← Back
Elevator apt, semi-fireproof without stores
The Pearson Court Square
45-50 PEARSON STREET · BIN 4000717
💬 Discuss this project
2012Year Built
15Stories
D1Building Class
M1-5/R7-3Zoning
142,398 sfGross Floor Area
197Units
LL97 CoveredRent Stabilized0 Open ViolationsFISP: SWARMP
Elevator apt, semi-fireproof without stores · Owner of record: PEARSON CAPITAL PARTNERS LLC · 28,617 sf lot · 4.98 FAR built · Flood zone X500
Locations of Work
ArchitectureStructural
Permit Issued — active, not yet Signed-off
RoofUnder Construction10p · 2 filings · 9 docs
Floor 15Under Construction8p · 1 filing · 7 docs
Floor 14Under Construction8p · 1 filing · 7 docs
Floor 13Under Construction8p · 1 filing · 7 docs
Floor 12Under Construction8p · 1 filing · 7 docs
Floor 11Under Construction8p · 1 filing · 7 docs
Floor 10Under Construction8p · 1 filing · 7 docs
Floor 9Under Construction8p · 1 filing · 7 docs
Floor 8Under Construction8p · 1 filing · 7 docs
Floor 7Under Construction8p · 1 filing · 7 docs
Floor 6Under Construction8p · 1 filing · 7 docs
Floor 5Under Construction8p · 1 filing · 7 docs
Floor 4Under Construction8p · 1 filing · 7 docs
Floor 3Under Construction8p · 1 filing · 7 docs
Floor 2Under Construction8p · 1 filing · 7 docs
Floor 1Under Construction8p · 1 filing · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
C+C MANAGEMENT1309/13/2026
PEARSON CAPITAL PARTNERS LLC603/22/2026
CONGRESS BUILDERS2003/22/2026
VFC PARTNERS 4 LLC, PARSO103/22/2026
RISI ASSOCIATES2403/21/2026
TOWER 56603/21/2026
MC O CONTRACTING203/21/2026
MNM INVESTOR GROUP403/21/2026
PEARSON MT LLC103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PAUL PERDEK, PROF. ENG. PLLC103/13/2026
RAND ENGINEERING & ARCHITECTURE DPC202/11/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION403/21/2026
JULIAN A. GOMEZ403/21/2026
SMEP DESIGN & CONSULTATION LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
POWERS BRIDGING & SCAFFOLDINGGeneral Contractor207/08/2026
SKYLINE RESTORATION INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SONI ENGINEERING CONSULTI9819203/23/2026
RAND ENGINEERING & ARCHIT266109/26/2025
Building Lifecycle
All (70)Filed (6)Permit Issued (6)Facade (FISP) (3)Violation (35)Objection (4)Special Inspection (16)
06/12/2026
Permit issued — Sidewalk Shed
Q01364492-I1-SH
05/01/2026
Permit issued — General Construction
Q00869899-I1-GC
03/26/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
nayan soni
03/26/2026
Special inspection requirement — Post-installed Anchors
nayan soni
03/23/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #1 change outrigger beam position
Q01321188-P1
03/16/2026
Permit issued — Sidewalk Shed
Q01364492-I1-SH
03/13/2026
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01364492-I1
02/27/2026
Permit issued — Suspended Scaffold
Q01321188-I1-SC
02/24/2026
Special inspection requirement — Tenant Protection Plan Compliance
John Monroe
02/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
John Monroe
02/24/2026
Special inspection requirement — Final
John Monroe
02/24/2026
Special inspection requirement — Energy Code Compliance Inspections
John Monroe
02/24/2026
Special inspection requirement — Air barrier - visual inspection
John Monroe
02/24/2026
Special inspection requirement — Post-installed Anchors
John Monroe
02/24/2026
Special inspection requirement — Masonry
John Monroe
02/11/2026
Filed — Alteration
General construction along exterior elevations and at roof level as part of a 9th Cycle Facade repair program. No change to use, egress, or occupancy.
Q00869899-P1
02/11/2026
Special inspection requirement — Post-installed Anchors
02/10/2026
Special inspection requirement — Energy Code Compliance Inspections
02/10/2026
Special inspection requirement — Tenant Protection Plan Compliance
02/10/2026
Special inspection requirement — Air barrier - visual inspection
02/10/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
02/10/2026
Special inspection requirement — Masonry
02/10/2026
Special inspection requirement — Final
01/21/2026
Permit issued — Suspended Scaffold
Q01321188-I1-SC
01/01/2026
Objection resolved — Addressed
12/22/2025
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #1 change outrigger beam position
Q01321188-I1
12/22/2025
Objection raised — Structural
11/04/2025
Objection resolved — Addressed
10/24/2025
Objection raised — Cost
09/26/2025
Filed — Alteration
General construction along exterior elevations and at roof level as part of a 9th Cycle Facade repair program. No change to use, egress, or occupancy.
