| Owner | Filings | Most Recent |
|---|---|---|
| 4502 SUNNYSIDE | 98 | 09/13/2026 |
| JLS GROUP CONSTRUCTION | 18 | 07/08/2026 |
| DORIA | 10 | 07/08/2026 |
| RASELL REALTY | 5 | 04/09/2026 |
| TRI BOROUGH SCAFFOLDING | 4 | 04/09/2026 |
| YOEL LANDAU-JL WORKS INC | 1 | 03/22/2026 |
| OWNERS REP | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/29/2022 | $11.0M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ADITYA DESAI | 1 | 05/22/2026 |
| LORING CONSULTING ENGINEERS, INC. | 4 | 05/08/2026 |
| MY ARCHITECT PC | 5 | 04/21/2026 |
| HOWARD SPIVAK | 1 | 02/23/2026 |
| HRM ENGINEERING SERVICES, PC | 11 | 08/05/2025 |
| SKYLINE RIGGING | 4 | 11/27/2024 |
| EDWIN CHEUK | 8 | 10/31/2024 |
| SYNERGIC DESIGN ARCHITECTS | 1 | 10/29/2024 |
| URBAN INTEGRATIONS | 3 | 06/05/2024 |
| YL ENGINEERING PLLC | 2 | 10/20/2023 |
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 08/31/2023 |
| ARK ENGINEERING CONSULTANT, P.C. | 1 | 05/05/2022 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 1 | 08/29/2019 |
| SCALAR ARCHITECTURE PC | 2 | 12/17/2018 |
| EDWARD C. HICKS RA | 1 | 05/17/2018 |
| S.M. BERGER ARCHITECTURE PC | 1 | — |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB BUILDING CONSULTING | 22 | 03/21/2026 |
| MY ARCHITECT | 18 | 03/21/2026 |
| Rigid Structural Design, LLC | 3 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 4 | 03/21/2026 |
| TWP DESIGN CONSULTING | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| ACE CONSULTANTS | 2 | 03/21/2026 |
| AVALON DESIGN | 2 | 03/21/2026 |
| KATARIA BUILDERS | 2 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JLS GROUP CONSTRUCTION LL | General Contractor | 25 | 07/08/2026 |
| VIP FIRE SPRINKLER INC | Fire Protection | 4 | 07/08/2026 |
| DYNAMIC HOISTING SCAFF IN | General Contractor | 4 | 04/09/2026 |
| SAFEPIPE PLUMBING INC | Fire Protection | 3 | 07/08/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 2 | 07/08/2026 |
| LW INTERIOR REMODELING IN | General Contractor | 2 | 04/09/2026 |
| AL-LECTRIC ELECT'L CONTRG | Electrical | 2 | 03/22/2026 |
| MY ARCHITECT | General Contractor | 1 | 03/22/2026 |
| PRD GROUP INC | General Contractor | 1 | 07/08/2026 |
| RIGHT ANGLE CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| SAFEPIPE PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| TOP PLUMBING AND HEATING | Plumbing | 1 | 07/08/2026 |
| SIGNSTAR NYC | Scaffold | 1 | 07/08/2026 |
| HIGH QUALITY ELECTRIC OF | Electrical | 1 | 03/22/2026 |
| ORBIT SPRINKLER CORP | Fire Protection | 1 | 06/27/2026 |
| ACCORD POWER INC | General Contractor | 1 | 04/09/2026 |
| JL WORKS INC | General Contractor | 1 | 04/09/2026 |
| JSB WORKS INC | General Contractor | 1 | 04/09/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CATALPA SPECIAL INSPECTIO | 2004 | 4 | 05/08/2026 |
| MEP INSPECTIONS, INC | 1102 | 2 | 05/08/2026 |
| ARK ENGINEERING PC | 7261 | 23 | 04/21/2026 |
| SPIVAK ARCHITECTS PC | 6957 | 4 | 02/25/2026 |
| SKYLINE RIGGING | 7880 | 4 | 11/27/2024 |
| SYNERGIC DESIGN LLC | 8561 | 1 | 10/29/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 05/29/2026 |
| DOB NOW | Plumbing | Signed-off | TOP PLUMBING AND HEATING | 03/16/2026 |
| DOB NOW | Sprinklers | Signed-off | ORBIT SPRINKLER CORP | 03/13/2026 |
| DOB NOW | Mechanical Systems | Signed-off | LW INTERIOR REMODELING IN | 03/09/2026 |
| DOB NOW | General Construction | Signed-off | LW INTERIOR REMODELING IN | 03/09/2026 |
| DOB NOW | Curb Cut | Signed-off | JLS GROUP CONSTRUCTION LL | 07/14/2025 |
| DOB NOW | Construction Fence | Signed-off | JLS GROUP CONSTRUCTION LL | 04/23/2025 |
