| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/20/2026 | — | — | Water/Sanitary |
| 10/21/2025 | Signed-off | HYDROKINETIC PLBG & HTG I | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/22/2026 | Permit Issued | KET ELECTRIC LLC | General Wiring |
| 02/14/2025 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 03/07/2024 | Complete | CRESCO ELECTRICAL CORP | General Wiring |
| 01/22/2024 | Complete | EVS ELECTRIC CORP | General Wiring |
| 07/31/2023 | Complete | CRESCO ELECTRICAL CORP | General Wiring |
| 05/17/2023 | Permit Issued | QEC ELECTRICAL SVCE CORP | General Wiring |
| 10/06/2022 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 09/29/2022 | Permit Issued | LENS ELECTRIC, INC | General Wiring |
| 03/23/2022 | Permit Issued | J Y ELECTRIC INC | General Wiring |
| 02/06/2022 | Complete | TEMPEST ELEC'L CONTRG, IN | General Wiring |
| 05/28/2021 | Complete | GEMINI ELECTRIC CO., INC. | General Wiring |
| 04/26/2021 | Complete | MARTIN DORKIN | General Wiring |
| 10/28/2020 | Permit Issued | POWERONE ELECT'L CONTRG | 20 meters, 1 new_meters |
| 07/31/2020 | Complete | CAMPISANO ELECTRIC INC | General Wiring |
| 11/13/2019 | Cancelled | TEMPEST ELEC'L CONTRG, IN | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/06/2018 | Permit Issued | KINGS GROUP NY CORP | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/04/2024 | Permit Issued | — | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| DOUGLAS ELLIMAN | 30 | 07/08/2026 |
| NITRA INVESTORS | 25 | 07/08/2026 |
| KINGS GROUP NY | 8 | 07/08/2026 |
| 444 CENTRAL PARK WEST OWNER S | 37 | 03/22/2026 |
| KAY WATERPROFING CORP | 3 | 03/22/2026 |
| 444 CENTRAL PARK OWNERS | 32 | 03/22/2026 |
| HNS CONSTRUCTION | 8 | 03/22/2026 |
| RON GUPTA/444 CENTRAL PAR | 1 | 03/22/2026 |
| HEIGHTS CONSTRUCTION | 1 | 03/22/2026 |
| ELTECH INDUSTRIES | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DIVERSIFIED DESIGN ASSOCIATES-ARCHI | 4 | 07/20/2026 |
| CORNACCHIA ARCHITECTS & PLANNERS | 2 | 04/08/2026 |
| KRISTIN LUKS ARCHITECTURE, PLLC | 2 | 10/21/2025 |
| AM ARCHITECT P.C. | 2 | 05/15/2025 |
| HIGH LINE ENGINEERING PC | 2 | 11/03/2023 |
| COUGHLIN ARCHITECTURE PLLC | 2 | 07/06/2023 |
| ROBERT YOUNG ARCHITECTS | 3 | 02/01/2023 |
| PS ENGINEERS, INC. | 1 | 11/30/2022 |
| JOSEPH KOELBEL ARCHITECT | 2 | 11/18/2022 |
| ASHRAF CORP | 2 | 10/01/2022 |
| JONG HAE CHANG ARCHITECT | 1 | 09/14/2022 |
| WALTER B. MELVIN ARCHITECTS, LLC | 1 | 08/24/2022 |
| B4 ARCHITECTURE LLC | 1 | 07/20/2021 |
| GIRANDOLA & SHUTKIND | 2 | 07/22/2020 |
| ROYAL ENGINEERING, P.C | 1 | 03/06/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AM EXPEDITING | 3 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 2 | 03/21/2026 |
| PS ENGINEERS | 4 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 2 | 03/21/2026 |
| GREEN LIGHT EXPEDITING LLC | 6 | 03/21/2026 |
| JM ZONING, LLC. | 2 | 03/21/2026 |
| QUICK FILING OF NY INC | 2 | 03/21/2026 |
| EA DESIGN GROUP | 2 | 03/21/2026 |
| A K EXPEDITING | 4 | 03/21/2026 |
| BOYD CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDAMIO SCAFFOLDING LLC | General Contractor | 7 | 07/08/2026 |
| KINGS GROUP NY CORP | General Contractor | 7 | 07/08/2026 |
| EV HOME RENOVATIONS CORP | General Contractor | 7 | 07/08/2026 |
| MASPETH CONTRACTING CORP | General Contractor | 5 | 07/08/2026 |
| ALKLEM PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| PROCORE MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| KOSTANDINOS TSOUKANTAS | Electrical | 1 | 03/21/2026 |
| MARTIN DORKIN | Electrical | 1 | 03/22/2026 |