Q00869899-I1
07/11/2025
Filed — Alteration
FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS.SEE ATTACHED PLANS Designated Primary Site supervisor: Jesus Decola
Q01243406-I1
07/11/2025
Permit issued — Suspended Scaffold
Q01243406-I1-SC
05/22/2023
Violation issued (HPD, closed)
B
05/22/2023
Violation issued (HPD, closed)
A
05/22/2023
Violation issued (HPD, closed)
C
05/22/2023
Violation issued (HPD, closed)
A
03/31/2023
Violation issued (HPD, closed)
A
02/21/2022
Cycle 9 facade report submitted
02/21/2022
Cycle 9 facade inspection completed
02/21/2022
Cycle 9 facade report signed — SWARMP
04/20/2021
Violation issued (HPD, closed)
A
04/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/29/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/29/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/10/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/10/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/04/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/04/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/30/2013
Violation issued (ECB, closed)
Construction
12/05/2012
Violation issued (ECB, closed)
Construction
12/05/2012
Violation issued (ECB, closed)
Construction
01/07/2012
Violation issued (ECB, closed)
Construction
11/25/2011
Violation issued (ECB, closed)
Construction
11/25/2011
Violation issued (ECB, closed)
Construction
12/06/2010
Violation issued (ECB, closed)
Unknown
08/03/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/29/2010
Violation issued (ECB, closed)
Construction
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedPOWERS BRIDGING & SCAFFOLDING06/12/2026
DOB NOWGeneral ConstructionPermit IssuedSKYLINE RESTORATION INC05/01/2026
DOB NOWSidewalk ShedPermit IssuedPOWERS BRIDGING & SCAFFOL03/16/2026
DOB NOWSuspended ScaffoldPermit IssuedSKYLINE RESTORATION INC02/27/2026
DOB NOWSuspended ScaffoldPermit IssuedSKYLINE RESTORATION INC01/21/2026
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM07/11/2025
BISOTISSUEDCONGRESS BUILDERS LLC03/17/2017
BISOTISSUEDCONGRESS BUILDERS LLC03/17/2017
BISSDISSUEDRO-SAL PLBG HTG INC07/23/2014
BISOTISSUEDCONGRESS BUILDERS LLC03/21/2014
BISOTISSUEDCONGRESS BUILDERS LLC02/03/2014
BISEQISSUEDCONGRESS BUILDERS LLC02/03/2014
BISMHISSUEDCONGRESS BUILDERS LLC02/03/2014
BIS—ISSUEDCONGRESS BUILDERS LLC02/03/2014
BISOTISSUEDCONGRESS BUILDERS LLC02/03/2014
BISEQISSUEDROCKLEDGE SCAFFOLD CORP10/18/2013
BISOTISSUEDCONGRESS BUILDERS LLC10/08/2013
BISOTISSUEDCONGRESS BUILDERS LLC10/08/2013
BISOTISSUEDCONGRESS BUILDERS LLC09/27/2013
BISOTISSUEDCONGRESS BUILDERS LLC09/27/2013
BISEQISSUEDM & A PROJECTS INC09/27/2013
BISEQISSUEDMC & O CONTRACTING INC08/14/2013
BISEQISSUEDROCKLEDGE SCAFFOLD CORP07/29/2013
BISPLISSUEDRO-SAL PLUMBING & HTG INC INC.07/19/2013
BISSDISSUEDRO-SAL PLBG HTG INC07/19/2013
BISBLISSUEDRO-SAL PLUMBING & HTG INC INC.06/12/2013
BISSPISSUEDRO-SAL PLBG HTG INC05/21/2013
BISEQISSUEDCONGRESS BUILDERS LLC02/22/2013
BISOTISSUEDCONGRESS BUILDERS LLC02/21/2013
BIS—ISSUEDCONGRESS BUILDERS LLC02/21/2013
BISEQISSUEDCONGRESS BUILDERS LLC02/21/2013
BISMHISSUEDCONGRESS BUILDERS LLC02/21/2013
BISOTISSUEDCONGRESS BUILDERS LLC02/21/2013
BISEQISSUEDROCKLEDGE SCAFFOLD CORP12/27/2012
BISEQISSUEDMC & O CONTRACTING INC12/17/2012
BISEQISSUEDROCKLEDGE SCAFFOLD CORP11/16/2012
BIS—ISSUEDCONGRESS BUILDERS LLC09/04/2012
BISEQISSUEDROCKLEDGE SCAFFOLD CORP08/27/2012
BISPLISSUEDRO-SAL PLUMBING & HTG INC INC.07/24/2012
BISSDISSUEDRO-SAL PLBG HTG INC07/24/2012
+ 15 more permits on file
2 projects · most recent 04/01/2026
FiledStatusContractorScope
04/01/2026CompleteJTE ELECTRICAL SERVICES—
02/23/2026Permit IssuedOPTIMAL ELECTRIC, INC—
1 project · most recent 03/13/2026
Sidewalk Shed
FiledStatusContractorScope
03/13/2026Permit IssuedPOWERS BRIDGING & SCAFFOLSidewalk Shed
