← Back
Miscellaneous one family
474 HANCOCK STREET
BROOKLYN · BIN 3046018
💬 Discuss this project
1901Year Built
2Stories
A9Building Class
R6BZoning
1,120 sfGross Floor Area
1Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Miscellaneous one family · Owner of record: DH 474 LLC · 2,000 sf lot · 0.56 FAR built · Flood zone X
Locations of Work
Roof2p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DH 474603/21/2026
547 ROGERS203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/17/2025$848K—SMJH GROUP LLC → DH 474 LLC$757/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HT ASSOCIATES404/08/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
HAOTIAN & ASSOCIATES INC.303/21/2026
Building Lifecycle
All (88)Filed (4)Violation (2)Objection (52)Special Inspection (30)
04/08/2026
Filed — Alteration
INSTALL 8'-0" HEIGHT CONSTRUCTION FENCE AS PER PLAN. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01242030-I1
04/03/2026
Objection raised — Zoning
04/03/2026
Objection resolved — Addressed
03/03/2026
Objection raised — Admin
03/03/2026
Objection resolved — Addressed
02/19/2026
Objection resolved — Addressed
01/22/2026
Objection raised — Admin
01/21/2026
Objection resolved — Addressed
01/21/2026
Objection resolved — Addressed
01/15/2026
Filed — New Building
APPLICATION FILED HEREWITH TO PROPOSED NEW FOUR STORY, FOUR FAMILY MULTI-DWELLING RESIDENCE, AND OBTAIN C OF O.
B01283744-S1
01/15/2026
Objection resolved — Addressed
01/14/2026
Objection resolved — Addressed
01/14/2026
Objection resolved — Addressed
01/14/2026
Objection resolved — Addressed
01/14/2026
Objection resolved — Addressed
01/14/2026
Special inspection requirement — Maintenance information
01/14/2026
Special inspection requirement — Electrical motors and elevators
01/14/2026
Special inspection requirement — Metering
01/14/2026
Special inspection requirement — HVAC-R and service water heating system controls
01/14/2026
Special inspection requirement — Energy Code Compliance Inspections
01/14/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
01/13/2026
Objection resolved — Addressed
01/13/2026
Objection resolved — Addressed
01/07/2026
Objection resolved — Addressed
11/14/2025
Objection resolved — Addressed
10/20/2025
Objection raised — Fire_Protection
10/20/2025
Objection raised — Fire_Protection
10/20/2025
Objection raised — Energy
10/20/2025
Objection raised — Scope
10/20/2025
Objection raised — Admin
10/20/2025
Objection raised — Admin
10/20/2025
Objection raised — Zoning
10/20/2025
Objection raised — Structural
10/20/2025
Objection raised — Scope
10/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/07/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
10/07/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
10/02/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
10/01/2025
Objection resolved — Addressed
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Zoning
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Zoning
09/25/2025
Objection raised — Zoning
09/25/2025
Objection raised — Zoning
09/25/2025
Objection raised — Structural
Latest 60 of 88 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDMORELL BUILDERS INC08/13/2018
1 project · most recent 01/15/2026
Sprinkler System
FiledStatusContractorScope
01/15/2026——Sprinkler System
1 project · most recent 01/15/2026
Storm Water/Sanitary
FiledStatusContractorScope
01/15/2026——Storm, Water/Sanitary
1 project · most recent 01/15/2026
Steel Concrete Masonry
FiledStatusContractorScope
01/15/2026——Steel, Concrete, Masonry
1 project · most recent 04/08/2026
Fence
FiledStatusContractorScope
04/08/2026——Fence
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
01/14/2026Maintenance information—energy_progress
01/14/2026Electrical motors and elevators—energy_progress
01/14/2026Metering—energy_progress
01/14/2026HVAC-R and service water heating system controls—energy_progress
01/14/2026Energy Code Compliance Inspections—progress
01/14/2026HVAC-R and service water piping design and insulation—energy_progress
10/07/2025Fire-Resistant Penetrations and Joints—special
10/07/2025Subsurface Investigations (Borings/Test Pits)—special
10/07/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
09/09/2025Fire-Resistance Rated Construction—progress
09/09/2025Air barrier — testing —energy_progress
09/09/2025Lighting controls—energy_progress
09/09/2025Metering—energy_progress
09/09/2025Lighting in dwelling units—energy_progress
09/09/2025Exterior lighting power—energy_progress
09/09/2025Maintenance information—energy_progress
09/09/2025Interior lighting power—energy_progress
09/09/2025Sprinkler Systems—special
09/09/2025Concrete - Cast-In-Place—special
09/09/2025Excavations - Sheeting, Shoring, and Bracing—special
09/09/2025Fire-Resistant Penetrations and Joints—special
09/09/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
09/09/2025Structural Steel - High Strength Bolting—special
09/09/2025Structural Steel - Welding—special
09/09/2025Subgrade Inspections—special
Latest 25 of 38.
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/03/2026B01242030-I1Request digital key ↗
08/21/2026B01241439-I1Request digital key ↗
08/18/2026B01283744-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
08/13/2018321821720Open ↗
02/13/2012320428113Open ↗
▸BISWORK PERMIT APPLICATION1
08/14/2018321821720Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01283744-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01283744-I1Open ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/03/2026B01242030-I1Open ↗
08/21/2026B01241439-I1Open ↗
08/18/2026B01283744-S1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
08/13/2018321821720Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
08/13/2018321821720Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
08/13/2018321821720Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
08/13/2018321821720Open ↗
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B01283744-I1Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST1
08/13/2018321821720Open ↗
▸DOB NOWStreet Tree Checklist1
08/13/2026B01283744-I1Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
08/13/2018321821720Open ↗
▸DOB NOWOER: Notice to Proceed1
08/13/2026B01283744-I1Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
08/13/2018321821720Open ↗
▸Inspections & Test Reports3
▸DOB NOWSOIL REPORT2
08/13/2026B01283744-S1Open ↗
08/13/2026B01283744-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B01283744-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
02/13/2012320428113Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
08/13/2018321821720Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
08/13/2018321821720Open ↗
02/13/2012320428113Open ↗
▸Other Documents7
▸DOB NOWProperty Ownership Certification2
08/21/2026B01241439-I1Open ↗
08/18/2026B01283744-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01283744-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01283744-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026B01241439-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026B01241439-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026B01241439-I1Open ↗