← Back
BuildNYC
Elevator cooperative
The Gregory House
440 EAST 79TH STREET · BIN 1046026
💬 Discuss this project
1956Year Built
16Stories
D4Building Class
R10AZoning
238,293 sfGross Floor Area
222Units
LL97 CoveredRent Stabilized26 Active Violations 20 unresolved · 6 paperwork only 1 old, status unconfirmed ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: 440 East 79th Street Owners · 22,988 sf lot · 10.37 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofRoof and pavers replacement7p · 1 filing · 14 docs
Floor 17Unit 17KL10p · 2 filings · 19 docs
Floor 16Unit 16K6p · 2 filings · 9 docs
Floor 15
Floor 14Unit 15D, Unit 15N8p · 3 filings · 18 docs
Floor 13
Floor 12Unit 12E4p · 1 filing · 3 docs
Floor 11
Floor 10
Floor 9Unit 9E, Unit 9G, Unit 9M17p · 6 filings · 20 docs
Floor 8
Floor 7Unit 7E3p · 1 filing · 3 docs
Floor 6
Floor 5
Floor 4
Floor 3Unit 3C, Unit 3J, Unit 3MUnder Construction19p · 5 filings · 20 docs
Floor 2Unit 2D, Unit 2JUnder Construction9p · 2 filings · 14 docs
Floor 1Garage concrete and masonry repairs6p · 2 filings · 12 docs
CellarB & 33rd LLC23p · 4 filings · 20 docs
Site & exteriorHeavy duty sidewalk shed installation1p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
440 East 79th St Owners5103/22/2026
440 East 71203/21/2026
Barrel404/09/2026
B & 33rd403/21/2026
79th Street Corp Impark203/21/2026
Quantum Design103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Atelier New York Architecture207/06/2026
Homone Engineering107/05/2026
Dina Vedmed Architect1405/05/2026
Howard L Zimmerman Arch & Engineering702/24/2026
EDG305/19/2025
H G Lee Architect809/12/2024
Eab Engineering210/27/2021
Shapeless Studio310/26/2021
Kossar + Garry Architects110/26/2021
Joel Phagoo P.E106/18/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Dina Vedmed Architect1203/21/2026
EDG403/21/2026
Hlzae403/21/2026
Howard L Zimmerman Architects403/21/2026
J Callahan Consulting603/21/2026
A1 Expediting Service203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Next Generation Restorationspecialty_contractor907/08/2026
Skyline Scaffolding GroupScaffold603/21/2026
Thomas MaintenanceGeneral Contractor607/08/2026
Central Construction ManagementGeneral Contractor408/26/2026
Sin Do ConstructionGeneral Contractor303/21/2026
L & Z ConsultingGeneral Contractor204/09/2026
Yates Exterior Restorationspecialty_contractor210/14/2026
Colgate Restorationspecialty_contractor203/21/2026
Empire PlumbingPlumbing207/08/2026
Eagle Contractors NYGeneral Contractor203/21/2026
CSC RenoGeneral Contractor107/08/2026
Kurti ConstructionGeneral Contractor104/09/2026
MTK ConstructionGeneral Contractor107/08/2026
Adriano Plumbing & HeatingPlumbing108/26/2026
Adriatic Plumbing & HeatingPlumbing107/08/2026
Amm General ContractingPlumbing107/08/2026
Crossfield Plumbing & HeatingPlumbing107/08/2026
Delta-Sigma MechanicalPlumbing107/08/2026
I Do Plumbing & HeatingPlumbing107/08/2026
Daven ElectricElectrical103/22/2026
M.A.C. PlumbingPlumbing107/08/2026
Robert Garcia Electrical ContElectrical103/21/2026
Falco Electrical ServicesElectrical103/21/2026
Silverescent Sign CoElectrical103/21/2026
Ajf ElectricElectrical103/21/2026
John H. MooreElectrical103/21/2026
Schondorf MichaelElectrical103/21/2026
Unity Electric CoElectrical103/21/2026
Angelo LelcajGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Atelier NY Architecture2438207/06/2026
Z & T Engineering591107/05/2026
Chanda Engineering Consultant6842205/05/2026
Howard L Zimmerman Architects17121202/24/2026
EDG2578105/19/2025
HG Lee Architect2554809/12/2024
Green River Environmental7841109/09/2024
Avt Engineering345101/21/2021
Building Lifecycle
