| Owner | Filings | Most Recent |
|---|---|---|
| NAFTALI GROUP | 109 | 08/28/2026 |
| VIK XS SERVICES | 6 | 07/08/2026 |
| 470 KENT AVE ASSOCIATES | 10 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/27/2020 | $51.2M | — | WATERFRONT REALTY II LLC → 470 KENT AVE ASSOCIATES LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| MG ENGINEERING D.P.C. | 23 | 06/24/2026 |
| GC ENG & ASSOCIATES, PC | 6 | 05/15/2026 |
| HTX BUILDING CONSULTING INC | 2 | 10/15/2025 |
| ROBERT GERMAIN JR. PE | 4 | 11/01/2024 |
| GGA STUDIOS, DPC | 1 | 09/06/2024 |
| MCLAREN ENGINEERING GROUP | 7 | 04/25/2024 |
| OSPINO ENGINEERING PLLC | 1 | 04/25/2024 |
| LOMBARDO PROFESSIONAL ENGINEERING | 5 | 10/27/2023 |
| PLAN B ENGINEERING | 6 | 10/16/2023 |
| HIGHBURY CONCRETE | 2 | 08/17/2023 |
| DOKA USA | 1 | 07/20/2023 |
| DESIMONE CONSULTING ENGINEERING | 4 | 05/23/2022 |
| MUESER RUTLEDGE CONSULTING ENGINEER | 2 | 02/10/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMANI CONSULTING | 38 | 03/21/2026 |
| LOMBARDO PROFESSIONAL ENGINEERING | 2 | 03/21/2026 |
| HTX BUILDING CONSULTING | 5 | 03/21/2026 |
| EUROCELT EXPEDITING, INC | 12 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 8 | 03/21/2026 |
| AO CONSULTING AND DRAFTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEW LINE STRUCTURES & DEV | General Contractor | 24 | 07/08/2026 |
| KG SPRINKLER CORP | Fire Protection | 12 | 07/08/2026 |
| PLATFORM SOLUTIONS, INC | General Contractor | 12 | 07/08/2026 |
| HIGHBURY CONCRETE, INC | General Contractor | 7 | 07/08/2026 |
| DONATO PLUMBING GROUP INC | Plumbing | 5 | 07/08/2026 |
| ELICC AMERICAS CORPORATION | General Contractor | 4 | 07/08/2026 |
| BEST PRICE RENOVATIONS LL | General Contractor | 3 | 04/09/2026 |
| AGIR ELEC'L LTD. D/B/A | Electrical | 2 | 03/22/2026 |
| C C CONTROLLED COMBUSTION | General Contractor | 2 | 03/21/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| DONATO, INC | Plumbing | 2 | 07/08/2026 |
| A & E PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| PREMIER FLOW PLBG AND HTG | Plumbing | 1 | 07/08/2026 |
| PREMIER FLOW PLBG AND HTG | Fire Protection | 1 | 07/08/2026 |
| LEIBY FISCHER | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN SPECIAL ENGINEERING | 2018 | 8 | 05/15/2026 |
| DOMANI INSPECTION SERVICE | 843 | 15 | 09/03/2025 |
| ROBERT F. GERMAIN JR. PE | 5100 | 4 | 11/01/2024 |
| DESIMONE CONSULTING ENGIN | 5942 | 4 | 05/23/2022 |
| MUESER RUTLEDGE CONSULTIN | 977 | 2 | 02/10/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | GALICJA PLBG AND HTG.CORP | 02/19/2026 |
| DOB NOW | Sprinklers | Signed-off | GALICJA PLBG AND HTG CORP | 02/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | BEST PRICE RENOVATIONS LL | 02/05/2026 |
| DOB NOW | General Construction | Permit Issued | BEST PRICE RENOVATIONS LL | 11/26/2025 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 11/12/2025 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 11/12/2025 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING GROUP INC | 11/07/2025 |
| DOB NOW | General Construction | Permit Issued | BEST PRICE RENOVATIONS LL | 10/02/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | UNIVERSAL STEEPLEJACK INC | 06/24/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | VIK XS SERVICES INC | 04/16/2025 |
| DOB NOW | Curb Cut | Signed-off | NEW LINE STRUCTURES & DEV | 02/27/2025 |
| DOB NOW | Curb Cut | Signed-off | NEW LINE STRUCTURES & DEV | 02/27/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | NEW LINE STRUCTURES & DEV | 01/13/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | NEW LINE STRUCTURES & DEV | 01/02/2025 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING GROUP INC | 12/03/2024 |
| DOB NOW | General Construction | Signed-off | C C CONTROLLED COMBUSTION | 11/21/2024 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 11/13/2024 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING GROUP INC | 11/12/2024 |
| DOB NOW | Structural | Signed-off | NEW LINE STRUCTURES & DEV | 10/28/2024 |
| DOB NOW | Boiler Equipment | Signed-off | A & E PLUMBING CORP | 10/17/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 10/04/2024 |
| DOB NOW | General Construction | Signed-off | NEW LINE STRUCTURES & DEV | 10/03/2024 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 09/25/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 09/16/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 09/11/2024 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 09/11/2024 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 09/10/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 05/14/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | VIK XS SERVICES INC | 04/26/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | INTERSYSTEMS INSTAL S&S | 01/30/2024 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING GROUP INC | 11/30/2023 |
| DOB NOW | Structural | Signed-off | NEW LINE STRUCTURES & DEV | 10/19/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 10/16/2023 |
| DOB NOW | Structural | Signed-off | NEW LINE STRUCTURES & DEV | 10/12/2023 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING GROUP INC | 09/28/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 09/25/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 09/22/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 09/18/2023 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 08/31/2023 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 08/31/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/08/2025 | — | — | Air Conditioning Systems | Cooling |