2 projects · most recent 03/23/2026
Suspended Scaffold
FiledStatusContractorScope
03/23/2026Permit IssuedSKYLINE RESTORATION INCSuspended Scaffold
07/11/2025Permit IssuedSTRUCTUAL PRESV SYSTEMSuspended Scaffold
2 projects · most recent 03/23/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
03/23/2026Permit IssuedSKYLINE RESTORATION INCSuspended Scaffold (SC)
07/11/2025Permit IssuedSTRUCTUAL PRESV SYSTEM—
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
03/26/2026Alternative Materials - OTCR Buildings Bulletin Numbernayan sonispecial
03/26/2026Post-installed Anchorsnayan sonispecial
02/24/2026Tenant Protection Plan ComplianceJohn Monroespecial
02/24/2026Structural Stability – Alterations of existing buildingsJohn Monroespecial
02/24/2026FinalJohn Monroeprogress
02/24/2026Energy Code Compliance InspectionsJohn Monroeprogress
02/24/2026Air barrier - visual inspectionJohn Monroeenergy_progress
02/24/2026Post-installed AnchorsJohn Monroespecial
02/24/2026MasonryJohn Monroespecial
02/11/2026Post-installed Anchors—special
02/10/2026Energy Code Compliance Inspections—progress
02/10/2026Tenant Protection Plan Compliance—special
02/10/2026Air barrier - visual inspection—energy_progress
02/10/2026Structural Stability – Alterations of existing buildings—special
02/10/2026Masonry—special
02/10/2026Final—progress
▾Documents — 304 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/19/2026Q01243406-I1Request digital key ↗
08/17/2026Q00869899-I1Request digital key ↗
08/17/2026Q00869899-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits55
▸BISPLAN / WORK APPROVAL APPLICATION28
05/09/2016421322928Open ↗
05/09/2016421322928Open ↗
09/17/2014420554885Open ↗
Showing 3 of 28 on file for this type
▸BISWORK PERMIT APPLICATION22
03/27/2017421322928Open ↗
03/27/2017421322928Open ↗
03/26/2014420578128Open ↗
Showing 3 of 22 on file for this type
▸BISIntent to Revoke Approval/Permit2
03/06/2013402102407Open ↗
02/24/2016420868252Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDOT Permit - House Connection1
08/04/2014420559372Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications76
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION53
03/27/2017421322928Open ↗
03/27/2017421322928Open ↗
05/09/2016421322928Open ↗
Showing 3 of 53 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
07/29/2013420868252Open ↗
01/08/2013420788026Open ↗
12/18/2012420794992Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
07/27/2013420868252Open ↗
12/28/2012420788026Open ↗
12/17/2012420794992Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/17/2026Q01364492-I1Open ↗
08/13/2026Q00869899-P1Open ↗
08/13/2026Q00869899-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/29/2026Q00869899-I1Open ↗
08/26/2026Q01321188-I1Open ↗
08/26/2026Q01321188-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/29/2026Q00869899-I1Open ↗
08/29/2026Q00869899-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
09/27/2013440106966Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
09/27/2013440106966Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/27/2013440106966Open ↗
▸Trade Schedules & Equipment45
▸BISSELF-CERT PLUMBING NOTICE11
10/14/2014420554885Open ↗
08/20/2014420555624Open ↗
07/09/2014420559363Open ↗
Showing 3 of 11 on file for this type
▸BISSCHEDULE B - PLUMBING9
05/02/2014420554885Open ↗
05/01/2014420554885Open ↗
01/23/2014420559363Open ↗
Showing 3 of 9 on file for this type
▸BISEQUIPMENT USE PERMITS5
10/28/2014420554885Open ↗
10/28/2014420554885Open ↗
10/28/2014420554885Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT4
07/11/2013420554885Open ↗
05/21/2013420554885Open ↗
Showing 2 of 4 on file for this type
▸BISSTANDPIPE INSP REPORT : FP-842
08/20/2014420555624Open ↗
