← Back
One story retail building
Gateway Center
459 GATEWAY DRIVE · BIN 3348831
💬 Discuss this project
2001Year Built
1Stories
K1Building Class
C4-2Zoning
37,833 sfGross Floor Area
1Units
LL97 Covered1 Open Violation ▸FDNY Report ↗
One story retail building · Owner of record: GATEWAY CENTER PROPERTIES I, L.L.C. · 37,833 sf lot · 1 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction32p · 10 filings · 20 docs
Floor 1Under Construction35p · 8 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GATEWAY CENTER PROPERTIES, LLC903/22/2026
Z BUILDERS203/22/2026
COMMISSIONER OF GENERAL SERVICES403/21/2026
GATEWAY CTR PROPERTIES PHASE II203/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SIGNS CAD403/21/2026
GEORGE E BERGER ASSOCIATES2003/21/2026
DOMANI CONSULTING2203/21/2026
WHIDDEN SILVER2003/21/2026
A1 EXPEDITING SERVICE CORP.1803/21/2026
NEW YORK SIGN CONSULTANTS1003/21/2026
D R BROWN603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LORICH CONSTRUCTION MANAGEMENTGeneral Contractor1107/08/2026
Z BUILDERS LLCGeneral Contractor607/08/2026
MAUCERI SIGNScaffold507/08/2026
SIGNSTAR NYCScaffold307/08/2026
SITEWORKS CONSULTING LLCGeneral Contractor307/08/2026
CMA PLUMBING & HEATING INFire Protection207/08/2026
BEDROCK MECHANICAL INCFire Protection107/08/2026
NEW YORK PLUMBING-HEATINGGeneral Contractor104/09/2026
NEXUS ACCESS LLCGeneral Contractor108/20/2026
CKC CONTRACTING CORP DBAElectrical103/22/2026
PROFF ELECTRICAL LLCElectrical103/22/2026
NEW YORK PLBG-HTG-COOL CFire Protection107/08/2026
BEDROCK PLBG. & HTG., INCPlumbing107/08/2026
J. CAIAZZO PLBG & HTG CORPlumbing107/08/2026
NEW YORK PLBG-HTG-COOLINGPlumbing108/26/2026
JEM ELEC'L CONTR. CORPElectrical103/22/2026
SIGNS CADScaffold107/08/2026
A & M WARSHAW PLBG & HTGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ATLAS ATC ENGINEERING INC8011507/07/2026
CONCESSI ENGINEERING, P.C5401010/02/2025
GRANT ENGINEERING2627610/25/2024
GEA CONSULTING ENGINEERS945210/17/2024
MILROSE CONSULTANTS LLC2003508/28/2024
ACTIVE DESIGN GROUP ENGIN6666203/28/2024
Building Lifecycle
All (223)Filed (53)Permit Issued (33)Signed Off (28)Violation (10)Inspection (31)Objection (38)Special Inspection (30)
08/07/2026
Special inspection requirement — Insulation placement and R values
RONALD GRAPIN
08/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RONALD GRAPIN
08/07/2026
Special inspection requirement — Fire-Resistance Rated Construction
RONALD GRAPIN
08/07/2026
Special inspection requirement — Fenestration air leakage
RONALD GRAPIN
08/07/2026
Special inspection requirement — Air barrier - visual inspection
RONALD GRAPIN
08/07/2026
Special inspection requirement — Fenestration areas
RONALD GRAPIN
08/07/2026
Special inspection requirement — Preliminary
RONALD GRAPIN
08/07/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
RONALD GRAPIN
07/28/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/24/2026
Objection raised — Scope
07/24/2026
Objection resolved — Addressed
07/07/2026
Filed — Alteration CO
It is proposed to demise a single retail tenant space into multi tenant spaces and change existing Use Group 10 to Use Group 6 as shown on plans. All tenant work to be filed under separate applications.
B00946629-P7
07/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RONALD GRAPIN
07/07/2026
Special inspection requirement — Preliminary
RONALD GRAPIN
07/07/2026
Special inspection requirement — Insulation placement and R values
RONALD GRAPIN
07/07/2026
Special inspection requirement — Fenestration air leakage
RONALD GRAPIN
07/07/2026
Special inspection requirement — Fire-Resistance Rated Construction
RONALD GRAPIN
07/07/2026
Special inspection requirement — Fenestration areas
RONALD GRAPIN
07/07/2026
Special inspection requirement — Air barrier - visual inspection
RONALD GRAPIN
07/07/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
RONALD GRAPIN
07/06/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/13/2026
Permit issued — General Construction
B01398391-I1-GC
05/12/2026
Filed — Alteration
B01398391-I1
05/11/2026
Signed off — Alteration
ERECT A SET OF ILLUMINATED BUSINESS ACCESSORY CHANNEL LETTERS ON A RACEWAY.
