← Back
Two stories - detached, small or mid-size
44 DOVER STREET
BROOKLYN · BIN 3245898
💬 Discuss this project
1940Year Built
2Stories
A1Building Class
R3-1Zoning
1,870 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 6,000 sf lot · 0.31 FAR built · Flood zone AE
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ISOPARM DESIGN GROUP111/04/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EA DESIGN GROUP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RANDAZZO CONSTRUCTION GROGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616111/04/2025
Building Lifecycle
All (13)Filed (1)Permit Issued (2)Violation (1)Objection (6)Special Inspection (3)
05/04/2026
Permit issued — General Construction
B01309088-I1-GC-CX
04/16/2026
Permit issued — Structural
B01309088-I1-GC-CX
11/25/2025
Objection resolved — Addressed
11/25/2025
Objection resolved — Addressed
11/25/2025
Objection resolved — Addressed
11/13/2025
Objection raised — Zoning
11/13/2025
Objection raised — Zoning
11/13/2025
Objection raised — Structural
11/04/2025
Filed — Alteration
Application filed for exterior renovation of existing garage as per plans filed herewith. No change in use, egress or occupancy.
B01309088-I1
10/28/2025
Special inspection requirement — Masonry
SHAHRIAR QUAYYUM
10/28/2025
Special inspection requirement — Structural Wood Frame
Alexander Sheyman
10/27/2025
Special inspection requirement — Final
Alexander Sheyman
07/03/2025
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedRANDAZZO CONSTRUCTION GRO05/04/2026
DOB NOWStructuralPermit IssuedRANDAZZO CONSTRUCTION GRO04/16/2026
1 project · most recent 11/04/2025
Wood
FiledStatusContractorScope
11/04/2025Permit IssuedRANDAZZO CONSTRUCTION GROWood
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
10/28/2025MasonrySHAHRIAR QUAYYUMspecial
10/28/2025Structural Wood FrameAlexander Sheymanprogress
10/27/2025FinalAlexander Sheymanprogress
▾Documents — 5 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026B01309088-I1Request digital key ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01309088-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
09/07/2026B01309088-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/07/2026B01309088-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01309088-I1Open ↗