05/22/2014420559363Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
08/04/2014420554885Open ↗
07/10/2014420554885Open ↗
▸BISEQUIPMENT USE APPLICATION-PERMIT2
10/30/2014420554885Open ↗
10/27/2014420554885Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA2
07/29/2014420578039Open ↗
05/22/2014420559363Open ↗
▸BISSEWER/HOUSE CON SIGNOFF: DEP HC 0211
05/22/2014420554885Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
05/22/2014420559363Open ↗
▸BISDETECTOR:SMOKE-CERTIFICATE OF INSTALLATION1
05/22/2014420559363Open ↗
▸BISRPZ/DDCV TEST REPORT : GEN215B1
05/22/2014420554885Open ↗
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
05/14/2014420578128Open ↗
▸BISGAS CUT-OFF1
11/13/2013420554885Open ↗
▸BISBOILERS - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISWATER METER PERMIT : DEP-METER1
05/22/2014420554885Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE SUPPORTING DOCUMENT1
08/04/2014420559372Open ↗
▸Environmental & Asbestos6
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
12/28/2012420788026Open ↗
12/17/2012420794992Open ↗
Showing 2 of 5 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
07/27/2013420868252Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
09/19/2016421322928Open ↗
05/02/2014420554885Open ↗
05/02/2014420554885Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections4
01/25/2013420554885Open ↗
01/25/2013420554885Open ↗
01/25/2013420554885Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS1
10/09/2014420554885Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX3
01/25/2013420554885Open ↗
12/24/2012420554885Open ↗
Showing 2 of 3 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION2
01/25/2013420554885Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
11/02/2013420554885Open ↗
01/25/2013420554885Open ↗
▸BISHYDRO FLOW TEST LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCONCRETE DESIGN MIX (TR-3) 27-6051
11/30/2012420554885Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY1
09/27/2013440106966Open ↗
▸Approvals, Objections & Sign-offs42
▸BISLETTERS - SUPPORTING DOCUMENTATION16
09/26/2014420559363Open ↗
09/26/2014420555624Open ↗
09/10/2014420559372Open ↗
Showing 3 of 16 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST12
10/27/2014420554885Open ↗
09/26/2014420559363Open ↗
09/26/2014420555624Open ↗
Showing 3 of 12 on file for this type
▸BISADMINISTRATIVE OBJECTIONS11
07/24/2013420868252Open ↗
01/08/2013420788026Open ↗
12/18/2012420794992Open ↗
Showing 3 of 11 on file for this type
▸BISTAP LETTER - DOM SVC : DEP-DOM2
05/22/2014420554885Open ↗
05/22/2014420554885Open ↗
▸BISSHED LETTER1
02/21/2014420787508Open ↗
▸Cost, Insurance & Ownership13
▸BISCOST AFFIDAVIT12
09/19/2016421322928Open ↗
09/19/2016421322928Open ↗
05/09/2016421322928Open ↗
Showing 3 of 12 on file for this type
▸BISBPP-11 - Affidavit as to Roadway Pavement And/Or Sidewalk and Curb Construction1
08/04/2014420559372Open ↗
▸Filing & Intake Forms32
▸BISEFILING COVER SHEET17
05/09/2016421322928Open ↗
05/09/2016421322928Open ↗
07/24/2013420868252Open ↗
Showing 3 of 17 on file for this type
▸BISADDITIONAL INFORMATION11
09/19/2016421322928Open ↗
09/19/2016421322928Open ↗
09/19/2016421322928Open ↗
Showing 3 of 11 on file for this type
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT32
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISeFiling Job Application Cover Sheet2
09/27/2013440106966Open ↗
Showing 1 of 2 on file for this type
▸Other Documents7
▸DOB NOWCalculations2
08/13/2026Q01321188-P1Open ↗
08/13/2026Q01321188-I1Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026Q01321188-P1Open ↗
08/13/2026Q01321188-I1Open ↗
▸BISDRY PIPE VALVE TEST : FP-101
07/09/2014420559363Open ↗
▸BISSD/SP FIRE PUMP TEST : FP-861
05/22/2014420559363Open ↗
▸DOB NOWIRA Certification1
08/13/2026Q01243406-I1Open ↗