← Back
STATEN ISLAND
47 FARVIEW PLACE
STATEN ISLAND · BIN 5176703
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone X
Locations of Work
ArchitectureStructural
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 1 filing · 20 docs
Floor 2Under Construction1p · 1 filing · 20 docs
Floor 1Under Construction2p · 1 filing · 20 docs
CellarUnder Construction2p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
S M TAM ARCHITECT, PLLC1108/07/2026
A & T ENGINEERING, P.C.1—
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LC EXPEDITING SERVICES203/21/2026
S M TAM ARCHITECT403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CTI CONSTRUCTION INCGeneral Contractor104/09/2026
Building Lifecycle
All (72)Filed (11)Permit Issued (1)Objection (30)Special Inspection (30)
08/31/2026
Objection resolved — Addressed
08/13/2026
Special inspection requirement — Duct leakage testing, insulation and design
08/07/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-Z1
07/31/2026
Objection raised — Energy
07/17/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S8
07/16/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S9
07/16/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S7
07/08/2026
Special inspection requirement — HVAC-R and service water heating equipment
07/08/2026
Special inspection requirement — Energy Code Compliance Inspections
07/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/08/2026
Special inspection requirement — Metering
07/08/2026
Special inspection requirement — HVAC-R and service water heating system controls
07/08/2026
Special inspection requirement — Ventilation and air distribution system
07/08/2026
Special inspection requirement — Maintenance information
07/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/08/2026
Special inspection requirement — Energy Code Compliance Inspections
07/08/2026
Special inspection requirement — Permanent certificate
07/08/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
06/26/2026
Special inspection requirement — Sprinkler Systems
06/26/2026
Special inspection requirement — Mechanical Systems
06/26/2026
Special inspection requirement — Final
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/14/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S4
04/14/2026
Objection resolved — Addressed
03/25/2026
Objection resolved — Addressed
03/25/2026
Objection resolved — Addressed
03/25/2026
Objection resolved — Addressed
03/25/2026
Objection resolved — Addressed
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Scope
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Admin
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Structural
03/11/2026
Objection raised — Structural
03/02/2026
Objection raised — Structural
03/02/2026
Objection raised — Scope
02/26/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S2
02/26/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S3
02/25/2026
Special inspection requirement — Concrete - Cast-In-Place
02/25/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
02/25/2026
Special inspection requirement — Subgrade Inspections
02/24/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S6
02/24/2026
Permit issued — Construction Fence
S00966109-S5-FN
02/23/2026
Objection resolved — Addressed
01/26/2026
Objection raised — Scope
01/21/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S5
01/12/2026
Filed — New Building
CONSTRUCTION OF NEW 2-STORY BUILDING INCLUDING CONCRETE COLUMNS, BEAMS, AND FOUNDATIONS.
S00966109-S1
Latest 60 of 72 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedCTI CONSTRUCTION INC02/24/2026
1 project · most recent 08/07/2026
FiledStatusContractorScope
08/07/2026Permit IssuedCTI CONSTRUCTION INC2 scope_items
1 project · most recent 08/07/2026
Fence
FiledStatusContractorScope
08/07/2026Permit IssuedCTI CONSTRUCTION INCFence
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
08/13/2026Duct leakage testing, insulation and design—energy_progress
07/08/2026HVAC-R and service water heating equipment—energy_progress
07/08/2026Energy Code Compliance Inspections—progress
07/08/2026Fire-Resistant Penetrations and Joints—special
07/08/2026Fire-Resistant Penetrations and Joints—special
07/08/2026Metering—energy_progress
07/08/2026HVAC-R and service water heating system controls—energy_progress
07/08/2026Ventilation and air distribution system—energy_progress
07/08/2026Maintenance information—energy_progress
07/08/2026Fire-Resistant Penetrations and Joints—special
07/08/2026Energy Code Compliance Inspections—progress
07/08/2026Permanent certificate—energy_progress
07/08/2026HVAC-R and service water piping design and insulation—energy_progress
06/26/2026Sprinkler Systems—special
06/26/2026Mechanical Systems—special
06/26/2026Final—progress
02/25/2026Concrete - Cast-In-Place—special
02/25/2026Subsurface Investigations (Borings/Test Pits)—special
02/25/2026Subgrade Inspections—special
12/30/2025Excavations - Sheeting, Shoring, and Bracing—special
12/30/2025Concrete - Cast-In-Place—special
12/30/2025Masonry—special
12/30/2025Subgrade Inspections—special
08/08/2025Final—progress
08/08/2025Footing and Foundation—progress
Latest 25 of 43.
▾Documents — 52 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/26/2026S01011592-I1Request digital key ↗
08/17/2026S00966109-I1Request digital key ↗
08/17/2026S00966109-Z1Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
02/19/2026540265844Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
02/19/2026540265844Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S00966109-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00966109-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00966109-I1Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/26/2026S01011592-I1Open ↗
08/17/2026S00966109-I1Open ↗
08/17/2026S00966109-Z1Open ↗
Showing 3 of 12 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
03/06/2025540265844Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026S00966109-I1Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST1
03/06/2025540265844Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/17/2026S00966109-I1Open ↗
▸DOB NOWStreet Tree Checklist1
08/13/2026S00966109-I1Open ↗
▸Inspections & Test Reports5
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026S00966109-S3Open ↗
08/13/2026S00966109-S2Open ↗
▸BISDOT WAIVER OF 5 FEET CONCRETE SIDEWALK.1
01/28/2026540265844Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00966109-S3Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026S00966109-S3Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
02/19/2026540265844Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
02/19/2026540265844Open ↗
01/28/2026540265844Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/19/2026540265844Open ↗
▸Other Documents9
▸BISBPP: TOPOGRAPHIC SURVEY2
02/19/2026540265844Open ↗
01/21/2026540265844Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
01/21/2026540265844Open ↗
▸BISDOT WAIVER OF CURB ALIGNMENT.1
01/28/2026540265844Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
03/06/2025540265844Open ↗
▸DOB NOWProperty Ownership Certification1
08/17/2026S00966109-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026S01011592-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026S00966109-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026S00966109-I1Open ↗