All (223)Filed (42)Permit Issued (34)Signed Off (19)Facade (FISP) (12)Violation (60)Inspection (14)Objection (12)Special Inspection (30)
10/13/2026
Permit issued — Structural
M01419245-S2-ST
10/13/2026
Permit issued — General Construction
M01419245-I1-GC
08/12/2026
Permit issued — Structural
M01419245-S2-ST
08/06/2026
Permit issued — Plumbing
M01419245-S1-PL
07/13/2026
Permit issued — General Construction
M01419245-I1-GC
07/06/2026
Filed — Alteration
PLUMBING WORK IN APT 2J AND 3J AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M01419245-S1
07/05/2026
Filed — Alteration
PLUMBING WORK IN APT 2J AND 3J AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M01419245-S2
07/01/2026
Filed — Alteration
PLUMBING WORK IN APT 2J AND 3J AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M01419245-I1
06/18/2026
Special inspection requirement — Tenant Protection Plan Compliance
Kenneth Hudes
05/05/2026
Filed — Alteration
M01376454-I1
05/05/2026
Filed — Alteration
M01376447-I1
03/30/2026
Special inspection requirement — Lighting in dwelling units
Dina Vedmed
03/26/2026
Violation issued (ECB, open)
Construction
03/26/2026
Violation issued (ECB, open)
Construction
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
Dina Vedmed
03/23/2026
Special inspection requirement — Final
Dina Vedmed
03/23/2026
Special inspection requirement — Energy Code Compliance Inspections
Dina Vedmed
02/26/2026
Signed off — Alteration
PROPOSED TEMPORARY SHORING INSTALLATION AS PER PLANS SUBMITTED HEREWITH. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00993601-I1
02/25/2026
Signed off — Alteration
GARAGE REPAIRS: CONCRETE REPAIRS WITH POLIMER-MODIFIED PATCHING MATERIAL & MISCELLANEOUS MASONRY REPAIRS. NO CHANGE IN USE, EGRESS OR OCCUPANCY,
M01149427-I1
02/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jon Colatrella
02/25/2026
Special inspection requirement — Tenant Protection Plan Compliance
02/25/2026
Special inspection requirement — Post-installed Anchors
Jon Colatrella
02/24/2026
Filed — Alteration
REPLACEMENT OF FLOOR DRAINS AND ASSOCIATED PIPING AT GARAGE CELLAR LEVEL. FLOOD MITIGATION AND PIPING UPGRADES FOR THE EAST AND WEST SIDE OF THE BUILDING AT CELLAR LEVEL. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. GC FILING #M01149427.
M01275660-P1
02/24/2026
Special inspection requirement — Post-installed Anchors
Jon Colatrella
02/24/2026
Special inspection requirement — Tenant Protection Plan Compliance
02/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jon Colatrella
12/09/2025
Signed off — Alteration
M01212224-I1
12/09/2025
Signed off — Alteration
M01287363-I1
10/24/2025
Violation issued (ECB, closed)
Construction
10/24/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/23/2025
Violation issued (ECB, closed)
Construction
10/23/2025
Violation issued (ECB, closed)
Construction
09/30/2025
Violation issued (HPD, closed)
A
09/30/2025
Violation issued (HPD, closed)
B
09/29/2025
Signed off — Alteration
RENOVATE EXISTING APARTMENT; PARTITIONS, FLOORING, CABINETRY, COUNTER, DOORS, FIXTURES & FINISHES. NO CHANGE IN USE,EGRESS OR OCCUPANCY
M01051272-I1
09/24/2025
Permit issued — General Construction
M01287363-I1-GC
09/18/2025
Filed — Alteration
M01287363-I1
09/18/2025
Violation issued (HPD, open)
C
09/18/2025
Violation issued (HPD, open)
A
09/18/2025
Violation issued (HPD, open)
A
09/18/2025
Violation issued (HPD, open)
A
09/18/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/10/2025
Permit issued — Plumbing
M01275660-I1-PL
08/27/2025
Filed — Alteration
REPLACEMENT OF FLOOR DRAINS AND ASSOCIATED PIPING AT GARAGE CELLAR LEVEL. FLOOD MITIGATION AND PIPING UPGRADES FOR THE EAST AND WEST SIDE OF THE BUILDING AT CELLAR LEVEL. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. GC FILING #M01149427.
