← Back
Two stories - detached, small or mid-size
48-19 213 STREET
QUEENS · Bayside · BIN 4158396
💬 Discuss this project
1940Year Built
2.5Stories
A1Building Class
R2AZoning
1,495 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 4,000 sf lot · 0.37 FAR built · Flood zone X
Locations of Work
Electrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction3p · 1 filing · 8 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/13/2016$819K—— → —$548/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC112/29/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036112/29/2025
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
12/31/2025
Permit issued — Solar
Q01339804-I1-SL
12/29/2025
Filed — Alteration
Q01339804-I1
12/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
12/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUL AHSAN
12/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
12/24/2025
Special inspection requirement — Final
Ayracon Almaraz
12/24/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedTRINITY SOLAR LLC12/31/2025
1 project · most recent 12/23/2025
FiledStatusContractorScope
12/23/2025Permit IssuedREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/24/2025Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
12/24/2025Structural Stability – Alterations of existing buildingsKAMRUL AHSANspecial
12/24/2025Energy Code Compliance InspectionsAyracon Almarazprogress
12/24/2025FinalAyracon Almarazprogress
12/24/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026Q01339804-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/22/2026Q01339804-I1Open ↗
08/22/2026Q01339804-I1Open ↗
08/22/2026Q01339804-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/22/2026Q01339804-I1Open ↗
08/22/2026Q01339804-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01339804-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01339804-I1Open ↗