← Back
Bungalow colony - cooperatively owned land
44 POPLAR AVENUE
BRONX · Throgs Neck-Schuylerville · BIN 2100577
💬 Discuss this project
1921Year Built
2Stories
A8Building Class
R4AZoning
53,594 sfGross Floor Area
45Units
0 Open ViolationsFDNY Report ↗
Bungalow colony - cooperatively owned land · Owner of record: SILVER BEACH GARDENS CORP · 153,700 sf lot · 0.35 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC204/27/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272204/27/2026
Building Lifecycle
All (16)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (12)
06/15/2026
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X01374043-I1
04/28/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
04/28/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Walid Abdulla
04/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
04/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
04/28/2026
Special inspection requirement — Final
Walid Abdulla
04/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
04/27/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X01374043-P1
04/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
04/09/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Walid Abdulla
04/09/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
04/09/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
04/09/2026
Special inspection requirement — Final
Walid Abdulla
04/09/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
03/26/2026
Permit issued — Solar
X01374043-I1-SL
03/19/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X01374043-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC03/26/2026
1 project · most recent 04/09/2026
FiledStatusContractorScope
04/09/2026CompleteSUNRUN SOLAR ELECTL CORP—
1 project · most recent 04/27/2026
FiledStatusContractorScope
04/27/2026Signed-offSUNRUN INSTALLATION SVC20 panels, 9 kw, 210.2 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
04/28/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
04/28/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Walid Abdullaspecial
04/28/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
04/28/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
04/28/2026FinalWalid Abdullaprogress
04/28/2026Energy Code Compliance InspectionsWalid Abdullaprogress
04/09/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
04/09/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Walid Abdullaspecial
04/09/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
04/09/2026Energy Code Compliance InspectionsWalid Abdullaprogress
04/09/2026FinalWalid Abdullaprogress
04/09/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/16/2026X01374043-I1Request digital key ↗
08/16/2026X01374043-P1Request digital key ↗
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026X01374043-I1Open ↗
09/01/2026X01374043-I1Open ↗
09/01/2026X01374043-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/01/2026X01374043-I1Open ↗
09/01/2026X01374043-I1Open ↗
09/01/2026X01374043-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/16/2026X01374043-I1Open ↗
08/16/2026X01374043-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/16/2026X01374043-P1Open ↗
08/16/2026X01374043-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/16/2026X01374043-I1Open ↗