| Owner | Filings | Most Recent |
|---|---|---|
| ATLAS CAPITAL GROUP | 305 | 07/19/2026 |
| STEEL SYSTEMS | 6 | 07/08/2026 |
| FACTORY OWNERS LLC | 327 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 3 | 03/22/2026 |
| PILKU CONSTRUCTION SVC | 1 | 03/22/2026 |
| PILKU CONSTRUCTION SERVIC | 1 | 03/22/2026 |
| CAROLE WREN INC | 1 | 03/22/2026 |
| JAP SPORTS LTD | 1 | 03/22/2026 |
| 30TH PLACE HOLDINGS | 160 | 03/22/2026 |
| 30 PLACE HOLDING LLC | 6 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JACK GREEN ASSOCIATES | 7 | 07/17/2026 |
| KAHN ARCHITECTURE & DESIGN PC | 2 | 07/16/2026 |
| DESIGN DEVELOPMENT ARCHITECTS | 1 | 07/08/2026 |
| P. M. ARCHITECTURE, PC | 1 | 06/24/2025 |
| JATTUSO ARCHITECTURE | 9 | 05/27/2025 |
| OLA CONSULTING ENGINEERS, PC | 9 | 05/01/2025 |
| ENV ARCHITECTS, DPC | 2 | 05/01/2025 |
| TPG ARCHITECTURE, LLP | 4 | 03/06/2024 |
| JAG ENGINEERING, LLC | 6 | 08/30/2023 |
| JACOB FEINBERG KATZ & MICHAELI CONS | 36 | 04/11/2023 |
| COSENTINI ASSOCIATES | 5 | 04/03/2023 |
| KM ENGINEERING, D.P.C | 1 | 11/29/2022 |
| JOHN F. GIUSEFFI, ARCHITECT, PC | 2 | 07/12/2022 |
| MG ENGINEERING D.P.C. | 6 | 07/12/2021 |
| SCHERER DESIGN GROUP | 5 | 05/04/2021 |
| THOMAS G. HAUCK, JR. | 4 | 10/09/2020 |
| RTM ENGINEERING CONSULTANTS LLC | 1 | 01/15/2020 |
| LALIRE MARCH ARCHITECTS LLP | 1 | 10/23/2019 |
| GREEN DESIGN | 1 | 11/19/2018 |
| ASHRAF CORP | 1 | 08/02/2018 |
| BAILEYS ENGINEERING PC | 1 | 06/05/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 114 | 03/21/2026 |
| DVA Advisors | 20 | 03/21/2026 |
| PM ARCHITECTURE PC | 2 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 10 | 03/21/2026 |
| JOANNA KARAGIANNIS | 4 | 03/21/2026 |
| HH BUILDING CONSULTING & ARCHITECTU | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| ATLANTIC BUILDING SUPPLY INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACG CONSTRUCTION MANAGEMENT | General Contractor | 41 | 07/08/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 11 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Fire Protection | 8 | 07/08/2026 |
| VILLAGE P & H NY INC | Fire Protection | 8 | 07/08/2026 |
| NPF CONSTRUCTION CORP | General Contractor | 7 | 07/08/2026 |
| L&J PLG & HTG CO OF NY IN | Plumbing | 7 | 07/08/2026 |
| CEDAR ELEC'L CONT'RS INC. | Electrical | 7 | 03/22/2026 |
| A.W. & S. CONSTRUCTION CO | General Contractor | 6 | 07/08/2026 |
| BENCHMARK BUILDERS LLC | General Contractor | 5 | 07/08/2026 |
| ODYSSIA GLOBAL COMM. CORP | General Contractor | 5 | 07/08/2026 |
| STEEL SYSTEMS LLC | General Contractor | 4 | 07/08/2026 |
| WHARTON SMITH CONSTRUCTI* | General Contractor | 4 | 07/08/2026 |
| J. PHELAN CONSTRUCTION CO | General Contractor | 4 | 03/21/2026 |
| ON-TRAC CONSTRUCTION ASSO | General Contractor | 4 | 07/08/2026 |
| HENICK-LANE SERVICE CORP | General Contractor | 4 | 06/28/2026 |
| CAPITOL FIRE SPRINKLER CO | Fire Protection | 3 | 07/08/2026 |
| TRISTATE AIR CONDITIONING | General Contractor | 3 | 03/21/2026 |
| BOCA FIRE PRODUCTS LLC | Fire Protection | 2 | 07/08/2026 |
| APOLLO ELECTRIC INSDUS IN | Electrical | 2 | 03/22/2026 |
| MAR-KAM ELEC'L CONTR'G IN | Electrical | 2 | 03/22/2026 |
| TRISTATE PLBG SVCS CORP | Fire Protection | 2 | 07/08/2026 |
| APB CONSULTING & CONSTRUC | General Contractor | 2 | 03/21/2026 |
| IDK COOLING CORP | General Contractor | 2 | 07/08/2026 |
| JAMES E FITZGERALD INC | General Contractor | 2 | 03/21/2026 |
| AURA PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JACK GREEN ASSOCIATES | 422 | 11 | 07/17/2026 |
| JUDGE ARCHITECTURE PC | 748 | 1 | 07/08/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 12 | 05/01/2025 |
| KATZ ENGINEERING | 238 | 6 | 01/22/2024 |
| O'ROURKE ENGINEERING, LLC | 5873 | 2 | 04/11/2023 |
| PSI AGENCY INC. | 254 | 38 | 12/25/2022 |