M01275660-I1
07/24/2025
Permit issued — Structural
M00993601-I1-ST
06/16/2025
Signed off — Alteration
M01102953-I1
05/20/2025
Special inspection requirement — Final
Howard Zimmerman
05/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Howard Zimmerman
05/20/2025
Special inspection requirement — Tenant Protection Plan Compliance
Howard Zimmerman
05/19/2025
Filed — Alteration
PROPOSED TEMPORARY SHORING INSTALLATION AS PER PLANS SUBMITTED HEREWITH. THERE IS NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00993601-P1
05/13/2025
Special inspection requirement — Final
Anthony Stasio
05/13/2025
Special inspection requirement — Tenant Protection Plan Compliance
ROBERT MASONE
05/13/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Anthony Stasio
05/13/2025
Special inspection requirement — Tenant Protection Plan Compliance
05/13/2025
Special inspection requirement — Final
Anthony Stasio
05/12/2025
Filed — Alteration
M01102953-P1
04/30/2025
Permit issued — General Construction
M01149427-I1-GC
04/24/2025
Permit issued — General Construction
M01212224-I1-GC
04/22/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
Latest 60 of 223 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedYates Exterior Restoration10/13/2026
DOB NOWGeneral ConstructionPermit IssuedYates Exterior Restoration10/13/2026
DOB NOWStructuralPermit IssuedCentral Construction Management08/12/2026
DOB NOWPlumbingPermit IssuedAdriano Plumbing & Heating08/06/2026
DOB NOWGeneral ConstructionPermit IssuedCentral Construction Management07/13/2026
DOB NOWGeneral ConstructionSigned-offKurti Construction09/24/2025
DOB NOWPlumbingPermit IssuedAdriatic Plumbing & Heating09/10/2025
DOB NOWStructuralSigned-offL & Z Consulting07/24/2025
DOB NOWGeneral ConstructionSigned-offL & Z Consulting04/30/2025
DOB NOWGeneral ConstructionSigned-offAngelo Lelcaj04/24/2025
DOB NOWStructuralSigned-offThomas Maintenance03/24/2025
DOB NOWStructuralSigned-offThomas Maintenance10/22/2024
DOB NOWStructuralSigned-offThomas Maintenance10/03/2024
DOB NOWGeneral ConstructionSigned-offNext Generation Restoration06/04/2024
DOB NOWPlumbingSigned-offI Do Plumbing & Heating05/13/2024
DOB NOWStructuralSigned-offThomas Maintenance03/26/2024
DOB NOWPlumbingSigned-offAmm General Contracting02/13/2024
DOB NOWGeneral ConstructionSigned-offNext Generation Restoration02/09/2024
DOB NOWGeneral ConstructionSigned-offSin Do Construction09/08/2023
DOB NOWGeneral ConstructionSigned-offColgate Restoration11/25/2022
DOB NOWGeneral ConstructionSigned-offNext Generation Restoration09/07/2022
DOB NOWPlumbingSigned-offDelta-Sigma Mechanical06/22/2022
DOB NOWGeneral ConstructionSigned-offMTK Construction06/15/2022
DOB NOWGeneral ConstructionSigned-offNext Generation Restoration05/16/2022
DOB NOWPlumbingPermit IssuedEmpire Plumbing02/03/2022
DOB NOWGeneral ConstructionSigned-offNext Generation Restoration01/26/2022
DOB NOWPlumbingSigned-offM.A.C. Plumbing11/23/2021
DOB NOWGeneral ConstructionPermit IssuedEagle Contractors NY11/18/2021
DOB NOWGeneral ConstructionSigned-offCentral Construction Management11/01/2021
DOB NOWSidewalk ShedSigned-offSkyline Scaffolding Group05/10/2021
DOB NOWGeneral ConstructionSigned-offCSC Reno04/29/2021
DOB NOWPlumbingSigned-offCrossfield Plumbing & Heating02/25/2021
DOB NOWPlumbingSigned-offEmpire Plumbing12/03/2020
DOB NOWSidewalk ShedSigned-offSkyline Scaffolding Group06/18/2020
BISOTISSUEDColgate Restoration03/11/2022
BISOTISSUEDColgate Restoration03/12/2021
BISPLISSUEDGenesis Plumbing and Heating01/13/2021
BISOTISSUEDNext Generation Restoration11/28/2020
BISOTISSUEDColgate Restoration09/17/2020
BISPLISSUEDNew York Standard Mechanical02/20/2020
+ 44 more permits on file
4 projects · most recent 07/06/2026
Water/Sanitary Gas
FiledStatusContractorScope
07/06/2026Permit IssuedAdriano Plumbing & HeatingGas, Water/Sanitary
02/24/2026Permit IssuedAdriatic Plumbing & HeatingWater/Sanitary
01/30/2024Signed-offAmm General ContractingGas, Water/Sanitary
10/27/2022Permit IssuedEmpire PlumbingWater/Sanitary
14 projects · most recent 08/05/2026
General Wiring
FiledStatusContractorScope
08/05/2026Permit IssuedApproved ElectricGeneral Wiring
05/16/2025CompleteDaven Electric—
05/12/2025CompleteGia ElectricalGeneral Wiring
09/17/2024CompleteGlendale Electl Contng—
06/18/2024Permit IssuedEmpire Lic Electrical ContractorsGeneral Wiring
12/12/2022CompletePro ElectricGeneral Wiring
07/18/2022CompleteMLS ElectricGeneral Wiring
11/18/2021CompleteEverest Electrical ContractingGeneral Wiring