B01118459-I1
05/08/2026
Special inspection requirement — Final
Ryan Hung
05/06/2026
Filed — Alteration
ERECT A SET OF ILLUMINATED BUSINESS ACCESSORY CHANNEL LETTERS ON A RACEWAY.
B01118459-P2
05/01/2026
Special inspection requirement — Final
Ryan Hung
04/20/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/08/2026
Violation issued (FDNY_ORDER, closed)
04/08/2026
Violation issued (FDNY_ORDER, closed)
04/08/2026
Violation issued (FDNY_ORDER, closed)
03/05/2026
Permit issued — General Construction
B00946629-I1-GC
02/13/2026
Signed off — Alteration CO
It is proposed to demise a single retail tenant space into multi tenant spaces and change existing Use Group 10 to Use Group 6 as shown on plans. All tenant work to be filed under separate applications.
B00946629-S5
02/09/2026
Violation issued (FDNY_ORDER, closed)
02/09/2026
Violation issued (FDNY_ORDER, closed)
02/06/2026
Signed off — Alteration
MECHANICAL WORK IN CONJUNCTION WITH DEMISING OF EXISTING BUILDING. WORK TO INCLUDE INSTALLATION OF NEW ROOFTOP UNITS AND ASSOCIATED PIPING, DUCTWORK EXHAUST FANS & REFRIGERATION EQUIPMENT. CHICK FIL A # 5655.
B01049495-I1
12/15/2025
Signed off — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-S2
11/06/2025
Signed off — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-S1
10/31/2025
Signed off — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-I1
10/29/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/27/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/21/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/21/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/03/2025
Special inspection requirement — Maintenance information
Robert Concessi
10/03/2025
Special inspection requirement — HVAC-R and service water heating system controls
Robert Concessi
10/03/2025
Special inspection requirement — Interior lighting power
Robert Concessi
10/03/2025
Special inspection requirement — Lighting controls
Robert Concessi
10/03/2025
Special inspection requirement — Mechanical Systems
Robert Concessi
10/03/2025
Special inspection requirement — Final
Robert Concessi
10/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Robert Concessi
10/03/2025
Special inspection requirement — HVAC-R and service water heating equipment
Robert Concessi
10/02/2025
Filed — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-P3
10/02/2025
Filed — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-P6
10/01/2025
Special inspection requirement — Post-installed Anchors
Robert Concessi
10/01/2025
Special inspection requirement — Final
THOMAS BERKOSKI
10/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Concessi
09/30/2025
Filed — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-P5
08/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Concessi
07/28/2025
Signed off — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-S3
07/16/2025
Filed — Alteration
Modification to sprinkler and plumbing systems for new Optimum Store (Altice) as shown in drawing filed herewith.
B01095308-P4
Latest 60 of 223 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNEXUS ACCESS LLC05/13/2026
DOB NOWGeneral ConstructionPermit IssuedNEW YORK PLUMBING-HEATING03/05/2026
DOB NOWSignSigned-offSIGNS CAD CORP12/12/2024
DOB NOWSprinklersSigned-offBEDROCK MECHANICAL INC11/15/2024
DOB NOWSprinklersSigned-offBEDROCK PLBG. & HTG., INC11/14/2024
DOB NOWGeneral ConstructionPermit IssuedZ BUILDERS LLC10/25/2024
DOB NOWMechanical SystemsSigned-offSITEWORKS CONSULTING LLC09/26/2024
DOB NOWGeneral ConstructionSigned-offSITEWORKS CONSULTING LLC09/26/2024
DOB NOWStructuralSigned-offSITEWORKS CONSULTING LLC09/26/2024
DOB NOWSignSigned-offMAUCERI SIGN CO., INC09/11/2024
DOB NOWSignSigned-offMAUCERI SIGN CO., INC09/11/2024
DOB NOWSignSigned-offMAUCERI SIGN CO., INC09/11/2024
DOB NOWSignSigned-offMAUCERI SIGN CO., INC09/11/2024
