| Owner | Filings | Most Recent |
|---|---|---|
| CENTURION REALTY | 49 | 07/08/2026 |
| B10 SOHO RETAIL JV | 2 | 06/02/2026 |
| CLIFTON ARCHITECTURAL GLA | 3 | 03/22/2026 |
| FROI, LLC | 1 | 03/22/2026 |
| WXIV BROADWAY GRAND REALTY | 24 | 03/22/2026 |
| WXV/BROADWAY GRAND REALTY | 1 | 03/22/2026 |
| PAVARINI MCGOVERN | 1 | 03/22/2026 |
| ESV REALTY | 1 | 03/22/2026 |
| MERCER ST LLC | 1 | 03/22/2026 |
| RL MERCER ST LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MURDOCH ENGINEERING | 1 | 05/21/2026 |
| GENSLER | 2 | 04/20/2026 |
| HNY CONSULTING ENGINEERS LLC | 2 | 03/18/2026 |
| D'ANTONIO CONSULTING ENGINEERS | 6 | 01/06/2026 |
| KAHN ARCHITECTURE & DESIGN PC | 1 | 10/30/2025 |
| HALLBERG ENGINEERING | 3 | 09/15/2025 |
| SOCOTEC, INC. | 1 | 04/30/2025 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 3 | 01/16/2025 |
| JEFFREY FLANIGAN, ARCHITECT | 2 | 10/31/2024 |
| SCHNACKEL ENGINEERS | 2 | 09/26/2024 |
| SARGENTI ARCHITECTS | 2 | 09/25/2024 |
| ZENITH HOME INSPECTIONS | 1 | 02/19/2024 |
| URBAN INTEGRATIONS | 1 | 11/20/2023 |
| PRUDIGM ENGINEERING LLC | 1 | 10/13/2023 |
| NAZZARENO CALLIPO P.E. | 1 | 10/13/2023 |
| STEVEN URAINE ARCHITECT | 1 | 07/26/2023 |
| OUTPOST ARCHITECTURE DPC | 1 | 02/24/2022 |
| BAILEYS ENGINEERING PC | 1 | 05/21/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 10 | 03/21/2026 |
| BURNHAM NATIONWIDE INC | 2 | 03/21/2026 |
| RICHARD WAINER ARCHITECT, PLLC | 4 | 03/21/2026 |
| RYBAK DEVELOPMENT | 2 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 20 | 03/21/2026 |
| GZ NC CODE PLANNING ENGINEERING | 2 | 03/21/2026 |
| JP EXPEDITE | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HIGHLINE CONSTRUCTION GR | General Contractor | 5 | 04/09/2026 |
| JRM CONSTRUCTION MGMT LLC | General Contractor | 5 | 07/08/2026 |
| POLAR MECHANICAL CORP | General Contractor | 4 | 03/21/2026 |
| J. CAIAZZO PLBG & HTG COR | Plumbing | 4 | 07/08/2026 |
| KG SPRINKLER | Plumbing | 3 | 03/22/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 3 | 07/08/2026 |
| SALT CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| PIECE MANAGEMENT INC | General Contractor | 2 | 03/21/2026 |
| DONATO PLUMBING, INC | Plumbing | 2 | 07/08/2026 |
| SIGNS CAD | Scaffold | 1 | 07/08/2026 |
| S&P ELECTRIC CO LLC | Electrical | 1 | 03/22/2026 |
| VALLESIGNS AWNINGS | Scaffold | 1 | 06/02/2026 |
| V.I.P. ELECTL CONTR CORP | Electrical | 1 | 03/22/2026 |
| KG SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 1 | 07/08/2026 |
| A & B CONTRACTING SVCS IN | General Contractor | 1 | 07/08/2026 |
| DYNAMIC CONSTRUCTION SERV | General Contractor | 1 | 07/08/2026 |
| HERBERT ROSE INC | General Contractor | 1 | 07/08/2026 |
| SHAPEL GENERAL CONTRACTIN | General Contractor | 1 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| D'ANTONIO CONSULTING ENGI | 931 | 4 | 01/06/2026 |
| SOCOTEC ENGINEERING | 4983 | 2 | 11/21/2025 |
| PROJECT TACTICAL SOLUTION | 5859 | 2 | 10/30/2025 |
| SOCOTEC, INC. | 301 | 1 | 04/30/2025 |
| CATALPA SPECIAL INSPECTIO | 2004 | 10 | 01/16/2025 |
| METRIC CONSULTING AND INS | 1803 | 4 | 01/16/2025 |
| A DEGREE OF FREEDOM STRUC | 925 | 2 | 10/31/2024 |
| MEP INSPECTIONS, INC | 1102 | 2 | 09/26/2024 |
