← Back
Miscellaneous two family
457 49 STREET
BROOKLYN · BIN 3012614
💬 Discuss this project
1901Year Built
2Stories
B9Building Class
R6BZoning
1,740 sfGross Floor Area
2Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
Miscellaneous two family · Owner of record: WU'S 457 LLC · 2,003 sf lot · 0.87 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Roof2p · 1 filing · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
WU'S 457 LLC103/22/2026
457 LI INC303/22/2026
467 LI INC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/08/2025$1.3M—— → —$764/sf building
03/02/2021$1.2M—Private party → 457 LI INC$678/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JX FLAME SOLUTION INC804/06/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
VIBEN BUILDING1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW LAND CONSTRUCTION NYGeneral Contractor104/09/2026
TIMING CONSTRUCTION TEAM*General Contractor107/08/2026
CATMAN PLUMBING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JX FLAME SOLUTION INC7286704/06/2026
Building Lifecycle
All (61)Filed (8)Permit Issued (3)Signed Off (3)Violation (9)Inspection (8)Special Inspection (30)
06/22/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/06/2026
Signed off — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-I1
05/05/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
05/04/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/29/2026
Signed off — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-S1
04/27/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIE ZHU
04/07/2026
Special inspection requirement — HVAC-R and service water heating system controls
JIE ZHU
04/07/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
JIE ZHU
04/07/2026
Special inspection requirement — HVAC-R and service water heating equipment
JIE ZHU
04/07/2026
Special inspection requirement — Energy Code Compliance Inspections
JIE ZHU
04/06/2026
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-P5
04/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIE ZHU
04/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
JIE ZHU
04/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
JIE ZHU
04/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
JIE ZHU
04/06/2026
Special inspection requirement — Energy Code Compliance Inspections
JIE ZHU
03/11/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/25/2026
Special inspection requirement — Interior lighting power
JIE ZHU
02/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIE ZHU
02/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
JIE ZHU
02/25/2026
Special inspection requirement — Energy Code Compliance Inspections
JIE ZHU
02/25/2026
Special inspection requirement — Fenestration areas
JIE ZHU
02/25/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
JIE ZHU
02/23/2026
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-P4
02/12/2026
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-P3
02/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIE ZHU
02/12/2026
Special inspection requirement — Energy Code Compliance Inspections
JIE ZHU
02/12/2026
Special inspection requirement — Fenestration areas
JIE ZHU
02/12/2026
Special inspection requirement — Interior lighting power
JIE ZHU
02/12/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
JIE ZHU
02/12/2026
Special inspection requirement — Fire-Resistance Rated Construction
JIE ZHU
02/09/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
02/05/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/04/2026
Violation issued (ECB, closed)
Unknown
01/14/2026
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-P2
01/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JIE ZHU
01/14/2026
Special inspection requirement — Energy Code Compliance Inspections
JIE ZHU
01/14/2026
Special inspection requirement — HVAC-R and service water heating equipment
JIE ZHU
01/14/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
JIE ZHU
01/14/2026
Special inspection requirement — HVAC-R and service water heating system controls
JIE ZHU
10/21/2025
Permit issued — Plumbing
B01286868-S1-PL
10/20/2025
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-S1
10/17/2025
Permit issued — General Construction
B01286868-I1-GC
10/07/2025
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-P1
10/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/07/2025
Special inspection requirement — Energy Code Compliance Inspections
10/07/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
09/19/2025
Filed — Alteration
RENOVATION OF AN EXISTING BUILDING AT CELLAR BASEMENT 1ST AND 2ND FLOOR. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION. PLUMBING WORK WILL BE FILED UNDER SEPARATE APPLICATION.
