Over six families without stores
Lott Legacy Apartments
441 EAST 116 STREET · East Harlem (North) · BIN 1053082
💬 Discuss this project
1910Year Built
6Stories
C1Building Class
R7BZoning
25,006 sfGross Floor Area
30Units
LL97 CoveredRent Stabilized42 Open Violations 41 unresolved · 1 paperwork only ▸FISP: UNSAFE
Over six families without stores · Owner of record: LOTT LEGACY APARTMENTS HOUSING DEVELOPME NT FUND · 5,752 sf lot · 4.35 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralEquipmentGeneral
Permit Issued — active, not yet Signed-off
Site & exteriorUnder Construction17p · 3 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
LOTT COMMUNITY DEVELOPMENT803/21/2026
PARK CONTRACTING GROUP607/31/2026
RENNON CONSTRUCTION503/22/2026
SAN FRANCISCO ASSOCIATES LP403/21/2026
SFDS DEVELOPMENT403/21/2026
GURNOOR CONSTRUCTION309/12/2026
CONCORD MANAGEMENT209/01/2026
PARSONS CONSTRUCTION203/21/2026
LOTT LEGACY APARTMENTS HOUSING DEVELOPME NT FUND103/22/2026
HPD103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
S&J Engineers PLLC207/27/2026
MERRITT ENGINEERING CONSULTANTS, DPC107/27/2026
MSM ENGINEERING SERVICES, PLLC104/15/2025
LIGHT HOUSE110/10/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CB EXPEDITING103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PARK CONTRACTING GROUPGeneral Contractor307/31/2026
RENNON CONSTRUCTION CORPGeneral Contractor203/21/2026
RICHARD NEUElectrical103/21/2026
GURNOOR CONSTRUCTION CORPGeneral Contractor108/16/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MERRITT ENGINEERING CONSU460107/27/2026
MOMENTUM DESIGN CONSULTAN9893107/27/2026
Building Lifecycle
All (99)Filed (5)Permit Issued (7)Signed Off (2)Facade (FISP) (18)Violation (60)Inspection (7)
08/14/2026
Permit issued — General Construction
M01429269-I1-GC
08/07/2026
Violation issued (HPD, open)
A
08/07/2026
Violation issued (HPD, open)
A
07/30/2026
Permit issued — Sidewalk Shed
M01210717-I1-SH
07/27/2026
Filed — Alteration
FACADE RESTORATION INCLUDING MORTAR JOINT REPOINTING, CONCRETE REPAIR, MASONRY, WINDOW SILL, SEALANT, LINTEL AND TERRA COTTA REPLACMENT. NO CHANG EIN USE, OCCUPANCY OR EGRESS.
M01429269-I1
07/27/2026
Filed — Alteration
Suspended scaffold in order to perform exterior facade repairs and periodic inspections. Inspections to be conducted by EOR. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.
M01435237-I1
07/27/2026
Permit issued — Suspended Scaffold
M01435237-I1-SC
07/24/2026
Signed off — Alteration
Suspended scaffold in order to perform exterior facade repairs and periodic inspections. Inspections to be conducted by EOR. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.
M01430397-I1
07/15/2026
Permit issued — Suspended Scaffold
M01430397-I1-SC
07/15/2026
Violation issued (ECB, closed)
Elevators
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
B
07/14/2026
Filed — Alteration
Suspended scaffold in order to perform exterior facade repairs and periodic inspections. Inspections to be conducted by EOR. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.