| GZ & NC CODE CONSULTING P | 7492 | 1 | 10/13/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Permit Issued | VALLESIGNS & AWNINGS INC | 05/29/2026 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 03/16/2026 |
| DOB NOW | Mechanical Systems | Signed-off | POLAR MECHANICAL CORP | 02/03/2026 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 12/17/2025 |
| DOB NOW | Plumbing | Signed-off | J. CAIAZZO PLBG & HTG COR | 12/01/2025 |
| DOB NOW | General Construction | Signed-off | SHAPEL GENERAL CONTRACTIN | 11/26/2025 |
| DOB NOW | General Construction | Signed-off | DYNAMIC CONSTRUCTION SERV | 11/19/2025 |
| DOB NOW | Structural | Signed-off | HIGHLINE CONSTRUCTION GR | 09/30/2025 |
| DOB NOW | General Construction | Signed-off | HIGHLINE CONSTRUCTION GR | 09/30/2025 |
| DOB NOW | General Construction | Signed-off | HERBERT ROSE INC | 05/14/2025 |
| DOB NOW | Mechanical Systems | Signed-off | POLAR MECHANICAL CORP | 03/21/2025 |
| DOB NOW | General Construction | Signed-off | HIGHLINE CONSTRUCTION GR | 03/20/2025 |
| DOB NOW | Structural | Signed-off | HIGHLINE CONSTRUCTION GR | 03/19/2025 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 03/17/2025 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 08/01/2024 |
| DOB NOW | Structural | Signed-off | JRM CONSTRUCTION MGMT LLC | 07/30/2024 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 07/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JRM CONSTRUCTION MGMT LLC | 07/23/2024 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 07/23/2024 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 02/20/2024 |
| DOB NOW | General Construction | Signed-off | SALT CONSTRUCTION INC | 10/30/2023 |
| DOB NOW | General Construction | Signed-off | A B CONTRACTING SVCS IN | 06/02/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 07/26/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 05/22/2018 |
| BIS | OT | ISSUED | PRECISION BUILDING & CONS | 12/24/2020 |
| BIS | PL | ISSUED | M&T PLBG AND HTG CO., INC | 08/14/2019 |
| BIS | OT | ISSUED | CLIFTON ARCHITECTURAL GLA | 01/10/2019 |
| BIS | OT | ISSUED | CLIFTON ARCHITECTURAL GLA | 06/22/2018 |
| BIS | OT | ISSUED | RITEWAY NY GENERAL CONTRA | 05/23/2018 |
| BIS | OT | ISSUED | GT PRESTIGE INC | 12/23/2015 |
| BIS | OT | ISSUED | CREATIVE CONSTRUCTORS COR | 05/20/2013 |
| BIS | MH | ISSUED | DUCE CONSTRUCTION CORP | 09/20/2012 |
| BIS | PL | ISSUED | A.R.L. PLUMBING & HTG LLC | 08/16/2012 |
| BIS | OT | ISSUED | MJL DESIGN & DEVELOPMENT | 08/07/2012 |
| BIS | MH | ISSUED | MJL DESIGN & DEVELOPMENT | 08/07/2012 |
| BIS | — | ISSUED | VALLESIGNS & AWNINGS INC | 10/19/2011 |
| BIS | — | ISSUED | VALLESIGNS & AWNINGS INC | 10/19/2011 |
| BIS | — | ISSUED | VALLESIGNS & AWNINGS INC | 10/19/2011 |
| BIS | OT | ISSUED | WADE RAY & ASSOC CONST IN | 03/18/2011 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 04/02/2010 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2026 | Signed-off | KG SPRINKLER CORP | 64 heads |
| 10/13/2023 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/20/2026 | Signed-off | J. CAIAZZO PLBG & HTG COR | Water/Sanitary |
| 01/06/2026 | — | — | — |
