| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/25/2025 | $1.1M | — | Private party → Private party | $653/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FARHAD BASSIRI-TEHRANI | 4 | 01/02/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KALE CONSTRUCTION INC | General Contractor | 1 | 04/09/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BASSIRI | 8394 | 2 | 01/02/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 10/17/2025 |
| DOB NOW | General Construction | Signed-off | KALE CONSTRUCTION INC | 10/09/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/02/2026 | Signed-off | JOHN FITZGERALD PLBG &HTG | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/27/2026 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/03/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/02/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/22/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/12/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/12/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/05/2026 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 01/05/2026 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 01/05/2026 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |