1955Year Built
21Stories
D7Building Class
R7-2Zoning
705,584 sfGross Floor Area
814Units
LL97 Covered21 Open Violations 19 unresolved · 2 paperwork only ▸FISP: SWARMP
Elevator apt, semi-fireproof with stores · Owner of record: NYC HOUSING AUTHORITY · 339,250 sf lot · 2.08 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Roof9p · 2 filings · 13 docs
Floor 19p · 2 filings · 11 docs
Cellar2p · 1 filing · 4 docs
Site & exterior2p · 1 filing · 4 docs
Filed — no permit issued25p · 2 filings · 12 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA2707/08/2026
NEW YORK CITY HOUSING AUTHORITY1207/08/2026
N Y C HOUSING AUTHORITY703/21/2026
NEW YORK HOUSING AUTHORITY103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ZI ENGINEERING, P.C106/13/2025
THE LIRO GROUP302/22/2024
GAMILL ENGINEERING, P.C108/28/2023
JOEL PHAGOO P.E. PLLC309/24/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JOEL PHAGOO P.E. PLLC103/21/2026
GAMILL ENGINEERING, PC203/21/2026
KINGSTON ENGINEERING203/21/2026
JOEL PHAGOO P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SKYWORX CONTRACTING INCGeneral Contractor707/08/2026
NEELAM CONSTRUCTION CORPGeneral Contractor507/08/2026
CHARNJIT SINGHElectrical203/21/2026
GREEHY, MICHAELElectrical103/21/2026
H&F IRON WORKSElectrical103/21/2026
ISLAND FIRE PROTECTIONElectrical103/21/2026
KOLKER, MIKHAILElectrical103/21/2026
LIPARI, GASPAREElectrical103/21/2026
LIT MODE ELECL CONTG INCElectrical103/22/2026
SEMPLE, JERYMANEElectrical103/21/2026
STEPHENS, KENNETHElectrical103/21/2026
VINCENT SPINAElectrical103/21/2026
WHEELER, RElectrical103/21/2026
AYALA GUALLI, LUISElectrical103/21/2026
JCC CONSTRUCTION CORPPlumbing107/08/2026
FOY, REMERElectrical103/21/2026
GALA RESORATATION INCElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOEL PHAGOO ,PE, PLLC2416208/12/2025
20/20 INSPECTIONS INC1471106/13/2025
RI CONSULTING SERVICES IN8904110/21/2024
GAMILL ENGINEERING, P.C.1773108/28/2023
Building Lifecycle
All (87)Filed (10)Permit Issued (13)Signed Off (5)Facade (FISP) (15)Violation (31)Inspection (3)Special Inspection (10)
06/08/2026
Signed off — Alteration
M01268457-I1
04/07/2026
Violation issued (ECB, open)
Construction
02/19/2026
Cycle 10 facade report submitted
02/19/2026
Cycle 10 facade report signed — SWARMP
02/18/2026
Cycle 10 facade inspection completed
02/06/2026
Cycle 10 facade report submitted
02/05/2026
Cycle 10 facade inspection completed
02/05/2026
Cycle 10 facade report signed — UNSAFE
08/15/2025
Permit issued — Suspended Scaffold
M01268457-I1-SC
08/12/2025
Filed — Alteration
M01268457-I1
06/13/2025
Filed — Alteration
FACADE RESTORATION AS INDICATED ON DRAWINGS. THERE WILL BE NO CHANGE IN THE USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01227121-I1
06/13/2025
Special inspection requirement — Post-installed Anchors
JACOB HAAS
06/13/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
JACOB HAAS
06/13/2025
Special inspection requirement — Final
JACOB HAAS
06/13/2025
Special inspection requirement — Tenant Protection Plan Compliance
JACOB HAAS
06/13/2025
Special inspection requirement — Masonry
JACOB HAAS
02/10/2025
Signed off — Alteration
M01128339-I1
11/04/2024
Permit issued — Suspended Scaffold
M01128339-I1-SC
10/21/2024
Filed — Alteration
M01128339-I1
05/02/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/17/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/13/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
02/22/2024
Filed — Alteration
M01006730-S2
02/22/2024
Filed — Alteration
M01006730-S1
02/22/2024
Filed — Alteration
M01006730-I1
02/16/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
02/16/2024
Special inspection requirement — Tenant Protection Plan Compliance
09/25/2023
Permit issued — Plumbing
M00922389-I1-PL
08/28/2023
Filed — Alteration
M00922389-I1
12/02/2022
Violation issued (ECB, closed)
Local Law
02/22/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/12/2021
Violation issued (ECB, open)
Construction
08/09/2021
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00231412-I1
08/09/2021
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00231387-I1
08/09/2021
Signed off — Alteration
M00231369-I1
08/06/2021
Permit issued — Construction Fence
M00231412-I1-FN
07/29/2021
Violation issued (ECB, closed)
Construction
06/23/2021
Violation issued (ECB, closed)
Construction
04/01/2021
Permit issued — Construction Fence
M00231412-I1-FN
03/12/2021
Violation issued (ECB, closed)
Construction
01/25/2021
Permit issued — Construction Fence
M00231412-I1-FN
01/05/2021
Permit issued — Sidewalk Shed
M00231369-I1-SH
