIN 4453377
💬 Discuss this project
1931Year Built
2Stories
K2Building Class
R1-2Zoning
24,630 sfGross Floor Area
24Units
10 Open Violations 2 unresolved · 8 paperwork only ▸FDNY Report ↗
Multi-story retail building (2+) · Owner of record: DOUGLASTON CORNER LLC · 18,414 sf lot · 1.34 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Roof2p · 1 filing · 8 docs
Floor 16p · 2 filings · 20 docs
Cellar1p · 1 filing · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
C PLUS DESIGN GROUP607/08/2026
WORLDKER CONSTRUCTION COR103/22/2026
B H B CONSTRUCTION203/21/2026
RIDGE REALTY403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BKH ARCHITECT, PLLC107/21/2026
JKM ARCHITECTURE PC208/03/2025
SY ENGINEERING PLLC808/17/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
C PLUS DESIGN GROUP2003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CK PLUMBING & MECH INCPlumbing307/08/2026
C PLUS DESIGN GROUP INCGeneral Contractor107/08/2026
UNIQUE MECHANICAL CORPGeneral Contractor107/25/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BKH ARCHITECT, PLLC6255107/21/2026
JKM ARCHITECTURE P.C.8906107/21/2025
SY ENGINEERING PLLC5149408/17/2021
Building Lifecycle
All (54)Filed (11)Permit Issued (5)Signed Off (3)Violation (5)Special Inspection (30)
08/05/2026
Signed off — Alteration
DIRECT REPLACE 2 HVAC (10 TOTAL) RTU ON ROOF THAT SERVE FIRST & SECOND FLOOR UNITS OF: 44-35/44-39 DOUGLASTON PARKWAY
Q01433394-I1
07/23/2026
Permit issued — General Construction
Q01433394-I1-GC-CX
07/21/2026
Filed — Alteration
DIRECT REPLACE 2 HVAC (10 TOTAL) RTU ON ROOF THAT SERVE FIRST & SECOND FLOOR UNITS OF: 44-35/44-39 DOUGLASTON PARKWAY
Q01433394-I1
07/20/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Brandon Hamchuk
07/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Brandon Hamchuk
07/20/2026
Special inspection requirement — Mechanical Systems
Brandon Hamchuk
07/20/2026
Special inspection requirement — Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components
Brandon Hamchuk
07/20/2026
Special inspection requirement — Maintenance information
Brandon Hamchuk
07/20/2026
Special inspection requirement — HVAC-R and service water heating equipment
Brandon Hamchuk
07/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
Brandon Hamchuk
07/20/2026
Special inspection requirement — Air barrier - visual inspection
Brandon Hamchuk
07/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Brandon Hamchuk
07/20/2026
Special inspection requirement — Energy Code Compliance Inspections
Brandon Hamchuk
07/20/2026
Special inspection requirement — Final
Brandon Hamchuk
08/03/2025
Filed — Alteration
INSTALLATION OF BBQ SYSTEM, INCLUDING EXHAUST DUCT AND FAN. NO CHANGE IN USE, OCCUPANCY CLASSIFICATION AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q01246687-S1
07/25/2025
Permit issued — Mechanical Systems
Q01246687-I1-MS
07/21/2025
Filed — Alteration
INSTALLATION OF BBQ SYSTEM, INCLUDING EXHAUST DUCT AND FAN. NO CHANGE IN USE, OCCUPANCY CLASSIFICATION AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q01246687-I1
06/26/2025
Special inspection requirement — Duct leakage testing, insulation and design
YOUNGSAM YU
06/25/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
John Min
06/25/2025
Special inspection requirement — Mechanical Systems
John Min
06/25/2025
Special inspection requirement — Final
John Min
06/01/2023
Violation issued (FDNY_ORDER, closed)
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/08/2021
Signed off — Alteration
INSTALLATION OF (2)GAS BOILER. NO CHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q00442289-I1
12/08/2021
Signed off — Alteration
REMOVAL AND INSTALLATION OF PLUMBING FIXTURE AND COOKING EQUIPMENT. THIS APPLICATION IS IN CONJUNCTION WITH APPLICATION# 421805026.
