← Back
Elevator apt, semi-fireproof with stores
481 FT WASHINGTON AVENUE
MANHATTAN · BIN 1064341
💬 Discuss this project
1936Year Built
6Stories
D7Building Class
R7-2Zoning
56,706 sfGross Floor Area
64Units
LL97 CoveredRent Stabilized12 Open Violations ▸FISP: SAFE
Elevator apt, semi-fireproof with stores · Owner of record: A & M REALTY LLC · 13,275 sf lot · 4.27 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SAFETECH ENTERPRISES503/22/2026
A M REALTY2703/22/2026
A AND B REALTY CO.103/22/2026
ABRO MANAGEMENT103/21/2026
45-18 LLC103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASR ENGINEERING PC111/28/2023
STRUCTURAL ENGINEERING BURO110/13/2023
PAUL PERDEK, PROF. ENG. PLLC110/07/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ADVANCED BUILDERS SERVICES103/21/2026
AE DESIGN SOLUTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EMPIRE NY INSTALLATIONS INCGeneral Contractor807/08/2026
SAFETECH ENTERPRISES CORPGeneral Contractor603/21/2026
JOSEPH VITALEElectrical103/21/2026
SIMENEH SEMEAElectrical103/21/2026
TITAN ELEC'L & ELEV CONTRElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
STRUCTURAL ENGINEERING BU5883210/13/2023
Building Lifecycle
All (97)Filed (3)Permit Issued (6)Signed Off (2)Facade (FISP) (18)Violation (60)Inspection (1)Special Inspection (7)
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
A
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
C
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
C
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, open)
B
06/10/2026
Cycle 10 facade report submitted
06/09/2026
Cycle 10 facade report signed — SAFE
05/29/2026
Cycle 10 facade inspection completed
10/30/2024
Violation issued (HPD, closed)
A
10/30/2024
Violation issued (HPD, closed)
B
10/30/2024
Violation issued (HPD, closed)
B
03/05/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00402091-I1
02/29/2024
Signed off — Alteration
REPLACEMENT OF THE ELEVATOR MACHINE ROOM EXTERIOR MASONRY WALLS
M00903404-I1
01/25/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/04/2023
Permit issued — Supported Scaffold
M00968087-I1-SF
11/28/2023
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CH #33 OF THE NYC CODE 2022. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M00968087-I1
11/14/2023
Violation issued (HPD, closed)
C
11/13/2023
Permit issued — Structural
M00903404-I1-ST
10/15/2023
Violation issued (HPD, closed)
B
10/15/2023
Violation issued (HPD, closed)
A
10/15/2023
Violation issued (HPD, closed)
B
10/15/2023
Violation issued (HPD, closed)
B
10/15/2023
Violation issued (HPD, closed)
C
10/15/2023
Violation issued (HPD, closed)
B
10/13/2023
Filed — Alteration
REPLACEMENT OF THE ELEVATOR MACHINE ROOM EXTERIOR MASONRY WALLS
M00903404-I1
10/11/2023
Special inspection requirement — Tenant Protection Plan Compliance
Ruslan Solovyev
07/13/2023
Special inspection requirement — Structural Cold-Formed Steel
Ruslan Solovyev
07/13/2023
Special inspection requirement — Structural Steel - Details
Ruslan Solovyev
07/13/2023
Special inspection requirement — Masonry
Ruslan Solovyev
07/13/2023
Special inspection requirement — Structural Steel - Welding
Ruslan Solovyev
07/13/2023
Special inspection requirement — Structural Steel - High Strength Bolting
Ruslan Solovyev
07/12/2023
Special inspection requirement — Final
Ruslan Solovyev
03/31/2023
Cycle 9 facade report signed — SAFE
03/01/2023
Cycle 9 facade report submitted
01/31/2023
Permit issued — Sidewalk Shed
M00402091-I1-SH
01/27/2023
Cycle 9 facade inspection completed
12/08/2022
Cycle 9 facade report submitted
12/08/2022