M01430397-I1
04/21/2026
Permit issued — Sidewalk Shed
M01210717-I1-SH
04/20/2026
Violation issued (ECB, open)
Local Law
03/17/2026
Cycle 9 facade report submitted
03/17/2026
Cycle 9 facade report signed — UNSAFE
03/05/2026
Cycle 9 facade inspection completed
02/24/2026
Violation issued (HPD, open)
C
02/24/2026
Violation issued (HPD, closed)
B
02/24/2026
Violation issued (HPD, closed)
B
02/16/2026
Violation issued (HPD, open)
C
02/16/2026
Violation issued (HPD, open)
A
02/16/2026
Violation issued (HPD, open)
C
01/12/2026
Violation issued (ECB, closed)
Elevators
01/12/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/12/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
01/12/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/08/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
11/12/2025
Violation issued (HPD, closed)
C
11/12/2025
Violation issued (HPD, closed)
C
11/12/2025
Violation issued (HPD, closed)
B
06/25/2025
Violation issued (ECB, closed)
Elevators
05/30/2025
Violation issued (HPD, closed)
C
05/30/2025
Violation issued (HPD, closed)
B
05/30/2025
Violation issued (HPD, closed)
A
05/30/2025
Violation issued (HPD, closed)
C
05/30/2025
Violation issued (HPD, closed)
A
05/30/2025
Violation issued (HPD, closed)
A
05/30/2025
Violation issued (HPD, closed)
B
05/30/2025
Violation issued (HPD, closed)
B
05/30/2025
Violation issued (HPD, closed)
B
04/17/2025
Permit issued — Sidewalk Shed
M01210717-I1-SH
04/17/2025
Violation issued (ECB, open)
Elevators
04/15/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01210717-I1
02/28/2025
Violation issued (HPD, closed)
B
02/28/2025
Violation issued (HPD, closed)
B
02/20/2025
Cycle 9 facade report submitted
02/19/2025
Cycle 9 facade report signed — UNSAFE
02/03/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
02/03/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/21/2025
Cycle 9 facade inspection completed
01/06/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/19/2024
Violation issued (ECB, open)
Construction
12/19/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/15/2024
Violation issued (HPD, closed)
C
06/10/2024
Violation issued (HPD, open)
B
06/10/2024
Violation issued (HPD, closed)
B
Latest 60 of 99 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedGURNOOR CONSTRUCTION CORP08/14/2026
DOB NOWSidewalk ShedPermit IssuedPARK CONTRACTING GROUP07/30/2026
DOB NOWSuspended ScaffoldPermit IssuedSHA HOME IMPROVEMENT INC07/27/2026
DOB NOWSuspended ScaffoldPermit IssuedC&C DALEY'S CONST.CORP07/15/2026
DOB NOWSidewalk ShedPermit IssuedPARK CONTRACTING GROUP04/21/2026
DOB NOWSidewalk ShedPermit IssuedPARK CONTRACTING GROUP04/17/2025
DOB NOWSidewalk ShedSigned-offRENNON CONSTRUCTION CORP10/21/2019
BISOTISSUEDMDG DESIGN & CONSTR LLC02/04/2020
BISOTISSUEDMDG DESIGN & CONSTR LLC04/22/2019
BISEQISSUEDEVEREST SCAFFOLDING INC02/12/2019
BISPLISSUEDJ-J PLUMBING CORP08/08/2018
BISOTISSUEDMDG DESIGN & CONSTR LLC02/09/2018
BISEQISSUEDEVEREST SCAFFOLDING INC01/03/2018
BISBLISSUEDJ-J PLUMBING CORP12/07/2017
BISBLISSUEDJ-J PLUMBING CORP07/27/2017
BISPLISSUEDJ-J PLUMBING CORP07/27/2017
BISEQISSUEDPARSONS CONSTRUCTION INC06/15/2017
BISOTISSUEDMDG DESIGN & CONSTR LLC06/15/2017
BISEQISSUEDEVEREST SCAFFOLDING INC01/17/2017
BISEQISSUEDEVEREST SCAFFOLDING INC01/22/2016
BISEQISSUEDEVEREST SCAFFOLDING INC02/05/2015
BISEQISSUEDEVEREST SCAFFOLDING INC02/14/2014
BISEQISSUEDEVEREST SCAFFOLDING INC02/06/2013
BISPLISSUEDMETROPOLITAN HEAT & POWER CO02/28/2008
BISBLISSUEDMETROPOLITAN HEAT & POWER CO02/28/2008
BISEQRE-ISSUEDNIDUS REALTY CORP./ARBOL DEV.COR03/17/1994
BIS—ISSUEDNIDUS REALTY CORP01/19/1994
BIS—ISSUEDNIDUS REALTY CORP06/30/1993
BISEQISSUEDNIDUS REALTY CORP06/29/1993
BISEQISSUEDROCKLEDGE SCAFFOLDING CORP06/15/1993
3 projects · most recent 04/17/2025
FiledStatusContractorScope
04/17/2025Permit IssuedRICHARD NEU—
10/08/2019CompleteWCK ELECTRIC CORP.—
04/15/2018Permit IssuedTUXEDO ELEC'L CONTR'G INC—
1 project · most recent 04/15/2025
Sidewalk Shed
FiledStatusContractorScope
04/15/2025Permit IssuedPARK CONTRACTING GROUPSidewalk Shed
2 projects · most recent 07/27/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
07/27/2026Permit IssuedSHA HOME IMPROVEMENT INCSuspended Scaffold (SC)
07/14/2026Permit IssuedC&C DALEY'S CONST.CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
01/12/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/12/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
01/12/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/08/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/03/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/03/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/06/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
07/10/2026Tenant Protection Plan ComplianceMohammed Babanspecial
07/10/2026MasonryChristopher Krepciospecial
07/10/2026FinalChristopher Krepcioprogress