DOB NOWSignSigned-offMAUCERI SIGN CO., INC09/11/2024
DOB NOWConstruction FenceSigned-offZ BUILDERS LLC08/22/2024
DOB NOWSignSigned-offSIGNSTAR NYC08/09/2024
DOB NOWSignSigned-offSIGNSTAR NYC08/09/2024
DOB NOWSignSigned-offSIGNSTAR NYC08/09/2024
DOB NOWSprinklersSigned-offCMA PLUMBING & HEATING IN08/07/2024
DOB NOWSprinklersSigned-offNEW YORK PLBG-HTG-COOL C07/31/2024
DOB NOWPlumbingSigned-offA & M WARSHAW PLBG & HTG07/18/2024
DOB NOWMechanical SystemsSigned-offLORICH CONSTRUCTION MANAGEMENT07/17/2024
DOB NOWSprinklersSigned-offCMA PLUMBING & HEATING IN07/16/2024
DOB NOWStructuralSigned-offLORICH CONSTRUCTION MANAGEMENT07/12/2024
DOB NOWGeneral ConstructionSigned-offLORICH CONSTRUCTION MANAGEMENT07/12/2024
DOB NOWMechanical SystemsSigned-offLORICH CONSTRUCTION MANAGEMENT07/12/2024
DOB NOWGeneral ConstructionSigned-offLORICH CONSTRUCTION MANAGEMENT07/12/2024
DOB NOWGeneral ConstructionSigned-offLORICH CONSTRUCTION MANAGEMENT06/24/2024
DOB NOWStructuralSigned-offZ BUILDERS LLC06/18/2024
DOB NOWPlumbingSigned-offJ. CAIAZZO PLBG & HTG COR05/30/2024
DOB NOWStructuralSigned-offLORICH CONSTRUCTION MANAGEMENT05/29/2024
DOB NOWPlumbingSigned-offNEW LEAF DEVELOPMENT LLC05/09/2024
DOB NOWGeneral ConstructionPermit IssuedZ BUILDERS LLC02/20/2024
BISOTISSUEDPRECISION RENEWABLES LLC09/08/2016
BISOTISSUEDPRECISION RENEWABLES LLC09/08/2016
BIS—ISSUEDMAUCERI SIGN CO., INC09/06/2002
BISSPISSUEDPACE PLBG CORP06/25/2002
BISMHISSUEDSCHIMENTI CONSTRUCTION CO06/20/2002
BISOTISSUEDSCHIMENTI CONSTRUCTION CO06/20/2002
BIS—ISSUEDHRH CONST LLC02/19/2002
+ 3 more permits on file
1 project · most recent 07/07/2026
Sprinkler System
FiledStatusContractorScope
07/07/2026Signed-offNEW YORK PLBG-HTG-COOL CSprinkler System
13 projects · most recent 07/08/2025
General Wiring
FiledStatusContractorScope
07/08/2025CompleteWELSBACH ELECTRIC CORP.1 meters, 1 new_meters
07/08/2025CompleteWELSBACH ELECTRIC CORP.2 meters, 1 new_meters
07/08/2025CompleteWELSBACH ELECTRIC CORP.1 meters, 1 new_meters
05/08/2025CompleteJEM ELEC'L CONTR. CORPGeneral Wiring
04/11/2025CompleteSIGNS CAD CORP—
03/03/2025CancelledSIGNS CAD CORP—
02/07/2025CompleteC.M. RICHEY ELEC'L CONTRGeneral Wiring
09/12/2024CompleteCKC CONTRACTING CORP DBA—
09/12/2024CompleteCKC CONTRACTING CORP DBA—
09/12/2024CompleteCKC CONTRACTING CORP DBA—
08/30/2024CompletePROFF ELECTRICAL LLC—
08/30/2024CompletePROFF ELECTRICAL LLC—
07/29/2024CompleteC.M. RICHEY ELEC'L CONTRGeneral Wiring
▾Field Inspections (DOB CAP) — 31
DateTypeResultReport
07/06/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/20/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/29/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/27/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/21/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/21/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/29/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/24/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/24/2024Pass-Final CND-Occupancy InspectionPassView ↗
11/22/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/19/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/30/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/25/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/22/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/16/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/16/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/13/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/30/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/27/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/26/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/20/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/06/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/01/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
Latest 25 of 31.