Cycle 9 facade report signed — UNSAFE
11/17/2022
Cycle 9 facade inspection completed
02/15/2022
Permit issued — Sidewalk Shed
M00402091-I1-SH
02/12/2021
Permit issued — Sidewalk Shed
M00402091-I1-SH
12/11/2020
Cycle 9 facade report submitted
11/30/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/30/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/30/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/06/2020
Cycle 9 facade inspection completed
10/17/2020
Cycle 9 facade report signed — UNSAFE
10/12/2020
Permit issued — Sidewalk Shed
M00402091-I1-SH
10/07/2020
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00402091-I1
10/01/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/30/2019
Violation issued (ECB, closed)
Construction
11/14/2018
Violation issued (ECB, closed)
Construction
07/30/2018
Violation issued (ECB, closed)
Local Law
05/31/2018
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/06/2017
Violation issued (HPD, closed)
B
Latest 60 of 97 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedSAFETECH ENTERPRISES CORP12/04/2023
DOB NOWStructuralSigned-offSAFETECH ENTERPRISES CORP11/13/2023
DOB NOWSidewalk ShedSigned-offEMPIRE NY INSTALLATIONS I01/31/2023
DOB NOWSidewalk ShedSigned-offEMPIRE NY INSTALLATIONS I02/15/2022
DOB NOWSidewalk ShedSigned-offEMPIRE NY INSTALLATIONS I02/12/2021
DOB NOWSidewalk ShedSigned-offEMPIRE NY INSTALLATIONS I10/12/2020
BISOTISSUEDSAFETECH ENTERPRISES CORP09/23/2022
BISOTISSUEDSAFETECH ENTERPRISES CORP05/04/2022
BISOTISSUEDRAPID MASONRY RESTORATION CORP08/15/2017
BISEQISSUEDEMPIRE SCAFFOLDING SYSTEM04/03/2012
BISOTISSUEDRAPID MASONRY RESTORATION CORP09/30/2011
BISEQISSUEDEMPIRE SCAFFOLDING SYSTEM09/16/2011
BISFSISSUEDG. BAUER, INC09/06/2011
BISPLISSUEDDOVAL PLBG & HTG CORP02/03/2010
BISOTISSUEDS.M.O CONTRACTORS INC01/13/2010
BISPLISSUEDPRECISION PLBG SVCS., INC09/22/2009
BISOTISSUEDMO'S CONTRACTING CORP06/22/2007
BISOTISSUEDMETROPOLITAN PLBG CORP08/18/1998
BISPLISSUEDMETROPOLITAN PLBG AND HTG08/18/1998
BISBLISSUEDG.BAUER INC05/19/1998
2 projects · most recent 11/15/2023
FiledStatusContractorScope
11/15/2023CompleteTITAN ELEC'L & ELEV CONTR—
09/21/2020CompleteMEGA ELEC'L CONTR'G, INC—
1 project · most recent 11/28/2023
Scaffold
FiledStatusContractorScope
11/28/2023Permit IssuedSAFETECH ENTERPRISES CORPScaffold
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
01/25/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
10/11/2023Tenant Protection Plan ComplianceRuslan Solovyevspecial
07/13/2023Structural Cold-Formed SteelRuslan Solovyevspecial
07/13/2023Structural Steel - DetailsRuslan Solovyevspecial
07/13/2023MasonryRuslan Solovyevspecial
07/13/2023Structural Steel - WeldingRuslan Solovyevspecial
07/13/2023Structural Steel - High Strength BoltingRuslan Solovyevspecial
07/12/2023FinalRuslan Solovyevprogress
▾Documents — 142 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch2
08/29/2026M00903404-I1Request digital key ↗
08/28/2026M00968087-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00402091-I1Request digital key ↗
▸Applications & Permits27
▸BISWORK PERMIT APPLICATION15
09/26/2022123052588Open ↗
05/04/2022123052588Open ↗
04/14/2022123052588Open ↗
Showing 3 of 15 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION11
05/17/2021123052588Open ↗
04/06/2021123052588Open ↗
02/25/2021123052588Open ↗
Showing 3 of 11 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
07/30/2013120821673Open ↗
▸Seals & Professional Certifications32
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
06/27/2017120814743Open ↗
04/24/2017123052588Open ↗
