| Owner | Filings | Most Recent |
|---|---|---|
| SUNLIGHT DEVELOPMENT GROUP | 10 | 09/23/2026 |
| 44-79 REALTY, LLC | 9 | 03/22/2026 |
| THE OWNER OF 2305 45 AVE | 1 | 03/22/2026 |
| HML DEVELOPMENTS | 7 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/29/2026 | $1.3M | — | 44-79 REALTY, LLC → 23RD VENTURE GROUP LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| DEFONSECA ARCHITECTS | 8 | 03/24/2026 |
| FLORINELA MURESAN | 3 | 10/02/2024 |
| RISE ARCHITECTURE | 4 | 08/23/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| H Z BUILDING NY | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JRL SKYLINE INC | General Contractor | 5 | 09/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HPL ENGINEERING PC | 5613 | 4 | 03/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Earth Work | Permit Issued | JRL SKYLINE INC | 09/21/2026 |
| DOB NOW | Support of Excavation | Permit Issued | JRL SKYLINE INC | 09/21/2026 |
| DOB NOW | Structural | Permit Issued | JRL SKYLINE INC | 09/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JRL SKYLINE INC | 09/14/2026 |
| DOB NOW | General Construction | Permit Issued | JRL SKYLINE INC | 09/14/2026 |
| DOB NOW | Construction Fence | Permit Issued | JRL SKYLINE INC | 09/01/2026 |
| BIS | OT | ISSUED | SILVERCUP SCFFLDNG I LLC | 05/14/2019 |
| BIS | EQ | ISSUED | AAA CONSTRUCTION SERVICE INC | 03/12/2004 |
| BIS | — | ISSUED | AAA CONSTRUCTION SERVICE INC | 03/12/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/02/2024 | — | — | Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems | Heat / Cool Lg ARUM048GSS5 54,000 BTU · Vrf Outdoor ×8 ARNU423M2A4 47,000 BTU · Vrf Indoor ×5 LSN240HFV3 22,000 BTU · Split System ×2 ARUM096BTE5 108,000 BTU · Vrf Outdoor ×1 Heating Marley CWH101DSAF 1 kW · Electric Heater ×5 Ventilation Energywall U-ERV-1200 800 CFM · Erv ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2024 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2024 | — | — | 1 scope_items |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/15/2026 | Air barrier — testing | — | energy_progress |
| 04/15/2026 | Maintenance information | — | energy_progress |
| 03/18/2026 | Construction Operations Influencing Adjacent Structures | Fran Huang | special |
| 03/18/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 03/18/2026 | Underpinning and alternate methods of support of buildings and adjacent property | — | special |
| 03/18/2026 | Concrete - Cast-In-Place | — | special |
| 03/18/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 03/18/2026 | Subgrade Inspections | Fran Huang | special |
| 03/18/2026 | Concrete - Cast-In-Place | Fran Huang | special |
| 03/17/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 03/17/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 03/17/2026 | Subgrade Inspections | — | special |
| 03/17/2026 | Footing and Foundation | Fran Huang | progress |
| 03/17/2026 | Final | Fran Huang | progress |
| 02/13/2026 | Metering | — | energy_progress |
| 02/13/2026 | Maintenance information | — | energy_progress |
| 01/30/2026 | Energy Code Compliance Inspections | — | progress |
| 01/30/2026 | Shutoff dampers | — | energy_progress |
| 01/30/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 01/30/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 01/30/2026 | Fire-Resistance Rated Construction | — | progress |
| 01/30/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 01/30/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 01/29/2026 | Mechanical Systems | — | special |
| 01/29/2026 | Final | — | progress |