Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsProcida Companies, LLC5 filings
INSTALLATION OF PLUMBING FIXTURES AND PIPING AS PER PLANS FILED. NO CHANGE TO USE, EGRESS, OR OCCUPANCY. FILED IN CONJUNCTION WITH NB #321600497
On file for this project
20 documents
Install combined sprinkler/standpipe system as per plans filed. No change to use, egress oroccupancy. Filed in conjunction with NB#321600497.
On file for this project
2 documents
Structural work as per plans filed in conjunction with NB# 321600497.
On file for this project
11 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
RoofSuspended scaffolding installation2p · 2 filings · 4 docs
ArchitectureEquipmentFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
INSTALLATION OF TWO POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
INSTALLATION OF 300PSF SIDEWALK SHED, OVERHEAD PROTECTION AND ROOF PROTECTION AS PER PLANS.ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE NYC CODE 2022. NO USE IN EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 1 drawing sheet
BulkheadSuspended scaffolding installation2p · 2 filings · 8 docs
ArchitectureStructural
INSTALLATION OF TWO POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
INSTALLATION OF MULTI-POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 7Two point suspended scaffolding1p · 1 filing
ElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
INSTALLATION OF TWO POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 6Two point suspended scaffolding1p · 1 filing
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
INSTALLATION OF TWO POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 5Two point suspended scaffolding1p · 1 filing
ElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
INSTALLATION OF TWO POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 4Two point suspended scaffolding1p · 1 filing
ElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
INSTALLATION OF TWO POINT SUSPENDED SCAFFOLDING IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 3
Floor 2
Floor 1Procida Development Group3 filings
EquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Curb Cut · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Support of Excavation
Install 13 ft. curb cut as per plans filed to provide access to parking garage as per plans filed. No change use, egress or occupancy. Filed in conjunction with NB# 321600497.
On file for this project
2 documents
Provide support of excavation work as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB #321600497.
On file for this project
10 documents
Installation of temporary construction fence equipment as per plans filed herewith. This application is filed in conjunction with NB-321600497.
On file for this project
2 documents
CellarConcrete reinforcement foundation1p · 1 filing
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Install foundation as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB# 321600497
On file for this project
5 documents · 1 drawing sheet
Site & exteriorTemporary plywood fence installation4 filings · 15 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Earth Work · Foundation · Protection and Mechanical Methods · Sidewalk Shed
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
On file for this project
4 documents · 3 drawing sheets
INSTALLATION OF 6000 LB SINGLE PERSONNEL/MATERIAL HOIST CAR AS PER PLANS DURING CONSTRUCTION. HOIST SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 3 drawing sheets
INSTALLATION OF 300PSF SIDEWALK SHED, OVERHEAD PROTECTION AND ROOF PROTECTION AS PER PLANS.ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE NYC CODE 2022. NO USE IN EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 5 drawing sheets
Latest 3 of 4 filings on this floor.