← Back
Two family frame
4762 CARPENTER AVENUE
BRONX · Wakefield-Woodlawn · BIN 2071701
💬 Discuss this project
1915Year Built
2Stories
B2Building Class
R4AZoning
3,366 sfGross Floor Area
2Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Two family frame · 3,465 sf lot · 0.97 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof2p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC110/29/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNCO CAPITAL203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNCO CAPITAL LLCGeneral Contractor203/21/2026
BERGER QUALITY ELEC'L CONElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854110/29/2024
Building Lifecycle
All (13)Filed (1)Permit Issued (1)Signed Off (1)Violation (2)Objection (2)Special Inspection (6)
03/29/2025
Violation issued (ECB, open)
Unknown
03/14/2025
Signed off — Alteration
X01126369-I1
12/09/2024
Violation issued (ECB, closed)
Construction
12/05/2024
Permit issued — Solar
X01126369-I1-SL
11/26/2024
Objection resolved — Addressed
11/14/2024
Objection raised — Admin
10/29/2024
Filed — Alteration
X01126369-I1
10/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
10/14/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
10/14/2024
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
TOM PETERSEN
10/14/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
10/14/2024
Special inspection requirement — Final
TOM PETERSEN
10/14/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNCO CAPITAL LLC12/05/2024
3 projects · most recent 07/10/2025
HVAC Wiring
FiledStatusContractorScope
07/10/2025CompleteMIDNIGHT ELECTRIC CORPHVAC Wiring
11/04/2024CompleteBERGER QUALITY ELEC'L CON3 meters
10/17/2024CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
10/14/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
10/14/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
10/14/2024Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)TOM PETERSENspecial
10/14/2024Energy Code Compliance InspectionsTOM PETERSENprogress
10/14/2024FinalTOM PETERSENprogress
10/14/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026X01126369-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWSpecial Inspector Seal & Signature3
08/29/2026X01126369-I1Open ↗
08/29/2026X01126369-I1Open ↗
08/29/2026X01126369-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/29/2026X01126369-I1Open ↗
08/29/2026X01126369-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026X01126369-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01126369-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01126369-I1Open ↗