RoofUnder Construction6p · 3 filings · 20 docs
ArchitectureElectricalMechanicalStructural
inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Diego Buri Cumbe
On file for this project
2 documents · 1 drawing sheet
Facade repair/restoration work as per plans. No change in use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Mechanical modifications as shown as per plans filed herewith. Filed in conjunction with DOB NOW structural application M00497294. No change in occupancy, egress, or use.
On file for this project
23 documents · 4 drawing sheets
Bulkhead2p · 2 filings · 11 docs
Structural
SUSPENDED SCAFFOLDING FOR FACADE RESTORATION
On file for this project
3 documents · 1 drawing sheet
Structural modifications filed as per plans filed herewith. The work scope associated with these drawings is associated with mechanical upgrades filed under DOB NOW application M00493030. no change in egress occupancy or use.
On file for this project
8 documents · 1 drawing sheet
Floor 409p · 1 filing · 3 docs
Architecture
Issued Permit Scope
General Construction
Herewith filing for interior demolition and installation of non-bearing partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
3 documents
Floor 391p · 1 filing · 6 docs
Architecture
SPEAR-- General construction inclusive of demolition and installation of interior partitions for office space renovation. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Floor 384p · 3 filings · 16 docs
Fire ProtectionMechanicalPlumbing
Modifications to the existing Sprinkler System: Remove (2) existing sprinkler heads and Relocate (19) sprinkler heads and associated piping on the 35th Floor (CO)/ 38th Floor (Marketing) as per plans (Chaincode Labs - Pineridge.) No change to u, e, o.
On file for this project
7 documents · 1 drawing sheet
Remove (1) drinking fountain and associated CW/sanitary piping and Install one (1) new drinking fountain and associated piping on the 35th Floor (CO)/ 38th Floor (Marketing) as per plans (Chaincode Labs - Pineridge.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC System: redistribution of ductwork and rebalancing on the 35th Floor (CO)/ 38th Floor (Marketing) as per plans (Chaincode Labs - PineRidge.) No change to use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Floor 372p · 2 filings · 7 docs
Plumbing
Sprinkler modifications taking place on the 37th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 1 drawing sheet
plumbing modifications taking place on the 37th floor as per plans filed herewith. No change in use, egress or occupancy
On file for this project
3 documents · 1 drawing sheet
Floor 3614p · 8 filings · 20 docs
ArchitectureGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
Alt 2 work for floor densification project
On file for this project
5 documents · 1 drawing sheet
Ductwork modification
On file for this project
6 documents · 1 drawing sheet
Mechanical work in conjunction with demo and general construction for tenant buildout.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 3511p · 5 filings · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Plumbing
Tenant alterations to commercial interior. Interior demolition only. No alterations to existing base building envelope, HVAC/mechanical, or lighting systems.
On file for this project
4 documents · 1 drawing sheet
Remove (1) drinking fountain and associated CW/sanitary piping and Install one (1) new drinking fountain and associated piping on the 35th Floor (CO)/ 38th Floor (Marketing) as per plans (Chaincode Labs - Pineridge.) No change to use, egress or occupancy.
On file for this project
3 documents
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 35th Floor (CO)/ 38th Floor (Marketing) as per plans (Chaincode Labs - PineRidge.) No change to use, egress or occupancy.
On file for this project
3 documents · 6 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 34Under Construction4p · 3 filings · 15 docs
Mechanical
Issued Permit Scope
Mechanical Systems
Lighting fixtures replacement as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
6 documents
Replacement of air conditioning units for 34th floor Data Center. No change in use egress and occupancy
On file for this project
3 documents
Installation of ductwork and new VAV. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Floor 33
Floor 32Under Construction6p · 3 filings · 19 docs
ArchitectureElectrical
Modifications to the existing system to accommodate new layout.
On file for this project
6 documents · 2 drawing sheets
General construction work associated with a floor densification project.
On file for this project
5 documents · 3 drawing sheets
Removal and installation of interior nonbearing partitions as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
8 documents · 1 drawing sheet
Floor 31
Floor 30Under Construction5p · 3 filings · 14 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Supported Scaffold
Modifications to the existing system to accommodate new layout.
On file for this project
6 documents · 3 drawing sheets
General construction work associated with a floor densification project.
On file for this project
5 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 291 filing · 3 docs
Issued Permit Scope
Supported Scaffold
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 2873p · 6 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 8 drawing sheets
Modify mechanical ductwork and related piping. No change in use, egress or occupancy.
On file for this project
3 documents
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 2772p · 6 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 7 drawing sheets
Modify mechanical ductwork and related piping. No change in use, egress or occupancy.
On file for this project
3 documents
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 2672p · 6 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 7 drawing sheets
Modify mechanical ductwork and related piping. No change in use, egress or occupancy.
On file for this project
3 documents
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 2543p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 2443p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 2344p · 4 filings · 20 docs
ArchitectureFire ProtectionStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
Floor 2244p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 2143p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 2044p · 4 filings · 20 docs
ArchitectureGeneralStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Structural work as per plans including: support of slab openings for MEP, support of new interior storefront and support of new garage doors.
On file for this project
67 documents · 1 drawing sheet
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
Latest 3 of 4 filings on this floor.
