| Owner | Filings | Most Recent |
|---|---|---|
| KAISHENG REALTY SEVEN | 48 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/30/2025 | $2.6M | — | KAISHENG REALTY SEVEN LLC → Private party | $930/sf building |
| 07/27/2022 | $998K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| LI ARCHITECT ASSOCIATE, PLLC | 13 | 10/30/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| LI ARCHITECT ASSOCIATE | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRIMROSE SERVICE INC | General Contractor | 11 | 07/08/2026 |
| DYNASTY CONTRACTING LLC | General Contractor | 6 | 03/21/2026 |
| VILLAGE P & H NY INC | Plumbing | 2 | 07/08/2026 |
| KJK ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| VILLAGE P & H NY INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LI ARCHITECT ASSOCIATE, P | 1104 | 10 | 10/30/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 09/29/2024 |
| DOB NOW | Curb Cut | Signed-off | PRIMROSE SERVICE INC | 08/22/2024 |
| DOB NOW | Structural | Signed-off | PRIMROSE SERVICE INC | 12/27/2023 |
| DOB NOW | Plumbing | Signed-off | VILLAGE P & H NY INC | 11/17/2023 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 09/20/2023 |
| DOB NOW | Construction Fence | Signed-off | PRIMROSE SERVICE INC | 08/16/2023 |
| DOB NOW | General Construction | Signed-off | PRIMROSE SERVICE INC | 08/16/2023 |
| DOB NOW | Foundation | Permit Issued | PRIMROSE SERVICE INC | 08/16/2023 |
| DOB NOW | Earth Work | Signed-off | DYNASTY CONTRACTING LLC | 07/14/2023 |
| DOB NOW | Construction Fence | Signed-off | DYNASTY CONTRACTING LLC | 05/18/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Signed-off | PRIMROSE SERVICE INC | Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Signed-off | PARAMOUNT SERVICES, LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Signed-off | VILLAGE P & H NY INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/19/2024 | Cancelled | KJK ELECTRIC INC | — |
| 01/19/2024 | Complete | KJK ELECTRIC INC | — |
| 10/23/2023 | Complete | KJK ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Signed-off | VILLAGE P & H NY INC | Steel, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Signed-off | VILLAGE P & H NY INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/21/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/03/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/30/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/24/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/06/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/04/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/14/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/14/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/30/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/02/2024 | Permanent certificate | Ling Li | energy_progress |
| 12/02/2024 | Fire-Resistant Penetrations and Joints | Ling Li | special |
| 12/02/2024 | Subgrade Inspections | Ling Li | special |
| 12/02/2024 | Concrete - Cast-In-Place | Ling Li | special |
| 12/02/2024 | Mechanical Systems | Ling Li | special |
| 12/02/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Ling Li | special |
| 12/02/2024 | Masonry | Ling Li | special |
| 12/02/2024 | Final | Ling Li | progress |
| 12/02/2024 | Preliminary | Ling Li | progress |
| 12/02/2024 | Energy Code Compliance Inspections | Ling Li | progress |
| 12/02/2024 | Fire-Resistance Rated Construction | Ling Li | progress |
| 12/02/2024 | Footing and Foundation | Ling Li | progress |
| 12/02/2024 | Electric vehicle service equipment requirements | Ling Li | energy_progress |
| 12/02/2024 | HVAC-R and service water heating equipment | Ling Li | energy_progress |
| 12/02/2024 | Fenestration areas | Ling Li | energy_progress |
| 12/02/2024 | Air barrier — testing | Ling Li | energy_progress |
| 12/02/2024 | Maintenance information | Ling Li | energy_progress |
| 12/02/2024 | HVAC-R and service water piping design and insulation | Ling Li | energy_progress |
| 12/02/2024 | Ventilation and air distribution system | Ling Li | energy_progress |
| 12/02/2024 | Interior lighting power | Ling Li | energy_progress |
| 12/02/2024 | Air barrier - visual inspection | Ling Li | energy_progress |
| 12/02/2024 | Fenestration air leakage | Ling Li | energy_progress |
| 12/02/2024 | Fenestration and door U-factor and product ratings | Ling Li | energy_progress |
| 12/02/2024 | Insulation placement and R values | Ling Li | energy_progress |
| 12/02/2024 | Duct leakage testing, insulation and design | Ling Li | energy_progress |