| DOB NOW | Standpipe | Signed-off | BELLEROSE PLBG & HEATING | 04/03/2025 |
| DOB NOW | Standpipe | Signed-off | BELLEROSE PLBG & HEATING | 04/03/2025 |
| DOB NOW | Sprinklers | Signed-off | BELLEROSE PLBG & HEATING | 04/02/2025 |
| DOB NOW | Plumbing | Signed-off | BELLEROSE PLBG & HTG | 02/06/2025 |
| DOB NOW | General Construction | Permit Issued | JLS GROUP CONSTRUCTION LL | 01/23/2025 |
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 11/06/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JLS GROUP CONSTRUCTION LL | 10/21/2024 |
| DOB NOW | Standpipe | Signed-off | VIP FIRE SPRINKLER INC | 10/10/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | JLS GROUP CONSTRUCTION LL | 09/20/2024 |
| DOB NOW | General Construction | Permit Issued | JLS GROUP CONSTRUCTION LL | 09/17/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC HOISTING SCAFF IN | 08/06/2024 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 07/30/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | DORIA, INC | 07/01/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC HOISTING SCAFF IN | 06/03/2024 |
| DOB NOW | Construction Fence | Signed-off | JLS GROUP CONSTRUCTION LL | 04/30/2024 |
| DOB NOW | Sprinklers | Signed-off | VIP FIRE SPRINKLER INC | 12/28/2023 |
| DOB NOW | Sprinklers | Signed-off | VIP FIRE SPRINKLER INC | 12/28/2023 |
| DOB NOW | Standpipe | Signed-off | VIP FIRE SPRINKLER INC | 11/09/2023 |
| DOB NOW | Foundation | Signed-off | JLS GROUP CONSTRUCTION LL | 10/18/2023 |
| DOB NOW | General Construction | Permit Issued | JLS GROUP CONSTRUCTION LL | 10/13/2023 |
| DOB NOW | Support of Excavation | Signed-off | JLS GROUP CONSTRUCTION LL | 10/13/2023 |
| DOB NOW | Structural | Signed-off | JLS GROUP CONSTRUCTION LL | 10/11/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PRD GROUP INC | 09/22/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | MC SUPERSTRUCTURE INC | 09/14/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | JLS GROUP CONSTRUCTION LL | 08/31/2023 |
| DOB NOW | Structural | Signed-off | JLS GROUP CONSTRUCTION LL | 07/19/2023 |
| DOB NOW | Foundation | Signed-off | JLS GROUP CONSTRUCTION LL | 07/19/2023 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 07/17/2023 |
| DOB NOW | Foundation | Signed-off | JLS GROUP CONSTRUCTION LL | 05/04/2023 |
| DOB NOW | Construction Fence | Signed-off | JLS GROUP CONSTRUCTION LL | 05/03/2023 |
| DOB NOW | General Construction | Permit Issued | JLS GROUP CONSTRUCTION LL | 02/02/2023 |
| DOB NOW | Support of Excavation | Signed-off | JLS GROUP CONSTRUCTION LL | 12/22/2022 |
| DOB NOW | Foundation | Signed-off | JLS GROUP CONSTRUCTION LL | 05/31/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/21/2026 | Permit Issued | JLS GROUP CONSTRUCTION LL | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Lg LMU361HHV 45,000 BTU · Vrf Outdoor ×74 LMU300HHV 28,600 BTU · Vrf Outdoor ×54 LUU240HHV 30,120 BTU · Heat Pump Outdoor ×2 Daikin RXYQ72TATJU 81,000 BTU · Vrf Outdoor ×6 RXSQ24TAVJU 27,000 BTU · Vrf Outdoor ×2 RXYQ120TATJU 135,000 BTU · Vrf Outdoor ×2 RXYQ96TATJU 108,000 BTU · Vrf Outdoor ×2 Aaon RN-013-8-0-EB09-3GB 292,500 BTU · Rooftop Unit ×4 Ventilation Greenheck USF-08 620 CFM · Exhaust Fan ×4 CUE-099-VG 150 CFM · Exhaust Fan ×2 USF-10 650 CFM · Exhaust Fan ×2 USF-24 7,200 CFM · Exhaust Fan ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2026 | Signed-off | ORBIT SPRINKLER CORP | — |
| 04/21/2026 | Signed-off | SAFEPIPE PLUMBING INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/21/2026 | Signed-off | BELLEROSE PLBG & HTG | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Complete | P & Z ELECTRIC CORP | General Wiring |
