| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/15/2020 | $498K | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| Lester Katz, Ncarb | 5 | 01/23/2024 |
| Eyal Levitt Architect | 2 | 05/04/2023 |
| R & S Associates | 2 | 03/12/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Expediter Group | 8 | 03/21/2026 |
| BDF Design | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Upperlevel Construction | General Contractor | 7 | 03/22/2026 |
| Horbridge Plumbing & Heating | Plumbing | 3 | 07/08/2026 |
| D & F Construction Group | General Contractor | 1 | 03/22/2026 |
| Horbridge Plumbing Heating | General Contractor | 1 | 03/22/2026 |
| Amb Mechanical | Plumbing | 1 | 03/22/2026 |
| BT's Plumbing and Heating | Plumbing | 1 | 07/08/2026 |
| Fried Electric Co | Electrical | 1 | 03/22/2026 |
| Prime Piping & Heating | Fire Protection | 1 | 07/08/2026 |
| Shtral Elect'l Cont'g | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| City-Wide Testing | 416 | 7 | 01/23/2024 |
| Metro Fire Control | 4538 | 2 | 05/04/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | Upperlevel Construction | 12/18/2023 |
| DOB NOW | Sprinklers | Signed-off | Amb Mechanical | 06/08/2023 |
| DOB NOW | Plumbing | Signed-off | Horbridge Plumbing & Heating | 01/06/2023 |
| DOB NOW | Plumbing | Signed-off | BT's Plumbing and Heating | 02/18/2022 |
| DOB NOW | Earth Work | Signed-off | Upperlevel Construction | 03/24/2021 |
| BIS | — | ISSUED | Upperlevel Construction | 09/19/2023 |
| BIS | — | ISSUED | Upperlevel Construction | 02/15/2023 |
| BIS | — | ISSUED | Upperlevel Construction | 08/23/2022 |
| BIS | — | ISSUED | Upperlevel Construction | 02/09/2022 |
| BIS | — | ISSUED | Upperlevel Construction | 03/26/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2024 | Complete | Shtral Elect'l Cont'g | General Wiring |
| 09/14/2021 | Complete | Fried Electric Co | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/31/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/22/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 09/20/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/18/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/14/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/15/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/20/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/20/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/22/2024 | HVAC and service water heating system controls | ELIAS RASABI | energy_progress |
| 01/22/2024 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 01/22/2024 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 01/22/2024 | HVAC and service water heating equipment | ELIAS RASABI | energy_progress |
| 01/22/2024 | HVAC insulation and sealing | ELIAS RASABI | energy_progress |
| 05/08/2023 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 05/08/2023 | Sprinkler Systems | JEFFREY HANDLER | special |
| 03/20/2023 | Sprinkler Systems | JEFFREY HANDLER | special |
| 03/20/2023 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 11/08/2022 | HVAC insulation and sealing | ELIAS RASABI | energy_progress |
| 11/08/2022 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 11/08/2022 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 11/08/2022 | HVAC and service water heating system controls | ELIAS RASABI | energy_progress |
| 11/08/2022 | HVAC and service water heating equipment | ELIAS RASABI | energy_progress |
| 03/11/2021 | Footing and Foundation | ELIAS RASABI | progress |
| 03/11/2021 | Concrete - Cast-In-Place | ELIAS RASABI | special |
| 03/11/2021 | Post-installed Anchors | ELIAS RASABI | special |
| 03/11/2021 | Structural Steel - High Strength Bolting | ELIAS RASABI | special |
| 03/11/2021 | Structural Steel - Welding | ELIAS RASABI | special |
| 03/11/2021 | Wood – High-Load Diaphragms | ELIAS RASABI | special |
| 03/11/2021 | Wood – Metal-Plate-Connected Trusses | ELIAS RASABI | special |
| 03/11/2021 | Structural Wood Frame | ELIAS RASABI | progress |
| 03/11/2021 | Subsurface Conditions – Fill Placement & In-Place Density | ELIAS RASABI | special |
| 03/11/2021 | Subsurface Investigations (Borings/Test Pits) | Soorjbally Harilall | special |
| 03/11/2021 | Final | ELIAS RASABI | progress |