← Back
Two stories - detached, small or mid-size
4625 CARPENTER AVENUE
BRONX · BIN 2070955
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R5AZoning
2,116 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,325 sf lot · 0.64 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/04/2019$470K—— → —$222/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC204/28/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JAY KAVI CORPORATION8500204/28/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
05/14/2025
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X00994866-I1
04/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
04/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Jay Kavi
04/30/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
04/30/2025
Special inspection requirement — Final
Ayracon Almaraz
04/30/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
04/28/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X00994866-P1
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
04/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Jay Kavi
04/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
04/28/2025
Special inspection requirement — Final
Ayracon Almaraz
04/28/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
02/01/2024
Permit issued — Solar
X00994866-I1-SL
01/29/2024
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X00994866-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC02/01/2024
1 project · most recent 01/17/2024
FiledStatusContractorScope
01/17/2024CompleteREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
04/30/2025Fire-Resistant Penetrations and JointsJay Kavispecial
04/30/2025Structural Stability – Alterations of existing buildingsJay Kavispecial
04/30/2025Energy Code Compliance InspectionsAyracon Almarazprogress
04/30/2025FinalAyracon Almarazprogress
04/30/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
04/28/2025Fire-Resistant Penetrations and JointsJay Kavispecial
04/28/2025Structural Stability – Alterations of existing buildingsJay Kavispecial
04/28/2025Energy Code Compliance InspectionsAyracon Almarazprogress
04/28/2025FinalAyracon Almarazprogress
04/28/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026X00994866-I1Request digital key ↗
08/19/2026X00994866-P1Request digital key ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature6
09/02/2026X00994866-I1Open ↗
09/02/2026X00994866-I1Open ↗
09/02/2026X00994866-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026X00994866-I1Open ↗
09/02/2026X00994866-I1Open ↗
09/01/2026X00994866-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026X00994866-I1Open ↗
08/13/2026X00994866-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026X00994866-P1Open ↗
08/13/2026X00994866-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X00994866-I1Open ↗