| Owner | Filings | Most Recent |
|---|---|---|
| GENESIS NYC CONSTRUCTION | 11 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/29/2019 | $845K | — | SHANGHAI ENTERPRISES LLC → Private party | $425/sf building |
| 03/08/2018 | $475K | — | NEW YORK CITY SHERIFF → SHANGHAI ENTERPRISES LLC | $239/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FIRST HEC DESIGN INC. | 5 | 07/23/2020 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GENESIS NYC CONSTRUCTION | General Contractor | 7 | 07/08/2026 |
| INTELOGIC ELECTRIC, INC. | Electrical | 1 | 03/22/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| POLY ENGINEER, P.C. | 6110 | 2 | 07/23/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | GENESIS NYC CONSTRUCTION | 11/12/2019 |
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 08/22/2019 |
| DOB NOW | Construction Fence | Signed-off | GENESIS NYC CONSTRUCTION | 07/09/2019 |
| DOB NOW | Construction Fence | Signed-off | GENESIS NYC CONSTRUCTION | 06/19/2019 |
| BIS | — | ISSUED | GENESIS NYC CONSTRUCTION | 06/23/2020 |
| BIS | OT | ISSUED | GENESIS NYC CONSTRUCTION | 06/23/2020 |
| BIS | — | ISSUED | GENESIS NYC CONSTRUCTION | 08/26/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/28/2020 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 08/16/2019 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/23/2020 | HVAC insulation and sealing | De Gao | energy_progress |
| 07/23/2020 | Smoke Control Systems Testing | De Gao | special |
| 07/23/2020 | Heating Systems | De Gao | special |
| 07/23/2020 | Mechanical Systems | De Gao | special |
| 07/23/2020 | Energy Code Compliance Inspections | De Gao | progress |
| 07/23/2020 | Final | De Gao | progress |
| 07/23/2020 | Electrical motors | De Gao | energy_progress |
| 07/23/2020 | HVAC and service water heating system controls | De Gao | energy_progress |
| 07/23/2020 | Maintenance information | De Gao | energy_progress |
| 07/23/2020 | HVAC and service water heating equipment | De Gao | energy_progress |
| 07/23/2020 | Permanent certificate | De Gao | energy_progress |
| 07/23/2020 | Duct leakage testing | De Gao | energy_progress |
| 07/23/2020 | Shutoff dampers | De Gao | energy_progress |
| 07/22/2020 | Maintenance information | De Gao | energy_progress |
| 07/22/2020 | Heating Systems | De Gao | special |
| 07/22/2020 | Mechanical Systems | De Gao | special |
| 07/22/2020 | Smoke Control Systems Testing | De Gao | special |
| 07/22/2020 | Energy Code Compliance Inspections | De Gao | progress |
| 07/22/2020 | Final | De Gao | progress |
| 07/22/2020 | Permanent certificate | De Gao | energy_progress |
| 07/22/2020 | HVAC and service water heating equipment | De Gao | energy_progress |
| 07/22/2020 | Duct leakage testing | De Gao | energy_progress |
| 07/22/2020 | HVAC insulation and sealing | De Gao | energy_progress |
| 07/22/2020 | Shutoff dampers | De Gao | energy_progress |
| 07/22/2020 | HVAC and service water heating system controls | De Gao | energy_progress |