01/05/2021
Permit issued — Supported Scaffold
M00231387-I1-SF
04/03/2020
Permit issued — Sidewalk Shed
M00231369-I1-SH
04/02/2020
Permit issued — Supported Scaffold
M00231387-I1-SF
01/13/2020
Cycle 8 facade report submitted
12/18/2019
Cycle 8 facade report signed — SWARMP
11/20/2019
Cycle 8 facade inspection completed
09/25/2019
Permit issued — Sidewalk Shed
M00231369-I1-SH
09/24/2019
Filed — Alteration
M00231369-I1
09/20/2019
Permit issued — Construction Fence
M00231412-I1-FN
09/20/2019
Permit issued — Supported Scaffold
M00231387-I1-SF
09/19/2019
Filed — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00231412-I1
09/19/2019
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00231387-I1
09/19/2019
Special inspection requirement — Final
JOEL PHAGOO
09/19/2019
Special inspection requirement — Post-installed Anchors
JOEL PHAGOO
09/19/2019
Special inspection requirement — Final
JOEL PHAGOO
08/07/2019
Violation issued (ECB, closed)
Construction
07/03/2019
Violation issued (ECB, closed)
Construction
02/23/2019
Violation issued (ECB, closed)
Construction
Latest 60 of 87 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offZORIA HOUSING LLC08/15/2025
DOB NOWSuspended ScaffoldSigned-offZIRCON GROUP INC11/04/2024
DOB NOWPlumbingSigned-offJCC CONSTRUCTION CORP09/25/2023
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP08/06/2021
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP04/01/2021
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP01/25/2021
DOB NOWSidewalk ShedSigned-offSKYWORX CONTRACTING INC01/05/2021
DOB NOWSupported ScaffoldSigned-offSKYWORX CONTRACTING INC01/05/2021
DOB NOWSidewalk ShedSigned-offSKYWORX CONTRACTING INC04/03/2020
DOB NOWSupported ScaffoldSigned-offSKYWORX CONTRACTING INC04/02/2020
DOB NOWSidewalk ShedSigned-offSKYWORX CONTRACTING INC09/25/2019
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP09/20/2019
DOB NOWSupported ScaffoldSigned-offSKYWORX CONTRACTING INC09/20/2019
BISOTISSUEDNEELAM CONSTRUCTION CORP08/04/2021
BISOTISSUEDNEELAM CONSTRUCTION CORP03/15/2021
BISOTISSUEDNEELAM CONSTRUCTION CORP03/15/2021
BISOTISSUEDNEELAM CONSTRUCTION CORP03/01/2021
BISOTISSUEDNEELAM CONSTRUCTION CORP07/28/2020
BISOTISSUEDNEELAM CONSTRUCTION CORP05/14/2020
BISPLISSUEDNYC HOUSING AUTHORITY02/06/2013
BISPLISSUEDNYC HOUSING AUTHORITY09/27/2012
BISFPISSUEDRELIABLE FIRE PROT. INC03/11/2011
BISEQISSUEDSAFEWAY STEEL PRODUCTS10/08/2002
BISEQISSUEDKMK CONSTRUCTION INC06/24/2002
BISPLISSUEDCAPE PLUMBING INC12/19/2001
BISEQISSUEDAIM CONSTRUCTION & CONTRACTING04/10/2001
BISOTISSUEDSTOW CONTRACTING CORP01/31/2001
BISOTISSUEDNAP CONSTRUCTION CO.09/07/2000
BISPLISSUEDCAPE PLUMBING INC07/26/2000
BISOTISSUEDNAP CONSTRUCTION CO.07/26/2000
BISEQISSUEDAIM CONSTRUCTION & CONTRACTING03/06/2000
BISEQISSUEDAIM CONSTRUCTION & CONTRACTING08/26/1999
BISOTISSUEDDAFRA GENERAL CONTRACTING INC01/28/1993
BISPLISSUEDFORSYTHE P&H CORP10/07/1992
BISOTISSUEDDAFRA GENERAL CONTRACTING INC02/18/1992
8 projects · most recent 01/08/2026
General Wiring
FiledStatusContractorScope
01/08/2026Permit IssuedLIT MODE ELECL CONTG INC—
12/18/2025Permit IssuedLIT MODE ELECL CONTG INC—
03/08/2023CompleteGILSTON ELEC'L CONTNG LLCGeneral Wiring
07/10/2021Permit IssuedROBERT CHIMENTI3 meters, 1 new_meters
07/07/2021Permit IssuedROBERT CHIMENTI4 meters, 1 new_meters
06/08/2020CompleteAMIN ELECTRICAL CORP—
09/24/2019CompleteRAIDEN ELECTRIC LLC—
02/06/2019CompleteAMIN ELECTRICAL CORP—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
05/02/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/17/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/13/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
06/13/2025Post-installed AnchorsJACOB HAASspecial
06/13/2025Structural Stability – Alterations of existing buildingsJACOB HAASspecial
06/13/2025FinalJACOB HAASprogress
06/13/2025Tenant Protection Plan ComplianceJACOB HAASspecial
06/13/2025MasonryJACOB HAASspecial
02/16/2024Fire-Resistant Penetrations and Joints—special
02/16/2024Tenant Protection Plan Compliance—special
09/19/2019FinalJOEL PHAGOOprogress
09/19/2019Post-installed AnchorsJOEL PHAGOOspecial
09/19/2019FinalJOEL PHAGOOprogress
▾Documents — 150 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch7
08/29/2026M00922389-I1Request digital key ↗
08/27/2026M01006730-I1Request digital key ↗
08/27/2026M01006730-S2Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/05/2026M00231412-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00231369-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/05/2026M00231387-I1Request digital key ↗
