| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/19/2026 | Signed-off | GOLDEN TIME CONTRACTING I | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NAM2 48,000 BTU · Heat Pump Outdoor ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/19/2026 | Signed-off | WASOFF PLBG & UTILITY CO | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2026 | Complete | I.P. ELECTRIC INC | — |
| 04/17/2026 | Complete | SWITCH ELECT OF THE FIVE | General Wiring |
| 08/15/2025 | Permit Issued | A.C. MORGAN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/19/2026 | Signed-off | GOLDEN TIME CONTRACTING I | Steel, Masonry, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | Permit Issued | AMERGY SOLAR INC | 78 panels, 35.1 kw, 2,783 roof_area_sqft |
| Owner | Filings | Most Recent |
|---|---|---|
| 15411 ASH STREET | 25 | 09/13/2026 |
| GOLDEN TIME CONTRACTING I | 6 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/03/2025 | $1.4M | — | — → — | $690/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SQUARE ARCH, LLC | 1 | 08/05/2026 |
| MEHDI GHAZI, P.E., P.C. | 6 | 06/19/2026 |
| MEI ARCHITECT PLLC | 2 | 06/19/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GOLDEN TIME CONTRACTING I | General Contractor | 13 | 07/08/2026 |
| AMERGY SOLAR INC | General Contractor | 1 | 08/08/2026 |
| WASOFF PLBG & UTILITY CO | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SQ. ARCH, LLC | 4802 | 1 | 08/05/2026 |
| MEHDI GHAZI, P.E. P.C. | 7129 | 6 | 06/19/2026 |
| TRIANGLE INSPECTION & TES | 7495 | 2 | 06/19/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | AMERGY SOLAR INC | 08/07/2026 |
| DOB NOW | Curb Cut | Signed-off | GOLDEN TIME CONTRACTING I | 06/11/2026 |
| DOB NOW | Plumbing | Signed-off | WASOFF PLBG & UTILITY CO | 08/14/2025 |
| DOB NOW | General Construction | Permit Issued | GOLDEN TIME CONTRACTING I | 08/13/2025 |
| DOB NOW | Foundation | Permit Issued | GOLDEN TIME CONTRACTING I | 08/12/2025 |
| DOB NOW | Structural | Signed-off | GOLDEN TIME CONTRACTING I | 08/11/2025 |
| DOB NOW | Construction Fence | Signed-off | GOLDEN TIME CONTRACTING I | 05/19/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/05/2026 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 08/05/2026 | Duct leakage testing, insulation and design | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Fenestration areas | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Insulation placement and R values | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Maintenance information | MEHDI GHAZI | energy_progress |
| 08/05/2026 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Air barrier — testing | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Fenestration and door U-factor and product ratings | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Permanent certificate | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Interior lighting power | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Electric vehicle service equipment requirements | MEHDI GHAZI | energy_progress |
| 08/05/2026 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Ventilation and air distribution system | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Fenestration air leakage | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Metering | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Protection of exposed foundation insulation | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Air barrier - visual inspection | MEHDI GHAZI | energy_progress |
| 08/05/2026 | Mechanical Systems | MEHDI GHAZI | special |
| 08/05/2026 | Heating Systems | MEHDI GHAZI | special |
| 08/05/2026 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 08/05/2026 | Structural Stability – Alterations of existing buildings | MEHDI GHAZI | special |
| 08/05/2026 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 08/05/2026 | Final | MEHDI GHAZI | progress |
| 08/05/2026 | Fire-Resistance Rated Construction | MEHDI GHAZI | progress |