← Back
Two family brick
4508 GLENDALE COURT
BROOKLYN · Flatlands · BIN 3213383
💬 Discuss this project
1945Year Built
2Stories
B1Building Class
R4Zoning
1,560 sfGross Floor Area
2Units
7 Open Violations 5 unresolved · 2 paperwork only ▸FDNY Report ↗
Two family brick · 1,892 sf lot · 0.82 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Floor 28p · 1 filing · 11 docs
Floor 16p · 1 filing · 11 docs
Cellar10p · 1 filing · 11 docs
Site & exterior6p · 1 filing · 11 docs
Filed — no permit issued26p · 3 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/12/2015$406K—GOSHEN MORTGAGE REO LLC → Private party$260/sf building
10/18/2013$309K—Private party → GOSHEN MORTGAGE REO LLC$198/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PWR ENGINEERING DESIGN DPC907/12/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KMP DESIGN ENGINEERING403/21/2026
KP CONSULTING ENGINEER803/21/2026
PWR Engineering Design DPC103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RM ELECTRIC CO., INC.Electrical103/22/2026
SEVA PROPERTY DEVLOPMENTGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IP CONCRETE TESTING AND I6252202/26/2026
Building Lifecycle
All (123)Filed (9)Permit Issued (1)Violation (7)Objection (76)Special Inspection (30)
08/11/2026
Objection resolved — Addressed
08/10/2026
Objection resolved — Addressed
07/29/2026
Objection raised — Energy
07/27/2026
Objection resolved — Addressed
07/25/2026
Objection resolved — Addressed
07/25/2026
Objection resolved — Addressed
07/25/2026
Objection resolved — Addressed
07/25/2026
Objection resolved — Addressed
07/25/2026
Objection resolved — Addressed
07/25/2026
Objection resolved — Addressed
07/14/2026
Objection raised — Other
07/13/2026
Objection raised — Cost
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Fire_Protection
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Structural
07/13/2026
Objection raised — Mechanical
07/12/2026
Filed — Alteration CO
CONVERT GARAGE INTO HABITABLE SPACE IN EXISTING 2 DU BUILDING. A 3 PCS BATHROOM AT CELLAR. NO CHANGE ON BULK.
B01362966-S3
07/08/2026
Filed — Alteration CO
CONVERT GARAGE INTO HABITABLE SPACE IN EXISTING 2 DU BUILDING. A 3 PCS BATHROOM AT CELLAR. NO CHANGE ON BULK.
B01362966-S2
06/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/02/2026
Objection resolved — Addressed
06/01/2026
Violation issued (ECB, open)
Construction
06/01/2026
Violation issued (ECB, open)
Unknown
05/28/2026
Objection resolved — Addressed
05/27/2026
Objection raised — Other
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/03/2026
Objection resolved — Addressed
03/30/2026
Objection resolved — Addressed
03/30/2026
Objection resolved — Addressed
03/30/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
03/11/2026
Objection raised — Zoning
03/11/2026
Objection raised — Scope
03/11/2026
Objection raised — Other
03/11/2026
Objection raised — Other
03/11/2026
Objection raised — Scope
03/11/2026
Objection raised — Other
03/10/2026
Special inspection requirement — Permanent certificate
INDARDEO PARBHUNATH
02/26/2026
Filed — Alteration CO
CONVERT GARAGE INTO HABITABLE SPACE IN EXISTING 2 DU BUILDING. A 3 PCS BATHROOM AT CELLAR. NO CHANGE ON BULK.