| KM ENGINEERING, D.P.C. | 5745 | 1 | 11/29/2022 |
| AK ENGINEERING PC | 678 | 7 | 07/12/2022 |
| SCHERER DESIGN GROUP | 7921 | 3 | 05/04/2021 |
| MILROSE CONSULTANTS LLC | 2003 | 4 | 10/09/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | SPRICE CONTRACTING INC | 07/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | HENICK-LANE SERVICE CORP | 01/20/2026 |
| DOB NOW | General Construction | Permit Issued | HENICK-LANE SERVICE CORP | 01/12/2026 |
| DOB NOW | Plumbing | Signed-off | ADVANCED PLUMBING MECH | 11/17/2025 |
| DOB NOW | Sprinklers | Permit Issued | VILLAGE P & H NY INC | 11/05/2025 |
| DOB NOW | General Construction | Permit Issued | HENICK-LANE SERVICE CORP | 11/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | HENICK-LANE SERVICE CORP | 11/03/2025 |
| DOB NOW | Sprinklers | Signed-off | FIREQUEST CORP | 08/25/2025 |
| DOB NOW | Sprinklers | Signed-off | MT ENERGY INC | 07/30/2025 |
| DOB NOW | General Construction | Signed-off | INS CONSTRUCTION CORP | 06/30/2025 |
| DOB NOW | General Construction | Signed-off | GRAVESEND CONSTRUCTION CO | 06/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | WHARTON SMITH CONSTRUCTI* | 06/05/2025 |
| DOB NOW | Plumbing | Signed-off | MT ENERGY INC | 06/05/2025 |
| DOB NOW | General Construction | Signed-off | WHARTON SMITH CONSTRUCTI* | 06/04/2025 |
| DOB NOW | Mechanical Systems | Signed-off | IDK COOLING CORP | 05/27/2025 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 05/15/2025 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 05/12/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CLUNE CONSTRUCTION CO LP | 05/02/2025 |
| DOB NOW | Sprinklers | Signed-off | ALLSTATE SPRINKLER LLC | 05/02/2025 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 05/02/2025 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 01/30/2025 |
| DOB NOW | General Construction | Signed-off | ON-TRAC CONSTRUCTION ASSO | 07/30/2024 |
| DOB NOW | General Construction | Signed-off | ON-TRAC CONSTRUCTION ASSO | 07/29/2024 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 03/19/2024 |
| DOB NOW | General Construction | Signed-off | JAMES E FITZGERALD INC | 01/05/2024 |
| DOB NOW | Structural | Signed-off | NPF CONSTRUCTION CORP | 10/13/2023 |
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 08/08/2023 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 08/08/2023 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 08/07/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CLUNE CONSTRUCTION CO LP | 08/04/2023 |
| DOB NOW | Mechanical Systems | Signed-off | A.W. & S. CONSTRUCTION CO | 06/14/2023 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 06/12/2023 |
| DOB NOW | General Construction | Signed-off | ACG CONSTRUCTION MANAGEME | 06/09/2023 |
| DOB NOW | General Construction | Signed-off | ACG CONSTRUCTION MANAGEME | 05/05/2023 |
| DOB NOW | Sprinklers | Signed-off | BOCA FIRE PRODUCTS LLC | 03/07/2023 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 02/01/2023 |
| DOB NOW | Structural | Signed-off | NPF CONSTRUCTION CORP | 01/10/2023 |
| DOB NOW | Sprinklers | Signed-off | BOCA FIRE PRODUCTS LLC | 01/04/2023 |
| DOB NOW | General Construction | Signed-off | NPF CONSTRUCTION CORP | 12/21/2022 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 12/20/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2026 | Permit Issued | PARAMOUNT SERVICES, LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2026 | Signed-off | ADVANCED PLUMBING MECH | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2026 | Permit Issued | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 08/20/2026 | Permit Issued | APOLLO ELECTRIC INC. | General Wiring |
| 08/18/2026 | Permit Issued | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 03/12/2026 | Complete | EPIC ELECTRIC INC | General Wiring |
