| Owner | Filings | Most Recent |
|---|---|---|
| CAVU PROPERTY GROUP | 25 | 07/08/2026 |
| OWNER'S REP | 8 | 07/08/2026 |
| CLASSON MARKS REALTY | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IMC ARCHITECTURE DPC | 19 | 03/29/2024 |
| FLORINELA MURESAN | 2 | 03/26/2024 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 05/19/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 2 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 21 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROYAL HOME IMPROVEMENTS INC | General Contractor | 17 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 4 | 07/08/2026 |
| GWT ENTERPRISES INC | General Contractor | 3 | 03/21/2026 |
| SOLAS ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| M & Y DEVELOPERS, INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 15 | 03/29/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | ROYAL HOME IMPROVEMENTS I | 02/22/2024 |
| DOB NOW | Sprinklers | Signed-off | SAFETY FIRE SPRINKLER CORP | 02/22/2024 |
| DOB NOW | Curb Cut | Signed-off | ROYAL HOME IMPROVEMENTS I | 02/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ROYAL HOME IMPROVEMENTS I | 02/06/2024 |
| DOB NOW | Supported Scaffold | Signed-off | GWT ENTERPRISES INC | 01/09/2024 |
| DOB NOW | Construction Fence | Signed-off | ROYAL HOME IMPROVEMENTS I | 12/19/2023 |
| DOB NOW | General Construction | Permit Issued | ROYAL HOME IMPROVEMENTS I | 08/23/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 05/20/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 05/20/2023 |
| DOB NOW | Structural | Signed-off | ROYAL HOME IMPROVEMENTS I | 05/04/2023 |
| DOB NOW | Foundation | Signed-off | ROYAL HOME IMPROVEMENTS I | 03/06/2023 |
| DOB NOW | Support of Excavation | Signed-off | ROYAL HOME IMPROVEMENTS I | 03/02/2023 |
| DOB NOW | Foundation | Signed-off | ROYAL HOME IMPROVEMENTS I | 03/01/2023 |
| DOB NOW | Support of Excavation | Signed-off | ROYAL HOME IMPROVEMENTS I | 01/11/2023 |
| DOB NOW | Construction Fence | Signed-off | ROYAL HOME IMPROVEMENTS I | 12/20/2022 |
| DOB NOW | Foundation | Permit Issued | M & Y DEVELOPERS, INC | 05/26/2022 |
| BIS | PL | ISSUED | THE PLBG COPMPANY INC | 07/30/2003 |
| BIS | CC | ISSUED | GALVIN BROS. INC. | 07/01/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/29/2024 | Signed-off | SAFETY FIRE SPRINKLER COR | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2023 | Complete | POWER DIRECT ELECTRIC INC | — |
| 05/23/2023 | Complete | D & W ELECTRICAL CONT COR | General Wiring |
| 02/27/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/01/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/21/2024 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 05/21/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/21/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/17/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/05/2024 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 04/05/2024 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 04/05/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 04/05/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 04/05/2024 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 04/05/2024 | Permanent certificate | FAHAD FATEH | energy_progress |
| 04/05/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 01/26/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 01/26/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 01/26/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 01/26/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 01/26/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 01/26/2024 | Masonry | FAHAD FATEH | special |
| 01/26/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 01/26/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 01/26/2024 | Wall Panels, Curtain Walls, and Veneers | FAHAD FATEH | special |
| 01/26/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 01/26/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 01/26/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 01/26/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 01/26/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 01/26/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 01/26/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 01/26/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 01/26/2024 | Masonry | FAHAD FATEH | special |