▾Special Inspection Requirements (DOB NOW) — 144
DateRequirementInspectorRole
08/07/2026Fenestration and door U-factor and product ratingsRONALD GRAPINenergy_progress
08/07/2026Insulation placement and R valuesRONALD GRAPINenergy_progress
08/07/2026Fenestration air leakageRONALD GRAPINenergy_progress
08/07/2026Fenestration areasRONALD GRAPINenergy_progress
08/07/2026Air barrier - visual inspectionRONALD GRAPINenergy_progress
08/07/2026Fire-Resistant Penetrations and JointsRONALD GRAPINspecial
08/07/2026Fire-Resistance Rated ConstructionRONALD GRAPINprogress
08/07/2026PreliminaryRONALD GRAPINprogress
07/07/2026Fire-Resistance Rated ConstructionRONALD GRAPINprogress
07/07/2026Fire-Resistant Penetrations and JointsRONALD GRAPINspecial
07/07/2026Fenestration air leakageRONALD GRAPINenergy_progress
07/07/2026Air barrier - visual inspectionRONALD GRAPINenergy_progress
07/07/2026Fenestration and door U-factor and product ratingsRONALD GRAPINenergy_progress
07/07/2026Fenestration areasRONALD GRAPINenergy_progress
07/07/2026Insulation placement and R valuesRONALD GRAPINenergy_progress
07/07/2026PreliminaryRONALD GRAPINprogress
05/08/2026FinalRyan Hungprogress
05/01/2026FinalRyan Hungprogress
10/03/2025Lighting controlsRobert Concessienergy_progress
10/03/2025HVAC-R and service water piping design and insulationRobert Concessienergy_progress
10/03/2025HVAC-R and service water heating system controlsRobert Concessienergy_progress
10/03/2025Interior lighting powerRobert Concessienergy_progress
10/03/2025FinalRobert Concessiprogress
10/03/2025Mechanical SystemsRobert Concessispecial
10/03/2025Maintenance informationRobert Concessienergy_progress
Latest 25 of 144.
▾Documents — 249 on file (BIS + DOB NOW)
▸Plans & Drawings51
▸DOB NOWPlans/Sketch50
08/25/2026B01025854-I1Request digital key ↗
08/25/2026B01029555-P1Request digital key ↗
08/25/2026B01029555-I1Request digital key ↗
Showing 3 of 50 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
08/23/2026B01048662-I1Request digital key ↗
▸Applications & Permits4
▸BISWORK PERMIT APPLICATION2
09/09/2016321406821Open ↗
09/09/2016321406821Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
09/14/2016321406821Open ↗
09/09/2016321406821Open ↗
▸Zoning, Tax Lot & Property Records12
▸DOB NOWRestrictive Declaration/Easement 24
08/23/2026B00946629-P7Open ↗
08/13/2026B00946629-P6Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWRestrictive Declaration/Easement 14
08/23/2026B00946629-P7Open ↗
08/13/2026B00946629-P6Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWZoning Exhibit form (1-5)2
08/23/2026B00946629-P7Open ↗
08/14/2026B00946629-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/14/2026B00946629-I1Open ↗
08/13/2026B00946629-I1Open ↗
▸Seals & Professional Certifications155
▸DOB NOWProgress Inspector Seal & Signature62
09/23/2026B00946629-P6Open ↗
09/20/2026B01025854-I1Open ↗
09/20/2026B01025854-I1Open ↗
Showing 3 of 62 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature52
08/25/2026B01041800-P1Open ↗
08/25/2026B01041800-P2Open ↗
08/25/2026B01041800-I1Open ↗
Showing 3 of 52 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature33
09/23/2026B00946629-P6Open ↗
09/20/2026B01025854-I1Open ↗
09/20/2026B01025854-I1Open ↗
Showing 3 of 33 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
07/19/2017321406821Open ↗
07/19/2017321406821Open ↗
07/19/2017321406821Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
09/09/2016321406821Open ↗
09/09/2016321406821Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
09/09/2016321406821Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist6
08/23/2026B00946629-P7Open ↗
08/13/2026B00946629-I1Open ↗
Showing 2 of 6 on file for this type
▸Energy Compliance6
▸DOB NOWPreliminary Commissioning Report Certification3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
07/19/2017321406821Open ↗
09/09/2016321406821Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/19/2017321406821Open ↗
▸Inspections & Test Reports2
▸DOB NOWSOIL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/19/2017321406821Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
07/19/2017321406821Open ↗
09/09/2016321406821Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET3
09/14/2016321406821Open ↗
09/07/2016321406821Open ↗
09/01/2016321406821Open ↗
▸Other Documents7
▸DOB NOWProperty Ownership Certification5
08/23/2026B00946629-P3Open ↗
08/23/2026B00946629-P4Open ↗
08/23/2026B00946629-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWFinal Survey1
08/13/2026B00946629-I1Open ↗
▸DOB NOWTR5H Test Report1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type