| METROPOLITAN OPERA ASSOCI | Electrical | 1 | 03/21/2026 |
| NYC DISTRICT COUNCIL OF C | Electrical | 1 | 03/21/2026 |
| PETROF, PETRE | Electrical | 1 | 03/21/2026 |
| ROLAND EDWARDS | Electrical | 1 | 03/21/2026 |
| SKOWRONSKI JEFF | Electrical | 1 | 03/21/2026 |
| STAN ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| TEMPEST ELEC'L CONTRG, IN | Electrical | 1 | 03/22/2026 |
| ARTA CONSTRUCTION & RENOV | General Contractor | 1 | 07/08/2026 |
| FILIP HOME IMPR CONTR INC | General Contractor | 1 | 04/09/2026 |
| FILIP PJETERGJOKA | General Contractor | 1 | 03/21/2026 |
| GROVE STREET BUILDERS LLC | General Contractor | 1 | 04/09/2026 |
| LOWER EAST SIDE CONST INC | General Contractor | 1 | 04/09/2026 |
| STARCOM CONSTRUCTION CO | General Contractor | 1 | 09/09/2026 |
| THAMES BUILDERS INC | General Contractor | 1 | 07/08/2026 |
| TROTH CONTRACTING INC | General Contractor | 1 | 07/08/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 1 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DIVERSIFIED DESIGN ASSOCI | 3403 | 3 | 07/20/2026 |
| WINTON GROUP ARCHITECTURE | 4343 | 2 | 10/21/2025 |
| HIGH LINE ENGINEERING PC | 2920 | 2 | 11/03/2023 |
| RYAN SPECIAL ENGINEERING | 2018 | 1 | 07/06/2023 |
| AR CONSULTING ENGINEER P. | 4054 | 1 | 11/30/2022 |
| JOSEPH KOELBEL ARCHITECT | 3677 | 1 | 11/18/2022 |
| JONG HAE CHANG ARCHITECT | 6169 | 1 | 09/14/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | STARCOM CONSTRUCTION CO | 09/08/2026 |
| DOB NOW | Plumbing | Signed-off | HYDROKINETIC PLBG & HTG I | 01/23/2026 |
| DOB NOW | General Construction | Signed-off | GROVE STREET BUILDERS | 01/20/2026 |
| DOB NOW | General Construction | Signed-off | FILIP HOME IMPR CONTR INC | 12/11/2025 |
| DOB NOW | Plumbing | Signed-off | RJ BRUNO INC | 06/11/2025 |
| DOB NOW | General Construction | Signed-off | JD WINDOW CLEA & CONST CO | 06/11/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | SPD CONSTRUCTION CORP | 04/09/2024 |
| DOB NOW | Mechanical Systems | Signed-off | EV HOME RENOVATIONS | 12/26/2023 |
| DOB NOW | General Construction | Permit Issued | MASPETH CONTRACTING CORP | 11/21/2023 |
| DOB NOW | General Construction | Signed-off | EV HOME RENOVATIONS | 11/08/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 10/02/2023 |
| DOB NOW | Plumbing | Signed-off | PROCORE MECHANICAL CORP | 07/26/2023 |
| DOB NOW | General Construction | Signed-off | EV HOME RENOVATIONS | 07/13/2023 |
| DOB NOW | General Construction | Signed-off | ARTA CONSTRUCTION & RENOV | 05/02/2023 |
| DOB NOW | Plumbing | Signed-off | PROCORE MECHANICAL CORP | 01/03/2023 |
| DOB NOW | Mechanical Systems | Signed-off | EV HOME RENOVATIONS | 12/29/2022 |
| DOB NOW | General Construction | Signed-off | EV HOME RENOVATIONS | 12/07/2022 |
| DOB NOW | Supported Scaffold | Signed-off | MASPETH CONTRACTING CORP | 12/01/2022 |
| DOB NOW | General Construction | Permit Issued | MASPETH CONTRACTING CORP | 11/23/2022 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 10/03/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 10/03/2022 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 08/30/2022 |
| DOB NOW | General Construction | Signed-off | THAMES BUILDERS INC | 08/29/2022 |
| DOB NOW | Plumbing | Signed-off | ORBIT PLBG & HTG INC | 03/23/2022 |
| DOB NOW | General Construction | Signed-off | TROTH CONTRACTING INC | 03/16/2022 |
| DOB NOW | Plumbing | Signed-off | ALKLEM PLUMBING INC | 11/24/2020 |
| DOB NOW | Plumbing | Signed-off | ALKLEM PLUMBING INC | 07/17/2020 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 09/30/2019 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 10/02/2018 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 03/06/2018 |