B01286868-I1
12/14/2023
Signed off — Alteration
B00845622-I1
12/12/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
09/14/2023
Violation issued (HPD, closed)
C
09/14/2023
Violation issued (HPD, closed)
C
09/14/2023
Violation issued (HPD, open)
C
09/14/2023
Violation issued (HPD, open)
B
04/12/2023
Permit issued — General Construction
B00845622-I1-GC
03/19/2023
Filed — Alteration
B00845622-I1
03/15/2023
Violation issued (ECB, closed)
Quality of Life
03/15/2023
Violation issued (ECB, closed)
Quality of Life
03/15/2023
Violation issued (ECB, closed)
Construction
Latest 60 of 61 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCATMAN PLUMBING INC10/21/2025
DOB NOWGeneral ConstructionSigned-offNEW LAND CONSTRUCTION NY10/17/2025
DOB NOWGeneral ConstructionSigned-offTIMING CONSTRUCTION TEAM*04/12/2023
1 project · most recent 04/06/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
04/06/2026Signed-offCATMAN PLUMBING INCGas, Storm, Water/Sanitary
2 projects · most recent 02/23/2026
General Wiring
FiledStatusContractorScope
02/23/2026CompleteR & T ELECTRICAL CORPGeneral Wiring
03/24/2023CompleteKJK ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
06/22/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/05/2026Pass-Final General Construction Non-Directive 14PassView ↗
05/04/2026Pass-Final General Construction Non-Directive 14PassView ↗
04/27/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/11/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/09/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/05/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/12/2023Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
04/07/2026Fire-Resistant Penetrations and JointsJIE ZHUspecial
04/07/2026HVAC-R and service water heating system controlsJIE ZHUenergy_progress
04/07/2026HVAC-R and service water piping design and insulationJIE ZHUenergy_progress
04/07/2026HVAC-R and service water heating equipmentJIE ZHUenergy_progress
04/07/2026Energy Code Compliance InspectionsJIE ZHUprogress
04/06/2026Fire-Resistant Penetrations and JointsJIE ZHUspecial
04/06/2026HVAC-R and service water piping design and insulationJIE ZHUenergy_progress
04/06/2026HVAC-R and service water heating equipmentJIE ZHUenergy_progress
04/06/2026HVAC-R and service water heating system controlsJIE ZHUenergy_progress
04/06/2026Energy Code Compliance InspectionsJIE ZHUprogress
02/25/2026Interior lighting powerJIE ZHUenergy_progress
02/25/2026Fire-Resistant Penetrations and JointsJIE ZHUspecial
02/25/2026Fire-Resistance Rated ConstructionJIE ZHUprogress
02/25/2026Energy Code Compliance InspectionsJIE ZHUprogress
02/25/2026Fenestration areasJIE ZHUenergy_progress
02/25/2026Fenestration and door U-factor and product ratingsJIE ZHUenergy_progress
02/12/2026Fire-Resistant Penetrations and JointsJIE ZHUspecial
02/12/2026Energy Code Compliance InspectionsJIE ZHUprogress
02/12/2026Fenestration areasJIE ZHUenergy_progress
02/12/2026Interior lighting powerJIE ZHUenergy_progress
02/12/2026Fenestration and door U-factor and product ratingsJIE ZHUenergy_progress
02/12/2026Fire-Resistance Rated ConstructionJIE ZHUprogress
01/14/2026Fire-Resistant Penetrations and JointsJIE ZHUspecial
01/14/2026Energy Code Compliance InspectionsJIE ZHUprogress
01/14/2026HVAC-R and service water heating equipmentJIE ZHUenergy_progress
Latest 25 of 33.
▾Documents — 39 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/27/2026B00845622-I1Request digital key ↗
08/17/2026B01286868-S1Request digital key ↗
08/17/2026B01286868-P5Request digital key ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications23
▸DOB NOWProgress Inspector Seal & Signature10
09/02/2026B01286868-I1Open ↗
09/02/2026B01286868-I1Open ↗
09/01/2026B01286868-P3Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/27/2026B00845622-I1Open ↗
08/17/2026B01286868-P5Open ↗
08/17/2026B01286868-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/02/2026B01286868-I1Open ↗
09/01/2026B01286868-P3Open ↗
08/31/2026B01286868-P5Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/27/2026B00845622-I1Open ↗
08/17/2026B01286868-P5Open ↗
08/17/2026B01286868-P2Open ↗
Showing 3 of 8 on file for this type