| Owner | Filings | Most Recent |
|---|---|---|
| ACER CONSTRUCTION | 1 | 03/22/2026 |
| HABITAT ON GARFIELD 1 | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/09/2022 | $3.5M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| YANG ENGINEERING LLC | 5 | 02/17/2025 |
| JIMENEZ BUILDING CONSULTING LLC | 4 | 11/06/2024 |
| JIAN ENGINEERING PLLC | 3 | 12/05/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SD DESIGN STUDIO | 24 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LXC CONSTRUCTION INC | General Contractor | 14 | 07/08/2026 |
| ACER CONSTRUCTION INC | General Contractor | 8 | 07/08/2026 |
| DYNAMIC PLBNG & SPRKR COR | Fire Protection | 2 | 07/08/2026 |
| DYNAMIC PLBG & SPRKLR COR | Plumbing | 2 | 07/08/2026 |
| ERIC & NG ELEC'L, INC. | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WELLDONE INSPECTION INC. | 8628 | 10 | 02/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | ACER CONSTRUCTION INC | 11/12/2024 |
| DOB NOW | Plumbing | Signed-off | CITYWIDE PLBG, HTG &SPRKL | 09/04/2024 |
| DOB NOW | Sprinklers | Signed-off | CITYWIDE PLBG HTG & SPKLS | 09/04/2024 |
| DOB NOW | Construction Fence | Signed-off | ACER CONSTRUCTION INC | 05/14/2024 |
| DOB NOW | General Construction | Permit Issued | ACER CONSTRUCTION INC | 04/25/2024 |
| DOB NOW | Construction Fence | Signed-off | ACER CONSTRUCTION INC | 04/24/2024 |
| DOB NOW | General Construction | Permit Issued | LXC CONSTRUCTION INC | 04/18/2024 |
| DOB NOW | General Construction | Permit Issued | LXC CONSTRUCTION INC | 04/01/2024 |
| DOB NOW | Structural | Signed-off | LXC CONSTRUCTION INC | 09/12/2023 |
| DOB NOW | Sprinklers | Signed-off | CITYWIDE PLBG HTG & SPKLS | 08/16/2023 |
| DOB NOW | Sprinklers | Signed-off | CITYWIDE PLBG, HTG &SPRKL | 08/16/2023 |
| DOB NOW | General Construction | Permit Issued | LXC CONSTRUCTION INC | 03/03/2023 |
| DOB NOW | Construction Fence | Signed-off | LXC CONSTRUCTION INC | 03/02/2023 |
| DOB NOW | Construction Fence | Signed-off | LXC CONSTRUCTION INC | 03/02/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/17/2025 | Signed-off | ACER CONSTRUCTION INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NAMHZ-U1 48,000 BTU · Heat Pump Outdoor ×16 MXZ-SM42NAMHZ-U1 42,000 BTU · Heat Pump Outdoor ×4 PUZ-HA24NHA1 24,000 BTU · Heat Pump Outdoor ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/17/2025 | Signed-off | DYNAMIC PLBNG & SPRKR COR | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/17/2025 | Signed-off | DYNAMIC PLBG & SPRKLR COR | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/19/2025 | Complete | ERIC & NG ELEC'L, INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/17/2025 | Signed-off | ACER CONSTRUCTION INC | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/26/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/24/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/21/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/05/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 02/05/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/29/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/06/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/21/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/22/2024 | Fire-Resistant Penetrations and Joints | QIUFAN JIANG | special |
| 11/22/2024 | HVAC-R and service water piping design and insulation | QIUFAN JIANG | energy_progress |
| 11/22/2024 | Energy Code Compliance Inspections | QIUFAN JIANG | progress |
| 11/22/2024 | Sprinkler Systems | QIUFAN JIANG | special |
| 11/22/2024 | HVAC-R and service water heating equipment | QIUFAN JIANG | energy_progress |
| 11/22/2024 | HVAC-R and service water heating system controls | QIUFAN JIANG | energy_progress |
| 11/22/2024 | Maintenance information | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Fire-Resistant Penetrations and Joints | QIUFAN JIANG | special |
| 10/18/2024 | Construction Operations Influencing Adjacent Structures | QIUFAN JIANG | special |
| 10/18/2024 | Concrete - Cast-In-Place | QIUFAN JIANG | special |
| 10/18/2024 | Fenestration air leakage | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Fenestration and door U-factor and product ratings | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Interior lighting power | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Metering | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Fire-Resistance Rated Construction | QIUFAN JIANG | progress |
| 10/18/2024 | Energy Code Compliance Inspections | QIUFAN JIANG | progress |
| 10/18/2024 | Structural Stability – Alterations of existing buildings | QIUFAN JIANG | special |
| 10/18/2024 | Air barrier - visual inspection | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Maintenance information | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Insulation placement and R values | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Fenestration areas | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Lighting in dwelling units | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Lighting controls | QIUFAN JIANG | energy_progress |
| 10/18/2024 | Exterior lighting power | QIUFAN JIANG | energy_progress |
| 10/09/2024 | Sprinkler Systems | QIUFAN JIANG | special |