▸Applications & Permits20
▸BISPLAN / WORK APPROVAL APPLICATION14
10/15/2021140829138Open ↗
04/15/2019140829138Open ↗
04/11/2019140829138Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION6
03/01/2021140829138Open ↗
05/14/2020140829138Open ↗
02/06/2013140053448Open ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications26
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/05/2026M00231369-I1Open ↗
08/29/2026M00922389-I1Open ↗
08/27/2026M01006730-I1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
02/12/2020140829138Open ↗
06/28/2013140053448Open ↗
03/20/2013121392493Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
04/15/2019140829138Open ↗
04/11/2019140829138Open ↗
09/28/2012121392493Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
02/08/2019140829138Open ↗
02/06/2013140053448Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
02/08/2019140829138Open ↗
02/06/2013140053448Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
02/08/2019140829138Open ↗
02/06/2013140053448Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/02/2026M00231387-I1Open ↗
08/28/2026M00231412-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
09/28/2012121392493Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/02/2026M00231387-I1Open ↗
▸Trade Schedules & Equipment11
▸BISSCHEDULE B - PLUMBING6
02/08/2019140829138Open ↗
03/06/2013140053448Open ↗
02/25/2013140053448Open ↗
Showing 3 of 6 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA3
06/15/2018123162825Open ↗
01/09/2018123054489Open ↗
07/27/2011120609617Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
12/13/2012121392493Open ↗
07/27/2011120609617Open ↗
▸Safety & Tenant Protection4
▸DOB NOWTenant Protection Plan3
08/13/2026M00231369-I1Open ↗
08/13/2026M00231412-I1Open ↗
08/13/2026M00231387-I1Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
02/08/2019140829138Open ↗
▸Environmental & Asbestos8
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
10/10/2017123162825Open ↗
06/19/2017123054489Open ↗
02/06/2013140053448Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORMPRIOR TO SIGN OFF: TRU0616MN201
09/23/2021140829138Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
02/14/2011120609617Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
02/08/2019140829138Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/29/2026M00922389-I1Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
09/23/2021140829138Open ↗
09/23/2021140829138Open ↗
05/14/2020140829138Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
02/08/2019140829138Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
09/23/2021140829138Open ↗
▸BISNYCECC ANALYSIS1
02/08/2019140829138Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY7
09/23/2021140829138Open ↗
09/23/2021140829138Open ↗
09/23/2021140829138Open ↗
Showing 3 of 7 on file for this type
▸Approvals, Objections & Sign-offs25
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter10
09/05/2026M00231369-I1Open ↗
08/29/2026M00922389-I1Open ↗
08/26/2026M01128339-I1Open ↗
Showing 3 of 10 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
11/19/2021140829138Open ↗
08/15/2019123162825Open ↗
08/03/2018123162825Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
07/30/2020140829138Open ↗
05/14/2020140829138Open ↗
02/27/2019140829138Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)3
08/13/2026M00231369-I1Open ↗
08/13/2026M00231412-I1Open ↗
08/13/2026M00231387-I1Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
09/28/2012121392493Open ↗
02/14/2011120609617Open ↗
▸BISSUPERSEDING LETTER1
03/01/2021140829138Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT10
02/08/2019140829138Open ↗
08/03/2018123162825Open ↗
01/24/2018123054489Open ↗
Showing 3 of 10 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
09/23/2021140829138Open ↗
▸Filing & Intake Forms15
▸BISBOROUGH INTAKE FORM7
03/01/2021140829138Open ↗
08/15/2019123162825Open ↗
04/11/2019140829138Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING COVER SHEET4
10/10/2017123162825Open ↗
06/19/2017123054489Open ↗
09/28/2012121392493Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION2
02/25/2013140053448Open ↗
01/07/2013121392493Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
02/08/2019140829138Open ↗
02/06/2013140053448Open ↗
▸Other Documents6
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
10/10/2017123162825Open ↗
06/20/2017123054489Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026M01268457-I1Open ↗
08/13/2026M01128339-I1Open ↗
▸DOB NOWCalculations2
08/13/2026M01268457-I1Open ↗
08/13/2026M01128339-I1Open ↗