| 12/16/2025 | Signed-off | DONATO PLUMBING, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2026 | Complete | WARREN OSTROFF ELEC., INC | General Wiring |
| 11/07/2025 | Complete | EPIC ELECTRIC INC | General Wiring |
| 10/31/2025 | Complete | LEBO ELECTRIC LLC | General Wiring |
| 03/13/2025 | Complete | WARREN OSTROFF ELEC., INC | — |
| 08/21/2024 | Complete | S&P ELECTRIC CO LLC | General Wiring |
| 08/06/2024 | Complete | V.I.P. ELECTL CONTR CORP | General Wiring |
| 02/13/2024 | Complete | STELLMANN ELECTRICAL CORP | General Wiring |
| 11/20/2023 | Complete | R. GUNZER, INC. | General Wiring |
| 08/01/2023 | Complete | COMMERCIAL ELECT CONT INC | General Wiring |
| 10/08/2020 | Complete | CORP. ELEC'L TECHNOLOGIES | — |
| 08/08/2019 | Complete | BIGMAN BROS., INC. | General Wiring, Lighting |
| 05/07/2018 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/20/2026 | Signed-off | J. CAIAZZO PLBG & HTG COR | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/13/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/29/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/28/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/26/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/23/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/30/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/27/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/28/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/25/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/23/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/19/2026 | Final | JERE MURDOCH | progress |
| 04/20/2026 | Tenant Protection Plan Compliance | ALEXIS SCHLESSINGERMAN | special |
| 04/20/2026 | Energy Code Compliance Inspections | ALEXIS SCHLESSINGERMAN | progress |
| 04/20/2026 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 02/20/2026 | Tenant Protection Plan Compliance | — | special |
| 02/20/2026 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 02/20/2026 | Energy Code Compliance Inspections | ALEXIS SCHLESSINGERMAN | progress |
| 12/30/2025 | Sprinkler Systems | GAETANO D'ANTONIO | special |
| 12/30/2025 | Post-installed Anchors | GAETANO D'ANTONIO | special |
| 12/30/2025 | Mechanical Systems | GAETANO D'ANTONIO | special |
| 12/30/2025 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 12/30/2025 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 12/30/2025 | Post-installed Anchors | GAETANO D'ANTONIO | special |
| 12/30/2025 | Final | GAETANO D'ANTONIO | progress |
| 12/12/2025 | Final | GAETANO D'ANTONIO | progress |
| 12/12/2025 | Post-installed Anchors | GAETANO D'ANTONIO | special |
| 12/12/2025 | Mechanical Systems | GAETANO D'ANTONIO | special |
| 12/12/2025 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 10/21/2025 | Tenant Protection Plan Compliance | Max Lee | special |
| 10/21/2025 | Final | Michael Kahn | progress |
| 09/15/2025 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 04/30/2025 | Masonry | Stanford Chan | special |
| 02/12/2025 | Tenant Protection Plan Compliance | Stanford Chan | special |
| 01/17/2025 | Final | ERIC BERLENT | progress |
| 01/17/2025 | Post-installed Anchors | SAMI HAJJAR P.E | special |