Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofDavi5p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Sprinklers
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents · 1 drawing sheet
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents
MECHANICAL SYSTEM
On file for this project
19 documents · 1 drawing sheet
BulkheadDavi2p · 2 filings · 20 docs
ArchitectureStructural
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 1 drawing sheet
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents · 1 drawing sheet
Floor 5Davi28p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Foundation · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 1 drawing sheet
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 4Davi33p · 5 filings · 20 docs
ElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Foundation · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 1 drawing sheet
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 3Davi34p · 5 filings · 20 docs
ElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Foundation · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents · 1 drawing sheet
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 1 drawing sheet
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 2Davi36p · 5 filings · 20 docs
ElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Foundation · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 1 drawing sheet
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Floor 1Davi32p · 6 filings · 20 docs
CivilEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Curb Cut · Foundation · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Structural
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents
Proposed new curb cut filed in conjunction with NB #321729723
On file for this project
2 documents
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
CellarDavi46p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · Foundation · Mechanical Systems · Plumbing · Sprinklers · Structural · Support of Excavation
INSTALLATION OF PIPING AND PLUMBING FIXTURES IN NEW 6 FAMILY BUILDING
On file for this project
26 documents · 1 drawing sheet
Structural work for 5 story building with a cellar.
On file for this project
46 documents · 3 drawing sheets
INSTALL NEW FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13 2007 EDIT, AS MODIFIED BY NYC BC 2014 APPENDIX Q AS PER PLAN, IN CONJUNCTION W/ NYC DOB NB APPLICATION #: 321729723.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Site & exteriorPipe scaffold installation9p · 2 filings · 6 docs
EquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Supported Scaffold
POST APPROVAL AMENDMENT FILED FOR CHANGES TO PLANS.
On file for this project
4 documents · 6 drawing sheets
Proposed construction fence. No change to use, egress or occupancy under this application.
On file for this project
2 documents · 3 drawing sheets