| 02/25/2026 | Permit Issued | EPIC ELECTRIC INC | General Wiring |
| 10/29/2025 | Complete | APOLLO ELECTRIC INSDUS IN | General Wiring |
| 06/11/2025 | Complete | ULTRA ELECTRIC CORP | General Wiring |
| 05/06/2025 | Complete | MIKOMA ELECTRIC LLC | General Wiring |
| 03/04/2025 | Complete | VALENTIS ELECTRIC, INC. | General Wiring |
| 03/03/2025 | Complete | DMMP ELECTRIC CONSTR. INC | General Wiring |
| 01/23/2025 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 12/02/2024 | Permit Issued | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 09/13/2024 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 05/28/2024 | Complete | APOLLO ELECTRIC INSDUS IN | General Wiring |
| 04/11/2024 | Complete | TANACHION ELEC'L CONT'G I | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/04/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/21/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/17/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/17/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/28/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/26/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/26/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/26/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/21/2025 | Fail-Final SP - Up to 3 Requested Floors | Fail | View ↗ |
| 08/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/04/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/10/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/05/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/01/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/01/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/06/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/09/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/30/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/27/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/25/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/24/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/06/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2026 | HVAC-R and service water heating equipment | JACK GREEN | energy_progress |
| 07/21/2026 | Fire-Resistant Penetrations and Joints | JACK GREEN | special |
| 07/21/2026 | HVAC-R and service water heating system controls | JACK GREEN | energy_progress |
| 07/17/2026 | Fire-Resistant Penetrations and Joints | JACK GREEN | special |
| 07/17/2026 | Fire-Resistance Rated Construction | JACK GREEN | progress |
| 07/17/2026 | Final | Michael Kahn | progress |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | Rachael Judge | special |
| 07/02/2026 | Fire-Resistance Rated Construction | RON HOINA | progress |
| 07/02/2026 | Energy Code Compliance Inspections | RON HOINA | progress |
| 06/23/2026 | Final | RON HOINA | progress |
| 09/24/2025 | Post-installed Anchors | JACK GREEN | special |
| 09/23/2025 | Mechanical Systems | JACK GREEN | special |
| 09/23/2025 | Sprinkler Systems | JACK GREEN | special |
| 09/23/2025 | Final | JACK GREEN | progress |
| 05/01/2025 | Fire-Resistant Penetrations and Joints | LAWRENCE GREEN | special |
| 05/01/2025 | Final | LAWRENCE GREEN | progress |
| 05/01/2025 | Post-installed Anchors | LAWRENCE GREEN | special |
| 05/01/2025 | Mechanical Systems | LAWRENCE GREEN | special |
| 05/01/2025 | Final | Joseph Jattuso | progress |
| 04/29/2025 | Fire-Resistant Penetrations and Joints | LAWRENCE GREEN | special |
| 04/16/2025 | Final | LAWRENCE GREEN | progress |
| 04/08/2025 | HVAC-R and service water heating equipment | LAWRENCE GREEN | energy_progress |
| 04/08/2025 | HVAC-R and service water heating system controls | LAWRENCE GREEN | energy_progress |
| 04/08/2025 | Shutoff dampers | LAWRENCE GREEN | energy_progress |
| 04/08/2025 | Final | LAWRENCE GREEN | progress |