Q00312849-I1
08/19/2021
Special inspection requirement — Maintenance information
SUNGBOM YI
08/19/2021
Special inspection requirement — Shutoff dampers
SUNGBOM YI
08/19/2021
Special inspection requirement — HVAC and service water heating equipment
SUNGBOM YI
08/19/2021
Special inspection requirement — HVAC and service water heating system controls
SUNGBOM YI
08/19/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SUNGBOM YI
08/17/2021
Filed — Alteration
INSTALLATION OF (2)GAS BOILER. NO CHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q00442289-P3
05/19/2021
Filed — Alteration
INSTALLATION OF (2)GAS BOILER. NO CHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q00442289-P2
03/22/2021
Special inspection requirement — Shutoff dampers
SUNGBOM YI
03/22/2021
Special inspection requirement — HVAC and service water heating system controls
SUNGBOM YI
03/22/2021
Special inspection requirement — Maintenance information
SUNGBOM YI
03/22/2021
Special inspection requirement — HVAC and service water heating equipment
SUNGBOM YI
03/22/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SUNGBOM YI
02/19/2021
Filed — Alteration
REMOVAL AND INSTALLATION OF PLUMBING FIXTURE AND COOKING EQUIPMENT. THIS APPLICATION IS IN CONJUNCTION WITH APPLICATION# 421805026.
Q00312849-P3
02/05/2021
Filed — Alteration
INSTALLATION OF (2)GAS BOILER. NO CHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q00442289-P1
02/05/2021
Permit issued — Plumbing
Q00312849-I1-PL
02/03/2021
Permit issued — Boiler Equipment
Q00442289-I1-BE
01/30/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SUNGBOM YI
01/30/2021
Special inspection requirement — HVAC and service water heating system controls
SUNGBOM YI
01/30/2021
Special inspection requirement — Maintenance information
SUNGBOM YI
01/30/2021
Special inspection requirement — Shutoff dampers
SUNGBOM YI
01/30/2021
Special inspection requirement — HVAC and service water heating equipment
SUNGBOM YI
01/11/2021
Filed — Alteration
INSTALLATION OF (2)GAS BOILER. NO CHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICATION.
Q00442289-I1
12/14/2020
Filed — Alteration
REMOVAL AND INSTALLATION OF PLUMBING FIXTURE AND COOKING EQUIPMENT. THIS APPLICATION IS IN CONJUNCTION WITH APPLICATION# 421805026.
Q00312849-P2
07/08/2020
Violation issued (ECB, closed)
Unknown
02/24/2020
Filed — Alteration
REMOVAL AND INSTALLATION OF PLUMBING FIXTURE AND COOKING EQUIPMENT. THIS APPLICATION IS IN CONJUNCTION WITH APPLICATION# 421805026.
Q00312849-P1
02/12/2020
Permit issued — Plumbing
Q00312849-I1-PL
02/10/2020
Filed — Alteration
REMOVAL AND INSTALLATION OF PLUMBING FIXTURE AND COOKING EQUIPMENT. THIS APPLICATION IS IN CONJUNCTION WITH APPLICATION# 421805026.