10/28/2021CompleteApproved ElectricGeneral Wiring
06/09/2020CompleteTop Shelf Electric—
11/21/2019CompleteCSM Electric—
10/28/2019Permit IssuedA&E Electrical Systems Co1 meters, 1 new_meters
09/20/2019CompleteLeone Electric CoGeneral Wiring
07/02/2019Permit IssuedSpiro ElectricGeneral Wiring
1 project · most recent 07/06/2026
Steel
FiledStatusContractorScope
07/06/2026Permit IssuedYates Exterior RestorationSteel
1 project · most recent 02/24/2026
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
02/24/2026Permit IssuedAdriatic Plumbing & HeatingTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 14
DateTypeResultReport
09/18/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/22/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/15/2024Pass-Final General Construction Non-Directive 14PassView ↗
09/24/2024Fail-Final General Construction Non-Directive 14FailView ↗
09/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/03/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
05/30/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/28/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/19/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/20/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/20/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/08/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/31/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 61
DateRequirementInspectorRole
06/18/2026Tenant Protection Plan ComplianceKenneth Hudesspecial
03/30/2026Lighting in dwelling unitsDina Vedmedenergy_progress
03/26/2026Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
03/26/2026Energy Code Compliance InspectionsDina Vedmedprogress
03/23/2026FinalDina Vedmedprogress
03/23/2026Energy Code Compliance InspectionsDina Vedmedprogress
02/25/2026Fire-Resistant Penetrations and JointsJon Colatrellaspecial
02/25/2026Tenant Protection Plan Compliance—special
02/25/2026Post-installed AnchorsJon Colatrellaspecial
02/24/2026Tenant Protection Plan Compliance—special
02/24/2026Fire-Resistant Penetrations and JointsJon Colatrellaspecial
02/24/2026Post-installed AnchorsJon Colatrellaspecial
05/20/2025Structural Stability – Alterations of existing buildingsHoward Zimmermanspecial
05/20/2025Tenant Protection Plan ComplianceHoward Zimmermanspecial
05/20/2025FinalHoward Zimmermanprogress
05/13/2025Tenant Protection Plan Compliance—special
05/13/2025FinalAnthony Stasioprogress
05/13/2025Tenant Protection Plan ComplianceROBERT MASONEspecial
05/13/2025Structural Stability – Alterations of existing buildingsAnthony Stasiospecial
05/13/2025FinalAnthony Stasioprogress
04/22/2025FinalAnthony Stasioprogress
04/22/2025Tenant Protection Plan Compliance—special
09/18/2024Fire-Resistance Rated ConstructionHe Gin Leeprogress
09/18/2024Fire-Resistant Penetrations and JointsHe Gin Leespecial
09/18/2024Interior lighting powerHe Gin Leeenergy_progress
Latest 25 of 61.
▾Documents — 544 on file (BIS + DOB NOW)
▸Plans & Drawings42
▸DOB NOWPlans/Sketch37
09/03/2026M00616480-I1Request digital key ↗
09/03/2026M00594603-I1Request digital key ↗
09/03/2026M00654475-I1Request digital key ↗
Showing 3 of 37 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
09/04/2026M00423740-I1Request digital key ↗
09/04/2026M00436493-I1Request digital key ↗
08/15/2026M00436493-P2Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/15/2026M00448040-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00356028-I1Request digital key ↗
▸Applications & Permits77
▸BISPLAN / WORK APPROVAL APPLICATION39
08/26/2025123895008Open ↗
01/28/2022123690862Open ↗
12/03/2020104164413Open ↗
Showing 3 of 39 on file for this type
▸BISWORK PERMIT APPLICATION38
11/28/2020140981061Open ↗
09/17/2020123690862Open ↗
02/21/2020122482919Open ↗
Showing 3 of 38 on file for this type
▸Seals & Professional Certifications150
▸DOB NOWDPL-1: Design Professional Seal & Signature42
09/04/2026M00356028-I1Open ↗
09/04/2026M00436493-P2Open ↗
09/04/2026M00436493-I1Open ↗
Showing 3 of 42 on file for this type
▸DOB NOWProgress Inspector Seal & Signature34
09/30/2026M00448040-I1Open ↗
09/30/2026M00448040-I1Open ↗
09/30/2026M00448040-I1Open ↗
Showing 3 of 34 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION32
05/27/2020102737549Open ↗
03/30/2020122482919Open ↗
03/30/2020122482919Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/30/2026M00448040-I1Open ↗
09/02/2026M00747353-I1Open ↗