| 04/23/2025 | Permit Issued | NEW LINE STRUCTURES & DEV | Air Conditioning Systems, Cooling Towers, Heating Systems | Cooling Ice Air 8VSHPW24 855 CFM · Heat Pump Outdoor ×126 8VSHPW12 440 CFM · Heat Pump Outdoor ×105 8VSHPW15 545 CFM · Heat Pump Outdoor ×41 8VSHPW18 680 CFM · Heat Pump Outdoor ×38 Climatemaster TSH030CHS28ULPS 1,000 CFM · Wshp ×13 TSH018BGS28TRBS 650 CFM · Wshp ×6 TSH006AGS18TLSS 240 CFM · Wshp ×4 TSH012AGS18TRBS 10,800 CFM · Wshp ×4 TCH072AHP2A4LSS 65,100 BTU · Wshp ×1 TSH012AGC18TRBS 350 CFM · Wshp ×2 TSH036CHS28ULPS 1,200 CFM · Wshp ×2 TSH048CHS28ULWS 47,000 BTU · Wshp ×1 TSH072AHPA4LSS 2,400 CFM · Wshp ×2 TSSH012AGS18TRBS 350 CFM · Wshp ×2 TSM-24 855 CFM · Heat Pump Outdoor ×126 TSM-12 440 CFM · Heat Pump Outdoor ×105 TSM-15 545 CFM · Heat Pump Outdoor ×41 TSM-18 680 CFM · Heat Pump Outdoor ×38 Aaon CFA-004-A-A-3 1,600 CFM · Rooftop Unit ×2 RN-006 1,200 CFM · Rooftop Unit ×2 RN-016 4,500 CFM · Rooftop Unit ×2 Heating Aerco BMK5000N 5,000,000 BTU · Boiler ×6 Cooling Tower Evapco AT39-3K36 900 tons · Cooling Tower ×2 |
| 11/13/2024 | Permit Issued | NEW LINE STRUCTURES & DEV | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2025 | Signed-off | KG SPRINKLER CORP | 10,026 heads, 3 outlets |
| 11/13/2024 | Permit Issued | KG SPRINKLER CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Signed-off | DONATO PLUMBING GROUP INC | Gas, Storm, Water/Sanitary |
| 11/13/2024 | Signed-off | DONATO PLUMBING GROUP INC | Water/Sanitary |
| 04/25/2024 | Signed-off | ACCURATE MECHANICAL INC | Storm |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/28/2026 | Complete | JAM ELECTRICAL CORP | — |
| 12/16/2025 | Permit Issued | SHTRAL ELECT'L CONT'G COR | General Wiring |
| 10/31/2024 | Permit Issued | MACK ELECTRICAL INC | General Wiring |
| 01/25/2024 | Complete | AGIR ELEC'L LTD. D/B/A | General Wiring |
| 05/16/2023 | Complete | AGIR ELEC'L LTD. D/B/A | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/23/2022 | Signed-off | NEW LINE STRUCTURES & DEV | 4 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/25/2024 | Permit Issued | VIK XS SERVICES INC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/16/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/20/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/20/2026 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 06/12/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/21/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/23/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/21/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/21/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/27/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/05/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/17/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/16/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/16/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/09/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/06/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 12/31/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 12/26/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/24/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/10/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/06/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/22/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 07/22/2026 | Lighting controls | William Ryan | energy_progress |
| 07/22/2026 | Interior lighting power | William Ryan | energy_progress |
| 07/22/2026 | Electrical motors and elevators | William Ryan | energy_progress |
| 07/22/2026 | Energy Code Compliance Inspections | William Ryan | progress |
| 07/22/2026 | Tenant Protection Plan Compliance | — | special |
| 07/16/2026 | HVAC-R and service water heating equipment | William Ryan | energy_progress |
| 07/16/2026 | Maintenance information | William Ryan | energy_progress |
| 07/16/2026 | HVAC-R and service water piping design and insulation | William Ryan | energy_progress |
| 07/16/2026 | Energy Code Compliance Inspections | — | progress |
| 07/16/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 07/16/2026 | Tenant Protection Plan Compliance | William Ryan | special |
| 07/10/2026 | Post-installed Anchors | — | special |
| 07/10/2026 | Energy Code Compliance Inspections | — | progress |
| 07/10/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 05/14/2026 | HVAC-R and service water piping design and insulation | William Ryan | energy_progress |
| 05/14/2026 | Maintenance information | William Ryan | energy_progress |
| 05/14/2026 | Tenant Protection Plan Compliance | William Ryan | special |
| 05/14/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 05/14/2026 | HVAC-R and service water heating equipment | William Ryan | energy_progress |
| 05/04/2026 | Maintenance information | William Ryan | energy_progress |
| 05/04/2026 | HVAC-R and service water heating equipment | William Ryan | energy_progress |
| 05/04/2026 | Shutoff dampers | William Ryan | energy_progress |
| 05/04/2026 | Mechanical Systems | William Ryan | special |
| 05/04/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |