| Owner | Filings | Most Recent |
|---|---|---|
| RELIABLE ENTERPRISES | 8 | 07/08/2026 |
| WEST 54TH STREET | 8 | 07/08/2026 |
| DAISY MANAGEMENT | 1 | 03/22/2026 |
| OWNER OF 47 MERCER STREET | 1 | 03/22/2026 |
| MERCER STATION LLC | 1 | 03/22/2026 |
| SCHIMENTI | 1 | 03/22/2026 |
| BRENMAC CONSTRUCTION | 2 | 03/21/2026 |
| A2 MERCER | 6 | 03/21/2026 |
| 47 MERCER | 1 | 03/21/2026 |
| 47 MERCER STREET CONDOMINIUM | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DEVERE ARCHITECTURE | 3 | 12/17/2025 |
| CHEUNG SHOWMAN ARCHITECTS | 5 | 09/19/2025 |
| OZAETA ENGINEERING, PLLC | 2 | 07/22/2025 |
| E4P CONSULTING ENGINEERING PLLC | 5 | 11/12/2024 |
| ROSINI ENGINEERING, PC | 5 | 02/06/2023 |
| ROBERT SILMAN ASSOC STRUCT ENG DPC | 1 | 01/13/2022 |
| THOMAS W HUT ARCHITECT PLLC | 1 | 01/11/2022 |
| LAWLESS AND MANGIONE ARCHITECTS AND | 1 | 11/24/2021 |
| ENTHINK ENGINEERS LLC | 2 | 11/10/2021 |
| GREGORY V. PEROTTO, P.E. | 2 | 05/03/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREGG ROTHSTEIN ARCHITECT | 3 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 24 | 03/21/2026 |
| CODE | 14 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CERTIFIED OF N.Y. INC | General Contractor | 13 | 07/15/2026 |
| FOLOR INC | General Contractor | 5 | 07/08/2026 |
| RELIABLE ENTERPRISES INC | General Contractor | 4 | 07/08/2026 |
| KG SPRINKLER CORP | Fire Protection | 4 | 07/08/2026 |
| GDC CONTRACTING LLC | General Contractor | 2 | 07/04/2026 |
| HENRY MYERS P & H, INC | Plumbing | 2 | 07/08/2026 |
| R.D.I. ASSOCIATES INC | Electrical | 1 | 03/21/2026 |
| PSI PARTNERS, LLC | Fire Protection | 1 | 07/08/2026 |
| SCHIMENTI CONSTRUCTION CO | General Contractor | 1 | 07/08/2026 |
| A&A PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| BARBIERI, LAWRENCE | Electrical | 1 | 03/21/2026 |
| TEE BEE SIGN INST | Scaffold | 1 | 07/08/2026 |
| BASS ELECTRICAL CORP. | Electrical | 1 | 03/22/2026 |
| BENI, CARMINE | Electrical | 1 | 03/21/2026 |
| CROSSWIRE ELECTRICAL INC | Electrical | 1 | 03/22/2026 |
| ESCORCE, MANUEL | Electrical | 1 | 03/21/2026 |
| PHONG NGUYEN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FORUM ENGINEERING, P. C. | 907 | 1 | 12/17/2025 |
| RYAN SPECIAL ENGINEERING | 2018 | 3 | 12/17/2025 |
| CHEUNG SHOWMAN ARCHITECTS | 7598 | 5 | 09/19/2025 |
| KADAN CORP. | 5956 | 2 | 07/22/2025 |
| HT ENGINEERING, PLLC | 6274 | 5 | 11/12/2024 |
| IVA FILIPOVIC ARCHITECT | 3142 | 1 | 11/07/2023 |
| ROSINI ENGINEERING, PC | 3282 | 4 | 02/06/2023 |
| CHEN ENGINEERING SERVICES | 1826 | 2 | 01/13/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | CERTIFIED OF N.Y. INC | 07/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | GDC CONTRACTING LLC | 07/02/2026 |
| DOB NOW | General Construction | Permit Issued | GDC CONTRACTING LLC | 07/01/2026 |
| DOB NOW | General Construction | Permit Issued | CERTIFIED OF N.Y. INC | 04/22/2026 |
| DOB NOW | General Construction | Permit Issued | CERTIFIED OF N.Y. INC | 01/27/2026 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 10/21/2025 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 10/21/2025 |
| DOB NOW | Plumbing | Permit Issued | HENRY MYERS P & H, INC | 10/20/2025 |
| DOB NOW | Structural | Permit Issued | CERTIFIED OF N.Y. INC | 09/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | CERTIFIED OF N.Y. INC | 07/16/2025 |
| DOB NOW | General Construction | Permit Issued | CERTIFIED OF N.Y. INC | 04/29/2025 |
| DOB NOW | General Construction | Permit Issued | CERTIFIED OF N.Y. INC | 02/13/2025 |
| DOB NOW | Structural | Permit Issued | CERTIFIED OF N.Y. INC | 10/02/2024 |
| DOB NOW | Plumbing | Permit Issued | HENRY MYERS P & H, INC | 07/16/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | CERTIFIED OF N.Y. INC | 07/03/2024 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 06/26/2024 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 06/26/2024 |
| DOB NOW | General Construction | Permit Issued | CERTIFIED OF N.Y. INC | 05/21/2024 |
| DOB NOW | General Construction | Permit Issued | CERTIFIED OF N.Y. INC | 03/15/2024 |
| DOB NOW | Structural | Signed-off | FOLOR INC | 03/14/2022 |
| DOB NOW | Sprinklers | Signed-off | MORA FIRE PROTECTION LLC | 03/08/2022 |
| DOB NOW | Mechanical Systems | Signed-off | FOLOR INC | 02/24/2022 |
| DOB NOW | Plumbing | Signed-off | A&A PLUMBING CORP | 02/19/2022 |
| DOB NOW | General Construction | Signed-off | FOLOR INC | 01/19/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 11/12/2021 |
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 11/10/2021 |
| DOB NOW | Sign | Permit Issued | WEINFELD, ELLIOT | 05/26/2021 |
| DOB NOW | General Construction | Signed-off | SCHIMENTI CONSTRUCTION CO | 04/05/2021 |
| BIS | PL | ISSUED | TOP PLUMBING GROUP,INC | 11/17/2016 |
| BIS | OT | ISSUED | TCM CORPORATION | 09/21/2016 |
| BIS | PL | ISSUED | GREAT CITY PLUMBING INC | 09/08/2016 |