07/10/2026Energy Code Compliance InspectionsChristopher Krepcioprogress
07/10/2026Air barrier - visual inspectionChristopher Krepcioenergy_progress
10/09/2019FinalSAMIR ABDALLAprogress
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch4
08/24/2026M01210717-I1Request digital key ↗
08/16/2026M01430397-I1Request digital key ↗
08/16/2026M01429269-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00243269-I1Request digital key ↗
▸Applications & Permits24
▸BISWORK PERMIT APPLICATION14
02/13/2019140053974Open ↗
01/05/2018140053974Open ↗
07/27/2017122682365Open ↗
Showing 3 of 14 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION10
03/13/2019122682365Open ↗
02/11/2019140053974Open ↗
11/14/2018122682365Open ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications25
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
09/20/2019140053974Open ↗
01/02/2018123075787Open ↗
06/19/2017123075787Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/16/2026M01430397-I1Open ↗
08/16/2026M01429269-I1Open ↗
08/16/2026M01435237-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
06/19/2017123075787Open ↗
12/18/2014140294358Open ↗
02/06/2013140053974Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026M00243269-I1Open ↗
08/26/2026M01429269-I1Open ↗
08/26/2026M01429269-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
12/18/2014140294358Open ↗
02/06/2013140053974Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
06/19/2017123075787Open ↗
02/08/2008110284647Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
12/18/2014140294358Open ↗
02/06/2013140053974Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026M01429269-I1Open ↗
08/26/2026M01429269-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
02/08/2008110284647Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
11/14/2018122682365Open ↗
09/07/2018122682365Open ↗
03/15/2016122682365Open ↗
▸BISSCHEDULE B - PLUMBING1
02/08/2008110284647Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
02/08/2008110284647Open ↗
▸Safety & Tenant Protection3
▸BISTenant Protection Plan and Notes2
03/20/2019122682365Open ↗
04/29/2016122682365Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00243269-I1Open ↗
▸Environmental & Asbestos4
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
12/18/2014140294358Open ↗
▸BISAPPLICANT SHALL PROVIDE 1 ACP-5 FORMPRIOR TO SIGN OFF: CONTROL # 16935971
09/11/2020122682365Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
02/08/2008110284647Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/16/2026M01429269-I1Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
09/11/2020122682365Open ↗
09/11/2020122682365Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/15/2016122682365Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
12/18/2014140294358Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
09/11/2020122682365Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
09/11/2020122682365Open ↗
09/11/2020122682365Open ↗
12/18/2014140294358Open ↗
Showing 3 of 4 on file for this type
▸BISNOTIF.-PROPOSED STEAM/HOT WATER INSPECTION1
02/08/2008110284647Open ↗
▸Approvals, Objections & Sign-offs16
▸BISSHED LETTER5
02/13/2019140053974Open ↗
02/13/2019140053974Open ↗
01/05/2018140053974Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
03/14/2019122682365Open ↗
01/05/2018140053974Open ↗
01/27/2017140053974Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
09/11/2020122682365Open ↗
09/20/2019140053974Open ↗
01/02/2018123075787Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/16/2026M01429269-I1Open ↗
08/13/2026M01210717-I1Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
02/08/2008110284647Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT6
04/29/2016122682365Open ↗
03/15/2016122682365Open ↗
12/18/2014140294358Open ↗
Showing 3 of 6 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
09/11/2020122682365Open ↗
▸Filing & Intake Forms14
▸BISBOROUGH INTAKE FORM8
09/20/2019140053974Open ↗
03/13/2019122682365Open ↗
02/04/2019140053974Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING COVER SHEET3
06/19/2017123075787Open ↗
04/08/2016122682365Open ↗
03/15/2016122682365Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
12/18/2014140294358Open ↗
02/06/2013140053974Open ↗
▸BISADDITIONAL INFORMATION1
04/29/2016122682365Open ↗
▸Other Documents10
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
06/15/2017123075787Open ↗
04/08/2016122682365Open ↗
02/06/2013140053974Open ↗
▸DOB NOWManufacturer's Specifications2
08/16/2026M01430397-I1Open ↗
08/16/2026M01435237-I1Open ↗
▸DOB NOWCalculations2
08/16/2026M01430397-I1Open ↗
08/16/2026M01435237-I1Open ↗
▸BISSupporting Document: Fee Exempt1
06/26/2017122682365Open ↗
▸BISTEMPORARY FLOOD SHIELDS: EMERGENCY FLOOD PLAN1
06/19/2017123075787Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
09/11/2020122682365Open ↗