| Owner | Filings | Most Recent |
|---|---|---|
| AQUILINA INDUSTRIES | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GHD | 3 | 04/01/2025 |
| GHD CONSULTING SERVICES INC. | 7 | 03/10/2025 |
| JOSEPH BOTTA, PE, PC | 4 | 07/23/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| M & S MECHANICAL SVCS INC | Plumbing | 10 | 07/08/2026 |
| O'LEARY CONSTRUCTION INC | General Contractor | 6 | 07/08/2026 |
| ABOVE & BEYOND P & H CORP | Plumbing | 4 | 07/08/2026 |
| JEAN-CLAUDE BELIZAIRE | Electrical | 1 | 03/21/2026 |
| M & S MECHANICAL SERVICES | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METRIC CONSULTING AND INS | 1803 | 10 | 04/01/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | M & S MECHANICAL SVCS INC | 08/05/2025 |
| DOB NOW | Structural | Signed-off | O'LEARY CONSTRUCTION INC | 04/08/2024 |
| DOB NOW | General Construction | Signed-off | O'LEARY CONSTRUCTION INC | 04/08/2024 |
| DOB NOW | Foundation | Signed-off | O'LEARY CONSTRUCTION INC | 04/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | M & S MECHANICAL SERVICES | 12/07/2023 |
| DOB NOW | Plumbing | Signed-off | M & S MECHANICAL SVCS INC | 12/07/2023 |
| DOB NOW | Structural | Signed-off | O'LEARY CONSTRUCTION INC | 12/07/2023 |
| DOB NOW | Foundation | Signed-off | O'LEARY CONSTRUCTION INC | 11/17/2023 |
| DOB NOW | General Construction | Signed-off | O'LEARY CONSTRUCTION INC | 11/16/2023 |
| DOB NOW | Plumbing | Signed-off | ABOVE & BEYOND P & H CORP | 05/04/2018 |
| DOB NOW | Plumbing | Permit Issued | ABOVE & BEYOND P & H CORP | 05/04/2018 |
| DOB NOW | Plumbing | Signed-off | ABOVE & BEYOND P & H CORP | 03/29/2018 |
| DOB NOW | Plumbing | Permit Issued | ABOVE & BEYOND P & H CORP | 10/23/2017 |
| BIS | MH | ISSUED | ABOVE AND BEYOND PLUMBING | 08/08/2016 |
| BIS | PL | ISSUED | CALA/SACCO-MECHANICAL INC | 03/21/2011 |
| BIS | OT | ISSUED | CATALYST CONSTRUCTION,LLC | 03/02/2011 |
| BIS | MH | ISSUED | CATALYST CONSTRUCTION,LLC | 05/27/2009 |
| BIS | PL | ISSUED | GRISDALE - HOWELL CONTRCTRS.LLC | 08/10/1999 |
| BIS | — | ISSUED | DOLA CONST CORP | 06/07/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/16/2018 | Complete | WILLDAN ELECTRICAL OF NY | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/07/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/07/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/20/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 04/23/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 04/09/2025 | Final | SAMI HAJJAR P.E | progress |
| 04/09/2025 | Footing and Foundation | SAMI HAJJAR P.E | progress |
| 04/09/2025 | Concrete - Cast-In-Place | SAMI HAJJAR P.E | special |
| 02/25/2025 | Footing and Foundation | SAMI HAJJAR P.E | progress |
| 02/25/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 02/25/2025 | Concrete - Cast-In-Place | SAMI HAJJAR P.E | special |
| 02/25/2025 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 02/25/2025 | Structural Steel - Details | SAMI HAJJAR P.E | special |
| 02/25/2025 | Subgrade Inspections | SAMI HAJJAR P.E | special |
| 02/25/2025 | Subsurface Conditions – Fill Placement & In-Place Density | SAMI HAJJAR P.E | special |
| 02/25/2025 | Final | SAMI HAJJAR P.E | progress |
| 02/25/2025 | Concrete - Cast-In-Place | SAMI HAJJAR P.E | special |
| 02/25/2025 | Final | SAMI HAJJAR P.E | progress |
| 11/14/2023 | Final | SAMI HAJJAR P.E | progress |
| 11/14/2023 | Subgrade Inspections | SAMI HAJJAR P.E | special |
| 11/14/2023 | Concrete - Cast-In-Place | SAMI HAJJAR P.E | special |
| 11/14/2023 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 11/14/2023 | Structural Steel - Details | SAMI HAJJAR P.E | special |
| 11/14/2023 | Subsurface Conditions – Fill Placement & In-Place Density | SAMI HAJJAR P.E | special |
| 07/31/2023 | Lighting controls | SAMI HAJJAR P.E | energy_progress |
| 07/31/2023 | Energy Code Compliance Inspections | SAMI HAJJAR P.E | progress |
| 07/18/2023 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 07/18/2023 | Final | SAMI HAJJAR P.E | progress |