Q00312849-I1
04/03/2017
Violation issued (FDNY_NOV, closed)
08/12/1992
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offUNIQUE MECHANICAL CORP07/23/2026
DOB NOWMechanical SystemsPermit IssuedC PLUS DESIGN GROUP INC07/25/2025
DOB NOWPlumbingSigned-offCK PLUMBING & MECH INC02/05/2021
DOB NOWBoiler EquipmentSigned-offCK PLUMBING & MECH INC02/03/2021
DOB NOWPlumbingSigned-offCK PLUMBING & MECH INC02/12/2020
BISOTISSUEDWORLDKOR CONSTRUCTION CORP10/07/2021
BISOTISSUEDWORLDKOR CONSTRUCTION CORP07/06/2020
BISOTISSUEDWORLDKOR CONSTRUCTION CORP01/09/2020
BISEQISSUEDB H & B CONSTRUCTION INC05/05/2014
BISFPISSUEDNY FIRE LLC12/24/2013
BISPLISSUEDDYCKMAN PLBG AND HTG INC11/27/2013
BISMHISSUEDHAI HONG CONSTRUCTION COR11/21/2013
BISFPISSUEDIDEAL FIRE SAFETY SYSTEMS04/21/2009
BISMHISSUEDDUAL PURPOSE CORPORATION05/18/2006
BISFPISSUEDFIRE COMMAND CO., INC10/24/2005
BISMHISSUEDGEORGE PEROTTO ASSOCIATES LLP.09/26/2003
BISMHRE-ISSUEDSPARACO'S PLG AND HEATING09/25/2002
BISMHISSUEDRUSSO ENTERPRISES03/05/2001
BISPLISSUEDTRI CITY MECHANICAL GROUP CORP03/01/2001
BISOTISSUEDRUSSO ENTERPRISES02/21/2001
BISFPISSUEDSENTIENEL FIRE CONTROL, INC.07/27/2000
2 projects · most recent 07/21/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/21/2026Signed-offUNIQUE MECHANICAL CORPHeating and Air Conditioning Systems
Heat / Cool
Carrier 48GEEM05A2A3-0A0A0 48,000 BTU · Rooftop Unit ×1
08/03/2025Permit IssuedC PLUS DESIGN GROUP INCVentilation Systems—
1 project · most recent 03/05/2020
General Wiring Lighting
FiledStatusContractorScope
03/05/2020Permit IssuedY.S ELECTRICGeneral Wiring, Lighting
1 project · most recent 07/21/2026
FiledStatusContractorScope
07/21/2026Signed-offUNIQUE MECHANICAL CORP1 scope_items
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
07/20/2026Structural Stability – Alterations of existing buildingsBrandon Hamchukspecial
07/20/2026Fire-Resistant Penetrations and JointsBrandon Hamchukspecial
07/20/2026Mechanical SystemsBrandon Hamchukspecial
07/20/2026Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical ComponentsBrandon Hamchukspecial
07/20/2026Maintenance informationBrandon Hamchukenergy_progress
07/20/2026HVAC-R and service water heating equipmentBrandon Hamchukenergy_progress
07/20/2026HVAC-R and service water heating system controlsBrandon Hamchukenergy_progress
07/20/2026Air barrier - visual inspectionBrandon Hamchukenergy_progress
07/20/2026HVAC-R and service water piping design and insulationBrandon Hamchukenergy_progress
07/20/2026Energy Code Compliance InspectionsBrandon Hamchukprogress
07/20/2026FinalBrandon Hamchukprogress
06/26/2025Duct leakage testing, insulation and designYOUNGSAM YUenergy_progress
06/25/2025Fire-Resistant Penetrations and JointsJohn Minspecial
06/25/2025Mechanical SystemsJohn Minspecial
06/25/2025FinalJohn Minprogress
08/19/2021Maintenance informationSUNGBOM YIenergy_progress
08/19/2021Shutoff dampersSUNGBOM YIenergy_progress
08/19/2021HVAC and service water heating equipment SUNGBOM YIenergy_progress
08/19/2021HVAC and service water heating system controls SUNGBOM YIenergy_progress
08/19/2021Fire-Resistant Penetrations and JointsSUNGBOM YIspecial
03/22/2021Shutoff dampersSUNGBOM YIenergy_progress
03/22/2021HVAC and service water heating system controls SUNGBOM YIenergy_progress
03/22/2021Maintenance informationSUNGBOM YIenergy_progress
03/22/2021HVAC and service water heating equipment SUNGBOM YIenergy_progress
03/22/2021Fire-Resistant Penetrations and JointsSUNGBOM YIspecial
Latest 25 of 30.
