💬 Discuss this project
1922Year Built
6Stories
W6Building Class
R6Zoning
1,743,584 sfGross Floor Area
1Units
LL97 CoveredRent Stabilized0 Active Violations
Other college and university · Owner of record: Fordham University · 3,392,065 sf lot · 0.51 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofFordham University3p · 2 filings · 11 docs
Floor 3Fordham University2p · 1 filing · 6 docs
Floor 2Fordham University2p · 1 filing · 6 docs
Floor 1
MezzanineFordham University2p · 1 filing · 6 docs
Site & exteriorFordham University31p · 4 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Fordham University803/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Ashraf405/10/2022
Howard L Zimmerman Arch & Engineering107/15/2021
Reuther Bowen104/28/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design403/21/2026
Nyccode403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Intersystem InstallationScaffold610/04/2026
Sentinel BuildersGeneral Contractor307/08/2026
Manhattan D EnterprisesScaffold303/21/2026
Lawrence J. LevineFire Protection103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Twin Peaks317107/15/2021
Tectonic Engineering Cons106104/28/2021
Building Lifecycle
All (26)Filed (6)Permit Issued (7)Signed Off (4)Violation (1)Inspection (1)Special Inspection (7)
10/20/2022
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00495497-I1
10/20/2022
Signed off — Alteration
Installation of temporary sidewalk shed as per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00734094-I1
07/28/2022
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
07/07/2022
Permit issued — Supported Scaffold
X00495497-I1-SF
05/11/2022
Special inspection requirement — Final
Eric Foster
05/10/2022
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00495497-P1
05/10/2022
Permit issued — Sidewalk Shed
X00734094-I1-SH
05/09/2022
Filed — Alteration
Installation of temporary sidewalk shed as per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00734094-I1
05/09/2022
Special inspection requirement — Final
Eric Foster
02/04/2022
Signed off — Alteration
APPLICATION IS FILED FOR STRUCTURAL WORK ASSOCIATED WITH THE EXISTING STAGE RIGGING SYSTEM REPLACEMENT. NO CHANGE OF USE, EGRESS, OR OCCUPANCY.
X00449796-I1
10/27/2021
Permit issued — General Construction
X00524902-I1-GC
10/12/2021
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00527202-I1
09/16/2021
Permit issued — General Construction
X00524902-I1-GC
07/30/2021
Permit issued — Supported Scaffold
X00495497-I1-SF
07/15/2021
Filed — Alteration
FACADE REPAIRS IN RESPONSE TO ECB VIOLATION# 39030422K FAILURE TO MAINTAIN THE FACADE. REPAIRS INCLUDE CORNICE REPAIR, STONE REPLACEMENT, MISCELLANEOUS STONE & BRICK REPAIRS.
X00524902-I1
07/14/2021
Special inspection requirement — Post-installed Anchors
GIORGI KHARDZEISHVILI
05/26/2021
Permit issued — Supported Scaffold
X00527202-I1-SF
05/25/2021
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00527202-I1
05/19/2021
Special inspection requirement — Final
Jon Colatrella
05/07/2021
Permit issued — Structural
X00449796-I1-ST
04/28/2021
Filed — Alteration
APPLICATION IS FILED FOR STRUCTURAL WORK ASSOCIATED WITH THE EXISTING STAGE RIGGING SYSTEM REPLACEMENT. NO CHANGE OF USE, EGRESS, OR OCCUPANCY.