B01362966-I1
02/25/2026
Special inspection requirement — Air barrier - visual inspection
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Interior lighting power
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Energy Code Compliance Inspections
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Fenestration areas
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Maintenance information
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Fenestration air leakage
INDARDEO PARBHUNATH
02/25/2026
Special inspection requirement — Insulation placement and R values
INDARDEO PARBHUNATH
08/27/2025
Objection raised — Other
08/26/2025
Objection resolved — Addressed
08/26/2025
Objection resolved — Addressed
08/26/2025
Objection resolved — Addressed
08/25/2025
Objection raised — Other
08/25/2025
Objection resolved — Addressed
08/25/2025
Objection raised — Other
08/25/2025
Objection resolved — Addressed
08/25/2025
Objection raised — Other
08/25/2025
Objection raised — Other
Latest 60 of 123 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedSEVA PROPERTY DEVLOPMENT10/21/2024
1 project · most recent 07/12/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/12/2026——Heating and Air Conditioning Systems
Heat / Cool
Gree V1R12HP115V1B0 12,000 BTU · Condensing Unit ×2
Mitsubishi Electric MUZ-WR18NA 18,000 BTU · Condensing Unit ×1
MXZ-3C30NA3-U1 30,000 BTU · Condensing Unit ×1
2 projects · most recent 07/12/2026
Gas Water/Sanitary
FiledStatusContractorScope
07/12/2026——Gas, Water/Sanitary
01/03/2025——Gas, Water/Sanitary
1 project · most recent 07/23/2026
General Wiring
FiledStatusContractorScope
07/23/2026Permit IssuedRM ELECTRIC CO., INC.General Wiring
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
06/16/2026Fire-Resistant Penetrations and Joints—special
03/30/2026Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
03/10/2026Permanent certificateINDARDEO PARBHUNATHenergy_progress
02/25/2026Air barrier - visual inspectionINDARDEO PARBHUNATHenergy_progress
02/25/2026Interior lighting powerINDARDEO PARBHUNATHenergy_progress
02/25/2026Fire-Resistance Rated ConstructionINDARDEO PARBHUNATHprogress
02/25/2026Energy Code Compliance InspectionsINDARDEO PARBHUNATHprogress
02/25/2026Fenestration areasINDARDEO PARBHUNATHenergy_progress
02/25/2026Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
02/25/2026Maintenance informationINDARDEO PARBHUNATHenergy_progress
02/25/2026Fenestration and door U-factor and product ratingsINDARDEO PARBHUNATHenergy_progress
02/25/2026Fenestration air leakageINDARDEO PARBHUNATHenergy_progress
02/25/2026Insulation placement and R valuesINDARDEO PARBHUNATHenergy_progress
07/21/2025Maintenance information—energy_progress
07/21/2025Permanent certificate—energy_progress
06/25/2025Fire-Resistant Penetrations and Joints—special
06/25/2025Structural Stability – Alterations of existing buildings—special
06/25/2025Energy Code Compliance Inspections—progress
06/25/2025Fire-Resistance Rated Construction—progress
06/25/2025Fenestration and door U-factor and product ratings—energy_progress
06/25/2025Insulation placement and R values—energy_progress
06/25/2025Fenestration areas—energy_progress
06/25/2025Interior lighting power—energy_progress
06/25/2025Fenestration air leakage—energy_progress
06/25/2025Air barrier - visual inspection—energy_progress
Latest 25 of 35.
▾Documents — 48 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/23/2026B01148954-I1Request digital key ↗
08/21/2026B00958763-S5Request digital key ↗
08/15/2026B00958763-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWRestrictive Declaration/Easement 13
08/14/2026B01362966-S2Open ↗
08/14/2026B01362966-S3Open ↗
08/13/2026B01362966-I1Open ↗
▸Seals & Professional Certifications21
▸DOB NOWProgress Inspector Seal & Signature10
08/24/2026B01362966-I1Open ↗
08/24/2026B01362966-I1Open ↗
08/24/2026B01362966-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/23/2026B01148954-S1Open ↗
08/23/2026B01148954-I1Open ↗
08/21/2026B00958763-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026B01362966-I1Open ↗
08/24/2026B01362966-I1Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist4
08/15/2026B00958763-I1Open ↗
08/14/2026B00958763-S4Open ↗
08/14/2026B01362966-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/23/2026B01148954-I1Open ↗
08/15/2026B00958763-I1Open ↗
08/14/2026B00958763-S4Open ↗
Showing 3 of 8 on file for this type
▸Other Documents3
▸DOB NOWProperty Ownership Certification3
08/23/2026B01148954-I1Open ↗
08/15/2026B00958763-I1Open ↗
08/14/2026B01362966-I1Open ↗