| Owner | Filings | Most Recent |
|---|---|---|
| Fordham University | 44 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Eme Consulting Engineering Group | 3 | 06/29/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| Nyccode | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Sentinel Builders | General Contractor | 4 | 07/08/2026 |
| Laura Electrical Lighting | Electrical | 1 | 03/21/2026 |
| Laura Electrical Lighting | Electrical | 1 | 03/22/2026 |
| Alafogiannis Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Tectonic Engineering Cons | 106 | 2 | 06/29/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/04/2025 | Permit Issued | Laura Electrical Lighting | — |
| 07/24/2025 | Permit Issued | E-J Electric Installation Co | — |
| 12/10/2024 | Complete | Laura Electrical Lighting | — |
| 07/23/2024 | Permit Issued | E-J Electric Installation Co | — |
| 09/11/2023 | Permit Issued | Laura Electrical Lighting | — |
| 05/19/2023 | Complete | E-J Electric Installation Co | — |
| 06/19/2019 | Complete | H. & L. Electric | General Wiring |
| 05/23/2019 | Complete | H. & L. Electric | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/07/2020 | HVAC insulation and sealing | EDUARDO LIEVANO | energy_progress |
| 07/07/2020 | Fire-Resistant Penetrations and Joints | EDUARDO LIEVANO | special |
| 07/07/2020 | Mechanical Systems | EDUARDO LIEVANO | special |
| 07/07/2020 | Final | EDUARDO LIEVANO | progress |
| 06/26/2020 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 06/26/2020 | Mechanical Systems | GEORGE GHEBRYAL | special |
| 06/26/2020 | Final | GEORGE GHEBRYAL | progress |
| 06/26/2020 | HVAC insulation and sealing | GEORGE GHEBRYAL | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Fordham University | Education | Floors 1, 2 | Project X00344909 Project X00339306 |