Floor 11 filing · 4 docs
Filed — no permit issued49p · 1 filing · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BBM CONSTRUCTION309/01/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DJLU ARCHITECT208/20/2026
ELEVATED ENGINEERING NYC406/25/2026
Building Lifecycle
All (63)Filed (6)Objection (30)Special Inspection (27)
08/26/2026
Objection resolved — Resolved
08/26/2026
Objection resolved — Resolved
08/26/2026
Objection resolved — Resolved
08/25/2026
Special inspection requirement — Lighting in dwelling units
08/20/2026
Filed — New Building
FOUNDATION FILED IN CONJUNCTION WITH GC # B01395686-I1
B01395686-S7
08/18/2026
Objection resolved — Resolved
08/18/2026
Objection resolved — Resolved
08/18/2026
Special inspection requirement — Air barrier - visual inspection
08/18/2026
Special inspection requirement — Lighting controls
08/18/2026
Special inspection requirement — Metering
08/18/2026
Special inspection requirement — Protection of exposed foundation insulation
08/18/2026
Special inspection requirement — Air barrier — testing
08/18/2026
Special inspection requirement — Electrical motors and elevators
08/18/2026
Special inspection requirement — Exterior lighting power
08/18/2026
Special inspection requirement — Fenestration areas
08/18/2026
Special inspection requirement — Interior lighting power
08/18/2026
Special inspection requirement — Fenestration air leakage
08/18/2026
Special inspection requirement — Insulation placement and R values
08/18/2026
Special inspection requirement — Maintenance information
08/18/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
08/17/2026
Objection resolved — Resolved
08/17/2026
Special inspection requirement — Energy Code Compliance Inspections
08/17/2026
Special inspection requirement — Fire-Resistance Rated Construction
08/17/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
08/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/17/2026
Special inspection requirement — Sprayed fire-resistant materials
07/15/2026
Objection raised — Other
07/15/2026
Objection raised — Other
07/15/2026
Objection raised — Other
07/13/2026
Objection resolved — Resolved
07/13/2026
Objection resolved — Addressed
07/13/2026
Objection resolved — Addressed
07/06/2026
Objection resolved — Resolved
07/06/2026
Objection resolved — Resolved
07/06/2026
Objection resolved — Resolved
07/06/2026
Objection resolved — Resolved
07/06/2026
Objection resolved — Resolved
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/29/2026
Objection raised — Other
06/25/2026
Filed — New Building
FOUNDATION FILED IN CONJUNCTION WITH GC # B01395686-I1
B01395686-S1
06/15/2026
Filed — New Building
FOUNDATION FILED IN CONJUNCTION WITH GC # B01395686-I1
B01395686-S3
06/15/2026
Filed — New Building
FOUNDATION FILED IN CONJUNCTION WITH GC # B01395686-I1
B01395686-S2
06/15/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
06/11/2026
Objection resolved — Resolved
06/09/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
06/09/2026
Special inspection requirement — Concrete - Cast-In-Place
06/09/2026
Special inspection requirement — Construction Operations Influencing Adjacent Structures
06/09/2026
Special inspection requirement — Subgrade Inspections
05/26/2026
Objection raised — Other
05/13/2026
Special inspection requirement — Footing and Foundation
05/13/2026
Special inspection requirement — Final
Latest 60 of 63 events.
Nothing on file for this building.
1 project · most recent 11/11/2024
FiledStatusContractorScope
11/11/2024Permit IssuedBBM CONSTRUCTION CORP1 scope_items
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
08/25/2026Lighting in dwelling units—energy_progress
08/18/2026Air barrier - visual inspection—energy_progress
08/18/2026Lighting controls—energy_progress
08/18/2026Metering—energy_progress
08/18/2026Protection of exposed foundation insulation—energy_progress
08/18/2026Air barrier — testing —energy_progress
08/18/2026Electrical motors and elevators—energy_progress
08/18/2026Exterior lighting power—energy_progress
08/18/2026Fenestration areas—energy_progress
08/18/2026Interior lighting power—energy_progress
08/18/2026Fenestration air leakage—energy_progress
08/18/2026Insulation placement and R values—energy_progress
08/18/2026Maintenance information—energy_progress
08/18/2026Fenestration and door U-factor and product ratings—energy_progress
08/17/2026Energy Code Compliance Inspections—progress
08/17/2026Fire-Resistance Rated Construction—progress
08/17/2026Exterior Insulation and Finish Systems (EIFS)—special
08/17/2026Fire-Resistant Penetrations and Joints—special
08/17/2026Sprayed fire-resistant materials—special
06/15/2026Structural Stability – Alterations of existing buildings—special
06/09/2026Subsurface Investigations (Borings/Test Pits)—special
06/09/2026Concrete - Cast-In-Place—special
06/09/2026Construction Operations Influencing Adjacent Structures—special
06/09/2026Subgrade Inspections—special
05/13/2026Footing and Foundation—progress
Latest 25 of 27.
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/23/2026B01133810-I1Request digital key ↗
08/15/2026B01395686-I1Request digital key ↗
08/15/2026B01395686-S2Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026B01395686-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026B01395686-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/15/2026B01395686-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/22/2026B01395686-S7Open ↗
08/16/2026B01395686-S3Open ↗
08/16/2026B01395686-S2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature1
09/28/2026B01133810-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/15/2026B01395686-I1Open ↗
▸Inspections & Test Reports1
▸DOB NOWSOIL REPORT1
08/15/2026B01395686-S1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/15/2026B01395686-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026B01395686-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/15/2026B01395686-I1Open ↗