| BIS | OT | ISSUED | TCM CORPORATION | 08/29/2016 |
| BIS | EQ | ISSUED | BRENMAC CONSTRUCTION INC | 08/01/2014 |
| BIS | PL | ISSUED | MARATHON MECHANICAL LLC | 01/10/2012 |
| BIS | OT | ISSUED | TATRAS CONSTRUCTION CORP | 01/09/2012 |
| BIS | EQ | ISSUED | PHOENIX BRIDGING INC | 01/03/2012 |
| BIS | EQ | ISSUED | PHOENIX BRIDGING INC | 12/28/2011 |
| BIS | OT | ISSUED | JEPOL CONSTRUCTION INC | 08/15/2011 |
| BIS | EQ | ISSUED | PHOENIX BRIDGING INC | 08/12/2011 |
| BIS | EQ | ISSUED | PHOENIX BRIDGING INC | 08/09/2011 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/19/2025 | Permit Issued | CERTIFIED OF N.Y. INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PEFY-P24NAMU-E4 25,934 BTU · Vrf Indoor ×2 MXZ-SM36NAMHZ2 42,000 BTU · Condensing Unit ×1 MXZ-SM48NAMHZ2 54,000 CFM · Condensing Unit ×1 MXZ-SM60NAM2 66,000 BTU · Condensing Unit ×1 PEFY-P36NAMU-E4 34,583 BTU · Vrf Indoor ×1 PEFY-P72NMHSU-E 37,703 BTU · Vrf Indoor ×1 PKA-A12LA 10,600 BTU · Heat Pump Outdoor ×1 PUZ-A12NKA7 18,000 BTU · Condensing Unit ×1 Ventilation Ortal VERTICAL POWER VENT SYSTEM 250 CFM ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/19/2025 | Permit Issued | KG SPRINKLER CORP | Sprinkler System |
| 11/12/2024 | Permit Issued | KG SPRINKLER CORP | 26 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2025 | — | — | Gas, Water/Sanitary |
| 09/19/2025 | Permit Issued | HENRY MYERS P & H, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Complete | BASS ELECTRICAL CORP. | General Wiring |
| 04/03/2025 | Complete | ALL WAYS ELECTRIC CORP.W | — |
| 02/02/2022 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 11/16/2021 | Permit Issued | RICHARD NEU | — |
| 04/16/2021 | Complete | CROSSWIRE ELECTRICAL INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/19/2025 | Permit Issued | CERTIFIED OF N.Y. INC | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/05/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/30/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/27/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/25/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/15/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 11/04/2025 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 11/04/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 10/30/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/23/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/21/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/10/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/13/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/16/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/02/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/02/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/24/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/05/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/31/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/28/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/26/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/26/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/31/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/11/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 12/05/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 12/05/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 12/05/2025 | Maintenance information | Alexander Rodsen | energy_progress |
| 12/05/2025 | HVAC-R and service water piping design and insulation | Alexander Rodsen | energy_progress |
| 12/05/2025 | Fire-Resistant Penetrations and Joints | Alexander Rodsen | special |
| 12/02/2025 | Final | SCOTT DEVERE | progress |
| 12/02/2025 | Final | Alexander Rodsen | progress |
| 12/02/2025 | Mechanical Systems | Alexander Rodsen | special |
| 12/02/2025 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 10/14/2025 | Tenant Protection Plan Compliance | IVA FILIPOVIC | special |
| 10/14/2025 | Fire-Resistant Penetrations and Joints | George Showman | special |
| 10/14/2025 | Energy Code Compliance Inspections | George Showman | progress |
| 10/14/2025 | Final | George Showman | progress |
| 09/19/2025 | Final | George Showman | progress |
| 09/19/2025 | Energy Code Compliance Inspections | George Showman | progress |
| 09/19/2025 | Tenant Protection Plan Compliance | — | special |
| 09/19/2025 | Fire-Resistant Penetrations and Joints | George Showman | special |
| 08/17/2025 | Structural Stability – Alterations of existing buildings | GEORGE OZAETA | special |
| 08/17/2025 | Structural Steel - Details | GEORGE OZAETA | special |
| 08/17/2025 | Structural Steel - Welding | GEORGE OZAETA | special |
| 08/17/2025 | Structural Steel - High Strength Bolting | GEORGE OZAETA | special |
| 08/17/2025 | Structural Wood Frame | GEORGE OZAETA | progress |
| 08/17/2025 | Final | GEORGE OZAETA | progress |
| 08/17/2025 | Structural Cold-Formed Steel | GEORGE OZAETA | special |