| 11/04/2024 | Complete | ACCORD POWER ELECTRIC LLC | — |
| 10/03/2024 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| 03/13/2024 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| 11/09/2023 | Complete | AL-LECTRIC ELECT'L CONTRG | — |
| 11/07/2023 | Complete | .UXEDO ELEC'L CONTR'G INC | — |
| 09/27/2023 | Complete | HIGH QUALITY ELECTRIC OF | — |
| 09/12/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| 12/09/2022 | Complete | AL-LECTRIC ELECT'L CONTRG | 1 meters, 1 new_meters |
| 08/22/2022 | Cancelled | AL-LECTRIC ELECT'L CONTRG | 1 meters, 1 new_meters |
| 12/14/2018 | Complete | V. VASS ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/07/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/12/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/15/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/18/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 09/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/28/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/05/2025 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 06/23/2025 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 06/23/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/28/2025 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 04/28/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/25/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 04/23/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/23/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 05/10/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/10/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/16/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 11/16/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 08/02/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/17/2026 | Air barrier continuity plan testing | George Lau | energy_progress |
| 07/17/2026 | Fire-Resistance Rated Construction | George Lau | progress |
| 07/17/2026 | Wall Panels, Curtain Walls, and Veneers | George Lau | special |
| 07/17/2026 | Preliminary | George Lau | progress |
| 07/17/2026 | Energy Code Compliance Inspections | George Lau | progress |
| 07/17/2026 | Fire-Resistant Penetrations and Joints | George Lau | special |
| 07/17/2026 | Protection of exposed foundation insulation | George Lau | energy_progress |
| 07/17/2026 | Fenestration areas | George Lau | energy_progress |
| 07/17/2026 | Insulation placement and R values | George Lau | energy_progress |
| 07/17/2026 | Air barrier - visual inspection | George Lau | energy_progress |
| 07/17/2026 | Fenestration air leakage | George Lau | energy_progress |
| 07/17/2026 | Vestibules | George Lau | energy_progress |
| 07/17/2026 | Fenestration and door U-factor and product ratings | George Lau | energy_progress |
| 05/22/2026 | Final | ADITYA DESAI | progress |
| 05/12/2026 | Tenant Protection Plan Compliance | Howard Spivak | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 05/12/2026 | Post-installed Anchors | Nicolas Crosetto | special |
| 05/12/2026 | Sprinkler Systems | Nicolas Crosetto | special |
| 05/06/2026 | Sprinkler Systems | Nicolas Crosetto | special |
| 05/06/2026 | Tenant Protection Plan Compliance | — | special |
| 05/06/2026 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 05/06/2026 | Post-installed Anchors | Nicolas Crosetto | special |
| 04/17/2026 | Air barrier continuity plan testing | George Lau | energy_progress |
| 04/17/2026 | Vestibules | George Lau | energy_progress |
| 04/17/2026 | Air barrier - visual inspection | George Lau | energy_progress |