Floor 1943p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 1843p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
INSTALLATION OF STEEL PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
3 documents
Floor 1743p · 3 filings · 19 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural · Supported Scaffold
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
INSTALLATION OF STEEL PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
3 documents
Floor 16Under Construction77p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Modify sprinkler heads and related piping. No change in use, egress or occupancy.
On file for this project
25 documents · 7 drawing sheets
Demolition and installation of non-bearing interior partitions, doors and finishes related to tenant fit out. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
10 documents
Latest 3 of 4 filings on this floor.
Floor 15Under Construction32p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Supported Scaffold
Modify sprinkler heads and related piping. No change in use, egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
INSTALLATION OF STEEL PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
3 documents
Floor 14Under Construction17p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Supported Scaffold
Modify sprinkler heads and related piping. No change in use, egress or occupancy.
On file for this project
18 documents
INSTALLATION OF STEEL PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
3 documents
Floor 13Under Construction37p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modify sprinkler heads and related piping. No change in use, egress or occupancy.
On file for this project
25 documents · 5 drawing sheets
Add and remove ductwork and diffusers as per plans. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
9 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 1212p · 8 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers
Removal and installation of ductwork. No change in use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Structural work as per plans. No change in use, egress or occupancy.
On file for this project
9 documents · 1 drawing sheet
Alteration of non-structural interior partitions and associated wall, ceiling, and floor finishes. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 11Under Construction30p · 7 filings · 20 docs
ArchitectureFire ProtectionGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers
Modify mechanical ductwork and related piping. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Removal of non-bearing interior partitions and associated finishes. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Interior renovation of non-load bearing partitions, doors and finishes related to tenant fit out as per plans. No change in use, egress or occupancy.
On file for this project
3 documents
Latest 3 of 7 filings on this floor.
Floor 1059p · 9 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers · Structural
Application filed for retrofit of existing steam coil. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Reinforcing of existing steel beam by welding steel plate to bottom flange. No change in use, egress or occupancy.
On file for this project
5 documents
Installation of the new concrete infill in existing conveyor openings. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 9Under Construction2p · 2 filings · 15 docs
PlumbingStructural
Support for Modernfold partition, support of (1) high density file system, and localized trenching for power. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modify plumbing fixtures and related piping as per plans. No change in use egress or occupancy.
On file for this project
12 documents · 1 drawing sheet
Floor 8Under Construction82p · 16 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Exterior Facade work as per plans. No change in use, egress or occupancy.
On file for this project
12 documents · 3 drawing sheets
INSTALLATION OF TEMPORARY SPRINKLER LOOP. NO CHANGE TO USE, EGRESS AND/OR OCCUPANCY.
On file for this project
4 documents
Removal of non-bearing interior partitions and associated finishes. No change in use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 8 filings on this floor.
Floor 7Under Construction14p · 8 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Sprinklers · Standpipe
Support of folding partition, support for feature stairs, support for new slab opening, support of feature wall, and support for MEP/food service slab opening and beam penetrations. No change in use, egress or occupancy.
On file for this project
44 documents · 2 drawing sheets
Alteration-CO to establish Place of Assemblies on floors 6 & 7 Construction (8 & 10 Marketing) with minor interior renovations of non-loading bearing partitions and doors on the 7th floor only. Refer to comments for additional information.
On file for this project
5 documents
Installation of two fire hose cabinets and related piping. No change in use, egress or occupancy.
On file for this project
4 documents
Latest 3 of 8 filings on this floor.
Floor 6Under Construction74p · 8 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Structural work as per plans including: support of slab openings for MEP, support of new interior storefront and support of new garage doors.
On file for this project
67 documents · 28 drawing sheets
Exterior Facade work as per plans. No change in use, egress or occupancy.
On file for this project
12 documents
Modify sprinkler heads and related piping. No change in use, egress or occupancy.
On file for this project
19 documents · 8 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 57p · 6 filings · 20 docs
Fire ProtectionMechanicalStructural
Support of folding partition, support for feature stairs, support for new slab opening, support of feature wall, and support for MEP/food service slab opening and beam penetrations. No change in use, egress or occupancy.
On file for this project
44 documents · 1 drawing sheet
Application filed for retrofit of existing steam coil. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Installation of the new concrete infill in existing conveyor openings. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 41p · 1 filing · 5 docs
Structural
Installation of the new concrete infill in existing conveyor openings. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Floor 31p · 1 filing · 5 docs
Structural
Installation of the new concrete infill in existing conveyor openings. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Floor 22p · 2 filings · 17 docs
PlumbingStructural
Installation of the new concrete infill in existing conveyor openings. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Modify plumbing fixtures and related piping as per plans. No change in use egress or occupancy.
On file for this project
12 documents · 1 drawing sheet
Floor 1Under Construction17p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Sprinklers · Structural
INSTALLATION OF TEMPORARY SPRINKLER LOOP. NO CHANGE TO USE, EGRESS AND/OR OCCUPANCY.
On file for this project
4 documents
Structural work as per plans
On file for this project
31 documents · 2 drawing sheets
Installation of the new concrete infill in existing conveyor openings. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.