X00449796-I1
03/30/2021
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00495497-I1
01/07/2021
Special inspection requirement — Structural Steel - Details
EDUARDO LIEVANO
01/07/2021
Special inspection requirement — Structural Steel - Welding
EDUARDO LIEVANO
01/07/2021
Special inspection requirement — Final
EDUARDO LIEVANO
10/15/2020
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offIntersystem Installation07/07/2022
DOB NOWSidewalk ShedSigned-offIntersystem Installation05/10/2022
DOB NOWGeneral ConstructionPermit IssuedSentinel Builders10/27/2021
DOB NOWGeneral ConstructionPermit IssuedSentinel Builders09/16/2021
DOB NOWSupported ScaffoldSigned-offIntersystem Installation07/30/2021
DOB NOWSupported ScaffoldSigned-offManhattan D Enterprises05/26/2021
DOB NOWStructuralSigned-offSentinel Builders05/07/2021
BISOTISSUEDCaldwell & Walsh Building Construction01/07/2020
BISMHISSUEDCaldwell & Walsh Building Construction01/07/2020
BISOTISSUEDCaldwell & Walsh Building Construction01/07/2020
BISSDISSUEDNYC Fire Sprinkler11/20/2019
BISPLISSUEDPar Plumbing Co09/23/2019
BISOTISSUEDCaldwell & Walsh Building Construction09/11/2019
BISOTISSUEDCaldwell & Walsh Building Construction09/11/2019
BISMHISSUEDCaldwell & Walsh Building Construction09/11/2019
2 projects · most recent 05/29/2022
General Wiring
FiledStatusContractorScope
05/29/2022CompleteSteven Farkas—
08/18/2020CompleteH. & L. ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
07/28/2022Pass-Final Curb Cut Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
05/11/2022FinalEric Fosterprogress
05/09/2022FinalEric Fosterprogress
07/14/2021Post-installed AnchorsGIORGI KHARDZEISHVILIspecial
05/19/2021FinalJon Colatrellaprogress
01/07/2021Structural Steel - DetailsEDUARDO LIEVANOspecial
01/07/2021Structural Steel - WeldingEDUARDO LIEVANOspecial
01/07/2021FinalEDUARDO LIEVANOprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Fordham UniversityEducationEntire building
Project X00734094 Alteration · LOC Issued · 05/09/2022
Project X00524902 Alteration · Permit Entire · 07/15/2021
Project X00527202 Alteration · LOC Issued · 05/25/2021
Project X00449796 Alteration · LOC Issued · 04/28/2021
Project X00495497 Alteration · LOC Issued · 03/30/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 121 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch5
08/25/2026X00495497-I1Request digital key ↗
08/25/2026X00495497-P1Request digital key ↗
08/25/2026X00527202-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Structural1
08/25/2026X00449796-I1Request digital key ↗
▸Applications & Permits26
▸BISPLAN / WORK APPROVAL APPLICATION17
04/30/2021220703950Open ↗
04/26/2021220703950Open ↗
04/16/2021220703950Open ↗
Showing 3 of 17 on file for this type
▸BISWORK PERMIT APPLICATION9
05/03/2021240298227Open ↗
01/08/2020220703950Open ↗
01/08/2020220703950Open ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications23
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
09/12/2019220703950Open ↗
09/12/2019220703950Open ↗
09/12/2019220703950Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/25/2026X00495497-I1Open ↗
08/25/2026X00527202-I1Open ↗
08/13/2026X00524902-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/26/2026X00449796-I1Open ↗
08/30/2026X00495497-I1Open ↗
08/28/2026X00734094-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/26/2026X00449796-I1Open ↗
09/26/2026X00449796-I1Open ↗
08/24/2026X00524902-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
01/05/2021240298227Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
01/05/2021240298227Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/05/2021240298227Open ↗
▸Trade Schedules & Equipment13
▸BISSCHEDULE B - PLUMBING4
04/30/2021220703950Open ↗
11/16/2020220703950Open ↗
11/16/2020220703950Open ↗
Showing 3 of 4 on file for this type
▸BISEQUIPMENT USE PERMITS4
07/02/2021220703950Open ↗
07/02/2021220703950Open ↗
07/02/2021220703950Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
08/13/2019220703950Open ↗
06/17/2019220703950Open ↗
▸BISSTANDPIPE SYSTEMS1
05/12/2021220703950Open ↗
▸BISELEVATOR JOB SIGNOFF1
06/11/2021220703950Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
07/02/2021220703950Open ↗
▸Safety & Tenant Protection1
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
09/10/2019220703950Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
01/05/2021240298227Open ↗
03/02/2015220428124Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026X00449796-I1Open ↗
08/13/2026X00524902-I1Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
09/12/2019220703950Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
09/12/2019220703950Open ↗
09/12/2019220703950Open ↗
06/17/2019220703950Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/05/2021240298227Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
06/09/2021220703950Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
06/09/2021220703950Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
06/09/2021220703950Open ↗
05/12/2021220703950Open ↗
04/29/2021240298227Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs14
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter6
08/25/2026X00495497-I1Open ↗
08/13/2026X00527202-I1Open ↗
08/13/2026X00734094-I1Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
06/11/2021220703950Open ↗
06/09/2021220703950Open ↗
10/29/2020220703950Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
07/02/2021220703950Open ↗
06/11/2021220703950Open ↗
▸BISCONSTRUCTION (OT) SIGNOFF1
06/11/2021220703950Open ↗
▸BISMECHANICAL (MH) SIGNOFF1
06/11/2021220703950Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT7
01/05/2021240298227Open ↗
08/13/2019220703950Open ↗
08/13/2019220703950Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
06/09/2021220703950Open ↗
▸Filing & Intake Forms13
▸BISADDITIONAL INFORMATION6
04/23/2021220703950Open ↗
09/06/2019220703950Open ↗
08/20/2019220703950Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET4
06/17/2019220703950Open ↗
06/12/2019220703950Open ↗
06/12/2019220703950Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM2
07/02/2021220703950Open ↗
09/06/2019220703950Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
01/05/2021240298227Open ↗