| Firm | Filings | Most Recent |
|---|---|---|
| PKAD ARCHITECTURE & DESIGN | 3 | 06/25/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADJ BUILDING CONSULTANT | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EAST END CONSTRUCTION & R | General Contractor | 6 | 03/21/2026 |
| PLUMB-IT MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| QUALITY TESTING, LLC | 7344 | 1 | 01/30/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | JVR PLBG AND HEATING INC | 11/13/2025 |
| DOB NOW | General Construction | Permit Issued | EAST END CONSTRUCTION & R | 08/01/2025 |
| DOB NOW | Structural | Permit Issued | EAST END CONSTRUCTION & R | 04/17/2025 |
| BIS | OT | ISSUED | SUNRUN INSTALLATION SVC | 08/26/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2026 | Permit Issued | PLUMB-IT MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2025 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | — |
| 06/17/2025 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 09/07/2023 | Permit Issued | SNB ELECTRICAL CONTNG COR | HVAC Wiring |
| 08/29/2022 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 05/16/2022 | Complete | S.A.L. ELECTRIC CO INC. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2026 | Permit Issued | PLUMB-IT MECHANICAL INC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/14/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/22/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/27/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/25/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/12/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/24/2025 | Concrete - Cast-In-Place | KEVIN SNEDEKER | special |
| 12/04/2024 | Wood – Prefabricated I-Joists | KEVIN SNEDEKER | special |
| 12/04/2024 | Lighting in dwelling units | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Structural Stability – Alterations of existing buildings | KEVIN SNEDEKER | special |
| 12/04/2024 | Interior lighting power | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Exterior lighting power | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Fenestration and door U-factor and product ratings | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Air barrier — testing | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Lighting controls | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Fenestration air leakage | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Insulation placement and R values | KEVIN SNEDEKER | energy_progress |
| 12/04/2024 | Air barrier - visual inspection | KEVIN SNEDEKER | energy_progress |
| 11/21/2024 | Final | KEVIN SNEDEKER | progress |