▾Documents — 132 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch - Plumbing4
08/28/2026Q00312849-I1Request digital key ↗
08/15/2026Q00312849-P3Request digital key ↗
08/15/2026Q00312849-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment4
08/27/2026Q00442289-P2Request digital key ↗
08/27/2026Q00442289-I1Request digital key ↗
08/15/2026Q00442289-P3Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch3
08/19/2026Q01246687-I1Request digital key ↗
08/19/2026Q01246687-S1Request digital key ↗
08/16/2026Q01433394-I1Request digital key ↗
▸Applications & Permits15
▸BISPLAN / WORK APPROVAL APPLICATION8
10/19/2021421802026Open ↗
10/12/2021421802026Open ↗
01/15/2020421802026Open ↗
Showing 3 of 8 on file for this type
▸BISWORK PERMIT APPLICATION7
01/15/2020421802026Open ↗
05/04/2014440141222Open ↗
01/06/2014420925921Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications43
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/19/2026Q01246687-S1Open ↗
08/19/2026Q01246687-I1Open ↗
08/16/2026Q01433394-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/23/2026Q00442289-I1Open ↗
09/01/2026Q01246687-I1Open ↗
09/01/2026Q01246687-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/23/2026Q00442289-I1Open ↗
09/01/2026Q01246687-I1Open ↗
09/01/2026Q01246687-I1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
01/15/2020421802026Open ↗
03/04/2014420924548Open ↗
11/26/2013420925921Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
01/15/2020421802026Open ↗
05/04/2014440141222Open ↗
11/25/2013420924548Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
05/04/2014440141222Open ↗
10/26/2013440112334Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
05/04/2014440141222Open ↗
10/26/2013440112334Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
01/15/2020421802026Open ↗
11/25/2013420924548Open ↗
▸Trade Schedules & Equipment3
▸BISSELF-CERT PLUMBING NOTICE2
02/13/2014420924548Open ↗
01/08/2014420924548Open ↗
▸BISSCHEDULE B - PLUMBING1
11/25/2013420924548Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/13/2026Q00312849-I1Open ↗
08/13/2026Q00442289-P1Open ↗
08/13/2026Q00442289-I1Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
01/15/2020421802026Open ↗
11/26/2013420925921Open ↗
11/25/2013420924548Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
04/07/2009420003196Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
01/15/2020421802026Open ↗
04/08/2014440112334Open ↗
03/27/2014420924548Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
12/13/2021421802026Open ↗
10/26/2013440112334Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
03/04/2014420924548Open ↗
04/08/2014440112334Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/26/2013440112334Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
12/13/2021421802026Open ↗
▸BISNYCECC ANALYSIS1
10/26/2013440112334Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
12/13/2021421802026Open ↗
05/04/2014440141222Open ↗
10/26/2013440112334Open ↗
▸Approvals, Objections & Sign-offs11
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
12/15/2021421802026Open ↗
04/08/2014440112334Open ↗
03/27/2014420924548Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
04/08/2014440112334Open ↗
03/27/2014420924548Open ↗
03/04/2014420925921Open ↗
▸BISADMINISTRATIVE OBJECTIONS3
11/26/2013420925921Open ↗
11/25/2013420924548Open ↗
04/07/2009420003196Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT8
01/15/2020421802026Open ↗
03/04/2014420925921Open ↗
03/04/2014420924548Open ↗
Showing 3 of 8 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
12/13/2021421802026Open ↗
▸Filing & Intake Forms8
▸BISEFILING COVER SHEET4
01/15/2020421802026Open ↗
11/26/2013420925921Open ↗
11/25/2013420924548Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
05/04/2014440141222Open ↗
10/26/2013440112334Open ↗
▸BISADDITIONAL INFORMATION2
10/19/2021421802026Open ↗
05/04/2014440141222Open ↗
▸Other Documents5
▸BISFIRE SUPP ANSUL APPROVL- FD-FSS4
03/04/2014420925921Open ↗
03/04/2014420924548Open ↗
02/13/2014420924548Open ↗
Showing 3 of 4 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
12/15/2021421802026Open ↗