| Firm | Filings | Most Recent |
|---|---|---|
| NEW AGE ENGINEERING PLLC | 4 | 07/18/2025 |
| WAVIC ENGINEERING PLLC | 1 | 01/26/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUSKA | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMOK INC | Fire Protection | 2 | 07/08/2026 |
| DEMAR MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| DEMAR PLUMBING CORP | General Contractor | 1 | 07/08/2026 |
| DEMAR PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NEW AGE ENGINEERING PLLC | 7746 | 4 | 07/18/2025 |
| WAVIC ENGINEERING PLLC | 1733 | 1 | 01/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DEMAR PLUMBING CORP | 07/30/2024 |
| DOB NOW | Sprinklers | Permit Issued | DEMAR MECHANICAL INC | 04/16/2024 |
| DOB NOW | Mechanical Systems | Signed-off | DEMAR PLUMBING CORP | 04/09/2024 |
| DOB NOW | Sprinklers | Signed-off | AMOK INC | 04/08/2024 |
| DOB NOW | Plumbing | Signed-off | AMOK INC | 03/03/2023 |
| DOB NOW | Plumbing | Permit Issued | DEMAR MECHANICAL INC | 03/03/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2023 | Signed-off | AMOK INC | 72 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/26/2023 | Permit Issued | DEMAR MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2025 | Permit Issued | DIAKONIA ELEC'L AND CONST | 2 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/30/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/05/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/21/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/20/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/05/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/12/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 04/09/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/30/2025 | HVAC-R and service water heating equipment | Stephen Shishko | energy_progress |
| 06/30/2025 | HVAC-R and service water heating system controls | Stephen Shishko | energy_progress |
| 06/30/2025 | Maintenance information | Stephen Shishko | energy_progress |
| 06/30/2025 | Fire-Resistant Penetrations and Joints | Stephen Shishko | special |
| 11/22/2024 | HVAC-R and service water heating equipment | Stephen Shishko | energy_progress |
| 11/22/2024 | HVAC-R and service water heating system controls | Stephen Shishko | energy_progress |
| 11/22/2024 | Maintenance information | Stephen Shishko | energy_progress |
| 11/22/2024 | Fire-Resistant Penetrations and Joints | Stephen Shishko | special |
| 04/08/2024 | Maintenance information | Stephen Shishko | energy_progress |
| 04/08/2024 | HVAC-R and service water heating equipment | Stephen Shishko | energy_progress |
| 04/08/2024 | HVAC-R and service water piping design and insulation | Stephen Shishko | energy_progress |
| 03/21/2024 | Final | Stephen Shishko | progress |
| 03/21/2024 | Fire-Resistant Penetrations and Joints | Stephen Shishko | special |
| 03/21/2024 | Mechanical Systems | Stephen Shishko | special |
| 12/13/2022 | Sprinkler Systems | DARIUSZ LUCZAK | special |
| 12/13/2022 | Energy Code Compliance Inspections | DARIUSZ LUCZAK | progress |