← Back
One story - permanent living quarter
48-52 208 STREET
QUEENS · BIN 4158190
💬 Discuss this project
1950Year Built
1Stories
A2Building Class
R2AZoning
1,025 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.26 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Floor 14p · 1 filing · 16 docs
Cellar4p · 1 filing · 16 docs
Basement1p · 1 filing · 16 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A2 ARCHITECTURE305/06/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PAMI CONSTRUCTION CORPGeneral Contractor204/09/2026
ALL WAYS ELECTRIC CORP.WElectrical103/22/2026
UNLIMITED PLG SOLUTIONSPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A2 ARCHITECTURE2736205/06/2025
Building Lifecycle
All (33)Filed (3)Permit Issued (3)Inspection (2)Objection (12)Special Inspection (13)
12/08/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/11/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/19/2025
Permit issued — Mechanical Systems
Q01197402-S2-MS
05/06/2025
Filed — Alteration
Replace tub, shower, lavatory & wc at 1st floor. Replace kitchen sink and dishwasher at first floor. Replace lavatory, wc, washing machine and laundry sink at cellar. Add new 3-piece (lavatory, wc & shower) at ground floor
Q01197402-S2
05/05/2025
Special inspection requirement — Energy Code Compliance Inspections
Anna Abramowicz
05/05/2025
Special inspection requirement — HVAC-R and service water heating equipment
Anna Abramowicz
05/05/2025
Special inspection requirement — Ventilation and air distribution system
Anna Abramowicz
05/05/2025
Special inspection requirement — Duct leakage testing, insulation and design
Anna Abramowicz
05/05/2025
Special inspection requirement — HVAC-R and service water heating system controls
Anna Abramowicz
05/05/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Anna Abramowicz
04/16/2025
Permit issued — Plumbing
Q01197402-S1-PL
04/15/2025
Permit issued — General Construction
Q01197402-I1-GC
04/08/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Objection resolved — Addressed
04/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Anna Abramowicz
04/03/2025
Objection raised — Plumbing
04/03/2025
Objection raised — Fire_Protection
04/03/2025
Objection raised — Other
04/03/2025
Objection raised — Plumbing
04/03/2025
Objection raised — Scope
04/02/2025
Filed — Alteration
Replace tub, shower, lavatory & wc at 1st floor. Replace kitchen sink and dishwasher at first floor. Replace lavatory, wc, washing machine and laundry sink at cellar. Add new 3-piece (lavatory, wc & shower) at ground floor
Q01197402-S1
03/25/2025
Objection raised — Scope
03/25/2025
Objection resolved — Addressed
03/20/2025
Filed — Alteration
Replace tub, shower, lavatory & wc at 1st floor. Replace kitchen sink and dishwasher at first floor. Replace lavatory, wc, washing machine and laundry sink at cellar. Add new 3-piece (lavatory, wc & shower) at ground floor
Q01197402-I1
03/20/2025
Special inspection requirement — Fire-Resistance Rated Construction
Anna Abramowicz
03/19/2025
Special inspection requirement — Final
Anna Abramowicz
03/19/2025
Special inspection requirement — Mechanical Systems
Anna Abramowicz
03/19/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Anna Abramowicz
03/19/2025
Special inspection requirement — Insulation placement and R values
Anna Abramowicz
03/19/2025
Special inspection requirement — Final
Anna Abramowicz
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedPAMI CONSTRUCTION CORP05/19/2025
DOB NOWPlumbingSigned-offCENTA PLBG & HTG INC04/16/2025
DOB NOWGeneral ConstructionPermit IssuedPAMI CONSTRUCTION CORP04/15/2025
BISOTISSUEDPRO CUSTOM SOLAR LLC01/08/2019
BISPLISSUEDJOHNNY'S P&H CONTRAC INC01/30/2003
BISOTISSUEDNEW PAL CONSTRUCTION CORP08/08/2002
1 project · most recent 05/06/2025
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/06/2025Permit IssuedPAMI CONSTRUCTION CORPAir Conditioning Systems
Cooling
York York YC2F 42,000 BTU · Condensing Unit ×1
1 project · most recent 05/06/2025
Water/Sanitary
FiledStatusContractorScope
05/06/2025Signed-offUNLIMITED PLG SOLUTIONSWater/Sanitary
3 projects · most recent 04/17/2025
General Wiring
FiledStatusContractorScope
04/17/2025Permit IssuedNY CITY ELECTRIC INCGeneral Wiring
10/16/2024Permit IssuedALL WAYS ELECTRIC CORP.W—
03/11/2019CompleteISLAND ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
12/08/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/11/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
05/05/2025Energy Code Compliance InspectionsAnna Abramowiczprogress
05/05/2025HVAC-R and service water heating equipmentAnna Abramowiczenergy_progress
05/05/2025Ventilation and air distribution systemAnna Abramowiczenergy_progress
05/05/2025Duct leakage testing, insulation and designAnna Abramowiczenergy_progress
05/05/2025HVAC-R and service water heating system controlsAnna Abramowiczenergy_progress
05/05/2025HVAC-R and service water piping design and insulationAnna Abramowiczenergy_progress
04/08/2025Fire-Resistant Penetrations and JointsAnna Abramowiczspecial
03/20/2025Fire-Resistance Rated ConstructionAnna Abramowiczprogress
03/19/2025FinalAnna Abramowiczprogress
03/19/2025Mechanical SystemsAnna Abramowiczspecial
03/19/2025Fenestration and door U-factor and product ratingsAnna Abramowiczenergy_progress
03/19/2025Insulation placement and R valuesAnna Abramowiczenergy_progress
03/19/2025FinalAnna Abramowiczprogress
▾Documents — 38 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/20/2026Q01197402-S1Request digital key ↗
08/20/2026Q01197402-I1Request digital key ↗
08/20/2026Q01197402-P3Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
01/04/2019440528742Open ↗
▸BISWORK PERMIT APPLICATION1
01/04/2019440528742Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/20/2026Q01197402-P3Open ↗
08/13/2026Q01197402-I1Open ↗
08/13/2026Q01197402-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/29/2026Q01197402-S2Open ↗
09/29/2026Q01197402-S2Open ↗
09/01/2026Q01197402-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/29/2026Q01197402-S2Open ↗
09/27/2026Q01197402-S1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
01/04/2019440528742Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
01/04/2019440528742Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/04/2019440528742Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
01/04/2019440528742Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/20/2026Q01197402-P3Open ↗
08/13/2026Q01197402-I1Open ↗
08/13/2026Q01197402-S2Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
01/04/2019440528742Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
12/31/2019440528742Open ↗
01/04/2019440528742Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/04/2019440528742Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/31/2019440528742Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
01/04/2019440528742Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
12/31/2019440528742Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
12/31/2019440528742Open ↗
01/04/2019440528742Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
12/31/2019440528742Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/31/2019440528742Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
12/31/2019440528742Open ↗
01/04/2019440528742Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
01/04/2019440528742Open ↗