| BIS | OT | ISSUED | STARCOM CONSTRUCTION CO | 09/04/2025 |
| BIS | OT | ISSUED | TROTH CONTRACTING INC | 01/23/2025 |
| BIS | OT | ISSUED | TROTH CONTRACTING INC | 12/07/2023 |
| BIS | OT | ISSUED | TROTH CONTRACTING INC | 12/09/2022 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 08/25/2022 |
| BIS | OT | ISSUED | TROTH CONTRACTING INC | 12/04/2021 |
| BIS | OT | ISSUED | MASPETH CONTRACTING CORP | 08/05/2020 |
| BIS | OT | ISSUED | GIRANDOLA & SHUTKING CONS | 06/24/2020 |
| BIS | OT | ISSUED | TROTH CONTRACTING INC | 05/14/2020 |
| BIS | PL | ISSUED | JODOM MECHANICAL, INC | 06/07/2019 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/31/2025 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 12/31/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 07/16/2025 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 07/16/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 07/15/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 03/14/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/14/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/21/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/25/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/02/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/14/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/01/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/22/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/20/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/11/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/07/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/12/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/08/2026 | Final | JOSEPH CORNACCHIA, AIA | progress |
| 03/18/2026 | Final | JOSEPH CORNACCHIA, AIA | progress |
| 10/16/2025 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 03/07/2025 | Final | Altagracia Martinez | progress |
| 11/29/2022 | Energy Code Compliance Inspections | Ruslan Nagorny | progress |
| 11/29/2022 | Fire-Resistant Penetrations and Joints | Ruslan Nagorny | special |
| 11/18/2022 | Insulation placement and R values | Joseph Koelbel | energy_progress |
| 11/18/2022 | Air barrier - visual inspection | Joseph Koelbel | energy_progress |
| 11/18/2022 | Fenestration and door U-factor and product ratings | Joseph Koelbel | energy_progress |
| 11/18/2022 | Maintenance information | Joseph Koelbel | energy_progress |
| 11/18/2022 | Lighting in dwelling units | Joseph Koelbel | energy_progress |
| 11/18/2022 | Metering | Joseph Koelbel | energy_progress |
| 11/18/2022 | Permanent certificate | Joseph Koelbel | energy_progress |
| 11/18/2022 | Post-installed Anchors | Joseph Koelbel | special |
| 11/18/2022 | Energy Code Compliance Inspections | Joseph Koelbel | progress |
| 11/18/2022 | Fire-Resistance Rated Construction | Joseph Koelbel | progress |
| 11/18/2022 | Fire-Resistant Penetrations and Joints | Joseph Koelbel | special |
| 11/09/2022 | Mechanical Systems | Ruslan Nagorny | special |
| 11/09/2022 | Final | Joseph Koelbel | progress |
| 11/09/2022 | Final | Ruslan Nagorny | progress |
| 09/14/2022 | Lighting in dwelling units | Jong Hae Kim | energy_progress |
| 07/08/2022 | Energy Code Compliance Inspections | ROBERT YOUNG | progress |
| 07/08/2022 | Final | ROBERT YOUNG | progress |
| 07/08/2022 | Lighting in dwelling units | ROBERT YOUNG | energy_progress |
| 04/20/2022 | Energy Code Compliance Inspections | Jong Hae Kim | progress |