1899Year Built
2.5Stories
B2Building Class
R4AZoning
2,348 sfGross Floor Area
2Units
Two family frame · 5,000 sf lot · 0.47 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
CellarCreation of mechanical room, installation of two new gas boi2p · 1 filing · 10 docs
Site & exterior11p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/19/2020$575K—KI TOV EQUITIES LLC → Private party$245/sf building
01/03/2020$370K—Private party → KI TOV EQUITIES LLC$158/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TSL Architect403/20/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Inside Design Build603/21/2026
Habtom203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
I&K Development & ConsultingGeneral Contractor207/08/2026
Samuel & Sons P & HPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Rojas Engineering6232403/20/2023
Building Lifecycle
09/26/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
08/11/2023
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
03/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Darlyn Alvarez
03/22/2023
Special inspection requirement — HVAC-R and service water heating equipment
Darlyn Alvarez
03/22/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Darlyn Alvarez
36 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offI&K Development & Consulting09/13/2022
DOB NOWPlumbingSigned-offSamuel & Sons P & H04/20/2022
DOB NOWGeneral ConstructionSigned-offI&K Development & Consulting12/21/2021
1 project · most recent 03/20/2023
Gas
FiledStatusContractorScope
03/20/2023Signed-offSamuel & Sons P & HGas
1 project · most recent 04/01/2023
FiledStatusContractorScope
04/01/2023CompleteInfiniti Electric—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
09/26/2023Pass-Final General Construction Non-Directive 14PassView ↗
08/11/2023Fail-Final General Construction Non-Directive 14FailView ↗
02/13/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/13/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/30/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/18/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
03/22/2023Fire-Resistant Penetrations and JointsDarlyn Alvarezspecial
03/22/2023HVAC-R and service water heating equipmentDarlyn Alvarezenergy_progress
03/22/2023HVAC-R and service water piping design and insulationDarlyn Alvarezenergy_progress
03/22/2023Permanent certificateDarlyn Alvarezenergy_progress
03/22/2023Maintenance informationDarlyn Alvarezenergy_progress
03/22/2023HVAC-R and service water heating system controlsDarlyn Alvarezenergy_progress
01/12/2023Permanent certificateDarlyn Alvarezenergy_progress
01/12/2023Fire-Resistant Penetrations and JointsDarlyn Alvarezspecial
01/12/2023HVAC-R and service water heating system controlsDarlyn Alvarezenergy_progress
01/12/2023Maintenance informationDarlyn Alvarezenergy_progress
01/12/2023HVAC-R and service water heating equipmentDarlyn Alvarezenergy_progress
01/12/2023HVAC-R and service water piping design and insulationDarlyn Alvarezenergy_progress
10/23/2021Fire-Resistance Rated ConstructionDarlyn Alvarezprogress
10/22/2021Fenestration air leakageDarlyn Alvarezenergy_progress
09/16/2021Permanent certificateDarlyn Alvarezenergy_progress
09/16/2021HVAC-R and service water piping design and insulationDarlyn Alvarezenergy_progress
09/16/2021Maintenance informationDarlyn Alvarezenergy_progress
09/12/2021Fire-Resistant Penetrations and JointsDarlyn Alvarezspecial
09/12/2021Insulation placement and R valuesDarlyn Alvarezenergy_progress