12/10/2012120829559Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST7
04/27/2017123052588Open ↗
04/05/2017123052588Open ↗
10/05/2011120829559Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/30/2026M00903404-I1Open ↗
08/30/2026M00903404-I1Open ↗
08/30/2026M00903404-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
10/05/2011120829559Open ↗
09/29/2011120821673Open ↗
09/19/2011120814743Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/29/2026M00903404-I1Open ↗
08/28/2026M00968087-I1Open ↗
08/13/2026M00402091-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
04/05/2017123052588Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/30/2026M00903404-I1Open ↗
▸Trade Schedules & Equipment8
▸BISSELF-CERT PLUMBING NOTICE4
05/05/2010120123829Open ↗
03/31/2010120123829Open ↗
12/16/2009110319183Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING3
11/02/2009120197269Open ↗
08/06/2009120123829Open ↗
08/21/2008110319183Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
09/19/2011120814743Open ↗
▸Safety & Tenant Protection2
▸BISTenant Protection Plan and Notes1
04/05/2017123052588Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00402091-I1Open ↗
▸Environmental & Asbestos9
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
09/26/2011120829559Open ↗
09/19/2011120814743Open ↗
08/06/2009120123829Open ↗
Showing 3 of 7 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
04/05/2017123052588Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/29/2026M00903404-I1Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
06/27/2017120814743Open ↗
04/24/2017123052588Open ↗
12/10/2012120829559Open ↗
▸BISTECHNICAL REPORT: ENERGY3
10/05/2011120829559Open ↗
09/19/2011120814743Open ↗
09/19/2011120814743Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
06/27/2017120814743Open ↗
12/10/2012120829559Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/07/2023123052588Open ↗
04/06/2021123052588Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
02/07/2023123052588Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
02/07/2023123052588Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
02/07/2023123052588Open ↗
02/07/2023123052588Open ↗
04/06/2021123052588Open ↗
▸Approvals, Objections & Sign-offs16
▸BISADMINISTRATIVE OBJECTIONS6
10/05/2011120829559Open ↗
09/29/2011120821673Open ↗
09/26/2011120829559Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
02/08/2023123052588Open ↗
06/27/2017120814743Open ↗
07/30/2013120821673Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
06/27/2017120814743Open ↗
06/27/2017120814743Open ↗
07/30/2013120821673Open ↗
▸BISFINAL1
02/08/2023123052588Open ↗
▸BISSUPERSEDING LETTER1
04/14/2022123052588Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT9
06/27/2017120814743Open ↗
04/05/2017123052588Open ↗
12/10/2012120829559Open ↗
Showing 3 of 9 on file for this type
▸BISCIVIL PENALTY AFFIDAVIT/REQUEST1
09/26/2022123052588Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
02/07/2023123052588Open ↗
▸Filing & Intake Forms15
▸BISEFILING COVER SHEET7
04/05/2017123052588Open ↗
10/05/2011120829559Open ↗
09/29/2011120821673Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM5
09/26/2022123052588Open ↗
05/04/2022123052588Open ↗
04/26/2022123052588Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION3
05/17/2021123052588Open ↗
03/29/2017120814743Open ↗
02/23/2010120197269Open ↗
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
06/27/2017120814743Open ↗
12/10/2012120829559Open ↗
04/05/2012120821673Open ↗
▸BISSupporting Document: Fee Exempt1
05/24/2010120123829Open ↗