09/02/2026M08012442-P1Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
11/24/2020140981061Open ↗
05/27/2020140905153Open ↗
12/12/2019140879681Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
06/23/2017121232175Open ↗
Showing 1 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
11/24/2020140981061Open ↗
05/27/2020140905153Open ↗
12/12/2019140879681Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
05/27/2020140905153Open ↗
12/12/2019140879681Open ↗
Showing 2 of 3 on file for this type
▸Trade Schedules & Equipment25
▸BISSELF-CERT PLUMBING NOTICE8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
02/18/2020122482919Open ↗
11/07/2019122482919Open ↗
05/28/2019123895008Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE B - PLUMBING6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISBOILERS - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection11
▸BISTenant Protection Plan and Notes7
09/09/2019123690862Open ↗
05/28/2019123895008Open ↗
03/29/2019122607303Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWTenant Protection Plan2
09/04/2026M00356028-I1Open ↗
08/13/2026M00423740-I1Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
04/30/2021140981061Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
09/09/2019123690862Open ↗
▸Environmental & Asbestos53
▸DOB NOWDEP ACP-5: Asbestos Assessment Report32
09/04/2026M00436493-I1Open ↗
09/04/2026M00436493-P2Open ↗
09/03/2026M00616480-I1Open ↗
Showing 3 of 32 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)12
11/24/2020140981061Open ↗
12/12/2019140879681Open ↗
05/28/2019123895008Open ↗
Showing 3 of 12 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
03/18/2022123690862Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
09/02/2026M00786633-I1Open ↗
▸Energy Compliance46
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS17
03/30/2020122482919Open ↗
03/30/2020122482919Open ↗
02/12/2020140879681Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY10
03/18/2022123690862Open ↗
02/08/2022123690862Open ↗
07/06/2021140981061Open ↗
Showing 3 of 10 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
03/18/2022123690862Open ↗
07/06/2021140981061Open ↗
03/30/2020122482919Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWEN2: As Built Energy Analysis6
09/02/2026M00747085-I1Open ↗
08/13/2026M00786633-I1Open ↗
08/13/2026M00796120-I1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
12/12/2019140879681Open ↗
Showing 1 of 2 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports16
▸BISTECHNICAL REPORT: RESPONSIBILITY15
09/08/2025123895008Open ↗
09/04/2025123895008Open ↗
08/25/2025123895008Open ↗
Showing 3 of 15 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
05/27/2020102737549Open ↗
▸Approvals, Objections & Sign-offs32
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST17
09/09/2025123895008Open ↗
03/25/2022123690862Open ↗
07/06/2021140981061Open ↗
Showing 3 of 17 on file for this type
▸BISADMINISTRATIVE OBJECTIONS7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
05/28/2020102737549Open ↗
01/23/2020122482919Open ↗
02/23/2018121232175Open ↗
Showing 3 of 5 on file for this type
▸BISSUPERSEDING LETTER2
02/21/2020122482919Open ↗
11/20/2019123895008Open ↗
▸BISThird Party Electrical Signoff Compliance Report1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership36
▸BISCOST AFFIDAVIT34
09/08/2025123895008Open ↗
08/25/2025123895008Open ↗
03/18/2022123690862Open ↗
Showing 3 of 34 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT2
11/28/2020140981061Open ↗
09/09/2020123690862Open ↗
▸Filing & Intake Forms43
▸BISBOROUGH INTAKE FORM16
05/27/2020102737549Open ↗
03/30/2020122482919Open ↗
02/18/2020122482919Open ↗
Showing 3 of 16 on file for this type
▸BISEFILING COVER SHEET12
09/09/2019123690862Open ↗
05/28/2019123895008Open ↗
05/28/2019123895008Open ↗
Showing 3 of 12 on file for this type
▸BISADDITIONAL INFORMATION11
02/09/2022123690862Open ↗
05/07/2020102737549Open ↗
11/13/2019122482919Open ↗
Showing 3 of 11 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
11/24/2020140981061Open ↗
05/27/2020140905153Open ↗
12/12/2019140879681Open ↗
Showing 3 of 4 on file for this type
▸Other Documents13
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWDHCR Document4
08/13/2026M00436493-P2Open ↗
08/13/2026M00448040-I1Open ↗
08/13/2026M00436493-P2Open ↗
Showing 3 of 4 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDHCR DOCUMENT1
05/27/2020140905153Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
09/17/2020123690862Open ↗