← Back
One family attached or semi-detached
455 EAST 56 STREET
BROOKLYN · East Flatbush-Rugby · BIN 3105576
💬 Discuss this project
1955Year Built
1Stories
A5Building Class
R4Zoning
1,566 sfGross Floor Area
1Units
One family attached or semi-detached · 2,167 sf lot · 0.72 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 8 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/01/2017$480K—— → —$306/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR105/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281105/22/2026
Building Lifecycle
All (12)Filed (1)Permit Issued (1)Inspection (3)Special Inspection (7)
09/09/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/03/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/03/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/28/2026
Permit issued — Solar
B01406501-I1-SL
05/22/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 11 modules, 4.51 KW
B01406501-I1
05/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
05/22/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
05/22/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
05/22/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
05/22/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
05/22/2026
Special inspection requirement — Final
Mina Makar
05/22/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR05/28/2026
2 projects · most recent 05/22/2026
FiledStatusContractorScope
05/22/2026Permit IssuedISLAND ELECTRIC CORP—
02/10/2026CompleteE D ELECTRICAL INC—
1 project · most recent 05/22/2026
FiledStatusContractorScope
05/22/2026Permit IssuedMOMENTUM SOLAR11 panels, 4.51 kw, 2,167 roof_area_sqft
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
09/09/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/03/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/03/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
05/22/2026Fire-Resistant Penetrations and JointsMina Makarspecial
05/22/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
05/22/2026Post-installed AnchorsMina Makarspecial
05/22/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
05/22/2026Energy Code Compliance InspectionsMina Makarprogress
05/22/2026FinalMina Makarprogress
05/22/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/16/2026B01406501-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026B01406501-I1Open ↗
08/28/2026B01406501-I1Open ↗
08/28/2026B01406501-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026B01406501-I1Open ↗
08/28/2026B01406501-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/16/2026B01406501-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/16/2026B01406501-I1Open ↗