1991Year Built
2Stories
B2Building Class
R6Zoning
2,000 sfGross Floor Area
2Units
Rent Stabilized8 Open Violations ▸
Two family frame · Owner of record: E 146 RESIDENCE CORP · 2,000 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingLandscape
Permit Issued — active, not yet Signed-off
Floor 3Under Construction4p · 1 filing · 12 docs
Floor 2Under Construction3p · 1 filing · 12 docs
Floor 1Under Construction3p · 1 filing · 12 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/06/2025$535K—— → —$268/sf building
08/28/2018$749K—YOUNG KIM CORP. → Private party$374/sf building
02/13/2018$450K—— → —$225/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SOLHJOU ENGINEERING104/16/2026
SION CONSULTING ENGINEERING PC410/27/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RENEW PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SION CONSULTING ENG. PC1108110/27/2025
Building Lifecycle
All (102)Filed (3)Permit Issued (1)Violation (22)Objection (52)Special Inspection (24)
09/21/2026
Objection resolved — Resolved
09/16/2026
Objection raised — Other
05/21/2026
Permit issued — Plumbing
X01238177-S2-PL
05/15/2026
Special inspection requirement — Energy Code Compliance Inspections
05/15/2026
Special inspection requirement — Fire-Resistance Rated Construction
04/28/2026
Objection raised — Structural
04/28/2026
Objection resolved — Addressed
04/28/2026
Objection raised — Admin
04/28/2026
Objection raised — Structural
04/28/2026
Objection resolved — Addressed
04/28/2026
Objection raised — Structural
04/28/2026
Objection resolved — Addressed
04/16/2026
Filed — Alteration CO
6 DU CONVERSION. OBTAIN NEW C.O.O. NO VERTICAL / HORIZONTAL EXTENSION AND ENLARGEMENT; NO CHANGE OF BUILDING ENVELOPE, FOOTPRINT, STRUCTURE, BULK, FACADE, EGRESS, AND ANY ITEM AFFECTING THE ENERGY OF THE BLDG.
X01238177-S4
02/20/2026
Objection resolved — Addressed
11/24/2025
Violation issued (HPD, open)
I
10/27/2025
Filed — Alteration CO
6 DU CONVERSION. OBTAIN NEW C.O.O. NO VERTICAL / HORIZONTAL EXTENSION AND ENLARGEMENT; NO CHANGE OF BUILDING ENVELOPE, FOOTPRINT, STRUCTURE, BULK, FACADE, EGRESS, AND ANY ITEM AFFECTING THE ENERGY OF THE BLDG.
X01238177-S2
10/23/2025
Special inspection requirement — Energy Code Compliance Inspections
sion hourizadeh
10/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
sion hourizadeh
10/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
sion hourizadeh
10/23/2025
Special inspection requirement — HVAC-R and service water heating system controls
sion hourizadeh
10/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
sion hourizadeh
10/20/2025
Objection resolved — Addressed
10/20/2025
Objection resolved — Addressed
10/20/2025
Objection resolved — Addressed
10/09/2025
Objection resolved — Addressed
10/09/2025
Special inspection requirement — Ventilation and air distribution system
10/09/2025
Special inspection requirement — Interior lighting power
10/09/2025
Special inspection requirement — Air barrier — testing
10/03/2025
Objection resolved — Addressed
10/03/2025
Special inspection requirement — Sprinkler Systems
10/02/2025
Special inspection requirement — Maintenance information
10/02/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
10/02/2025
Special inspection requirement — Air barrier - visual inspection
10/02/2025
Special inspection requirement — Fenestration air leakage
10/02/2025
Special inspection requirement — Fenestration areas
09/23/2025
Special inspection requirement — HVAC-R and service water heating system controls
09/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
09/23/2025
Special inspection requirement — Metering
09/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/04/2025
Objection resolved — Addressed
08/04/2025
Objection resolved — Addressed
08/04/2025
Objection resolved — Addressed
08/01/2025
Objection resolved — Addressed
07/30/2025
Objection resolved — Addressed
07/30/2025
Objection resolved — Addressed
07/30/2025
Objection resolved — Addressed
07/30/2025
Objection resolved — Addressed
07/22/2025
Objection raised — Fire_Protection
07/22/2025
Objection raised — Plumbing
07/22/2025
Objection raised — Other
07/22/2025
Objection raised — Other
07/22/2025
Objection raised — Energy
07/22/2025
Objection raised — Scope
Latest 60 of 102 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedRENEW PLUMBING CORP05/21/2026
1 project · most recent 04/16/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
04/16/2026——Heating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-3D24NLHZ MSZ-FX06NL MSZ-FX15NL 24,000 BTU · Split System ×6
Ventilation
Panasonic FV-1115VQ1 150 CFM · Exhaust Fan ×12
1 project · most recent 04/16/2026
Sprinkler System
FiledStatusContractorScope
04/16/2026——Sprinkler System
1 project · most recent 04/16/2026
Plumbing-Sprinkler
FiledStatusContractorScope
04/16/2026Permit IssuedRENEW PLUMBING CORPPlumbing-Sprinkler
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
05/15/2026Energy Code Compliance Inspections—progress
05/15/2026Fire-Resistance Rated Construction—progress
10/23/2025Energy Code Compliance Inspectionssion hourizadehprogress
10/23/2025HVAC-R and service water heating equipmentsion hourizadehenergy_progress
10/23/2025Fire-Resistant Penetrations and Jointssion hourizadehspecial
10/23/2025HVAC-R and service water heating system controlssion hourizadehenergy_progress
10/23/2025HVAC-R and service water piping design and insulationsion hourizadehenergy_progress
10/09/2025Ventilation and air distribution system—energy_progress
10/09/2025Interior lighting power—energy_progress
10/09/2025Air barrier — testing —energy_progress
10/03/2025Sprinkler Systems—special
10/02/2025Maintenance information—energy_progress
10/02/2025Fenestration and door U-factor and product ratings—energy_progress
10/02/2025Air barrier - visual inspection—energy_progress
10/02/2025Fenestration air leakage—energy_progress
10/02/2025Fenestration areas—energy_progress
09/23/2025HVAC-R and service water heating system controls—energy_progress
09/23/2025HVAC-R and service water piping design and insulation—energy_progress
09/23/2025Metering—energy_progress
09/23/2025HVAC-R and service water heating equipment—energy_progress
06/09/2025Mechanical Systems—special
06/09/2025Final—progress
06/09/2025Fire-Resistant Penetrations and Joints—special
06/09/2025Heating Systems—special
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/17/2026X01238177-S4Request digital key ↗
08/17/2026X01238177-S2Request digital key ↗
08/17/2026X01238177-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X01238177-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/17/2026X01238177-S4Open ↗
08/13/2026X01238177-S2Open ↗
08/13/2026X01238177-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026X01238177-S2Open ↗
08/23/2026X01238177-S2Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026X01238177-S2Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026X01238177-I1Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/13/2026X01238177-I1Open ↗