← Back
Factory, heavy manufacturing, fireproof
49-33 31 PLACE
QUEENS · BIN 4003549
💬 Discuss this project
1962Year Built
2Stories
F1Building Class
M2-1Zoning
47,540 sfGross Floor Area
3Units
LL97 Covered0 Open Violations
Factory, heavy manufacturing, fireproof · Owner of record: B9 HUNTERS POINT OWNER LLC · 50,000 sf lot · 0.95 FAR built · Flood zone X500
Locations of Work
StructuralMechanicalPlumbingFire Protection
Roof11p · 3 filings · 20 docs
Floor 128p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
B9 HUNTERS POINT OWNER LLC103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HYKE ENGINEERING & MANAGEMENT PC707/28/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMB BUILDING CONSULTING1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
H BRONNER & SON PLBG & HTGPlumbing307/08/2026
DUDLEY JAMALElectrical203/21/2026
JAMAL DUDLEYElectrical203/21/2026
SAFETY FIRE SPRINKLER CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HYKE ENGINEERING & MANAGE2422607/28/2020
Building Lifecycle
All (79)Filed (7)Permit Issued (4)Violation (2)Objection (44)Special Inspection (22)
08/03/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/03/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/09/2020
Permit issued — Plumbing
Q00265618-I1-PL
08/16/2020
Special inspection requirement — Fire-Resistance Rated Construction
08/16/2020
Special inspection requirement — Energy Code Compliance Inspections
08/04/2020
Special inspection requirement — Energy Code Compliance Inspections
Gene Hu
08/04/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gene Hu
08/04/2020
Special inspection requirement — Post-installed Anchors
Gene Hu
07/31/2020
Objection resolved — Addressed
07/30/2020
Objection raised — Scope
07/28/2020
Filed — Alteration
PROPOSE PLUMBING WORK IN CONJUNCTION WITH ALT II # 440569886. PROVIDE DOMESTIC WATER AND GAS MODIFICATIONS TO EXISTING SYSTEMS FOR TENANT FIT OUT. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q00265618-P3
07/25/2020
Special inspection requirement — Post-installed Anchors
Gene Hu
07/25/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gene Hu
07/25/2020
Special inspection requirement — Energy Code Compliance Inspections
Gene Hu
07/21/2020
Objection raised — Admin
07/21/2020
Objection resolved — Addressed
07/20/2020
Permit issued — Sprinklers
Q00353636-I1-EW-SP
07/20/2020
Objection raised — Scope
07/20/2020
Objection resolved — Addressed
07/20/2020
Objection raised — Zoning
07/20/2020
Objection resolved — Addressed
07/20/2020
Objection raised — Energy
07/20/2020
Objection resolved — Addressed
07/16/2020
Filed — Alteration
Propose to install HVAC rooftop units equipment, walk-in refrigeration equipment, and kitchen hood duct & exhausts as per plan. This is filed in conjunction with Alt 2 # 440569886.
Q00293249-I1
07/16/2020
Filed — Alteration
PROPOSE PLUMBING WORK IN CONJUNCTION WITH ALT II # 440569886. PROVIDE DOMESTIC WATER AND GAS MODIFICATIONS TO EXISTING SYSTEMS FOR TENANT FIT OUT. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q00265618-P2
06/14/2020
Objection resolved — Addressed
06/14/2020
Objection resolved — Addressed
06/14/2020
Objection resolved — Addressed
06/14/2020
Objection resolved — Addressed
06/14/2020
Objection resolved — Addressed
06/11/2020
Objection raised — Mechanical
06/11/2020
Objection raised — Scope
06/11/2020
Objection raised — Structural
06/11/2020
Objection raised — Scope
06/11/2020
Objection raised — Scope
06/08/2020
Filed — Alteration
Propose Sprinkler Work in conjunction with Alt 2 # 440569886
Q00353636-I1
04/28/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gene Hu
04/28/2020
Special inspection requirement — Post-installed Anchors
Gene Hu
04/28/2020
Special inspection requirement — Energy Code Compliance Inspections
Gene Hu
01/29/2020
Objection resolved — Addressed
01/28/2020
Objection raised — Other
01/21/2020
Filed — Alteration
PROPOSE PLUMBING WORK IN CONJUNCTION WITH ALT II # 440569886. PROVIDE DOMESTIC WATER AND GAS MODIFICATIONS TO EXISTING SYSTEMS FOR TENANT FIT OUT. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q00265618-P1
01/21/2020
Permit issued — Plumbing
Q00265618-I1-PL
01/16/2020
Filed — Alteration
Q00267132-I1
01/16/2020
Special inspection requirement — Energy Code Compliance Inspections
Gene Hu
01/16/2020
Special inspection requirement — Post-installed Anchors
Gene Hu
01/16/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gene Hu
01/08/2020
Special inspection requirement — Mechanical Systems
Gene Hu
01/08/2020
Special inspection requirement — HVAC and service water heating system controls
Gene Hu
01/08/2020
Special inspection requirement — Heating Systems
Gene Hu
01/08/2020
Special inspection requirement — Shutoff dampers
Gene Hu
01/08/2020
Special inspection requirement — Maintenance information
Gene Hu
01/08/2020
Special inspection requirement — HVAC and service water heating equipment
Gene Hu
01/08/2020
Special inspection requirement — Final
Gene Hu
01/08/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gene Hu
12/19/2019
Permit issued — Plumbing
Q00265618-I1-PL
11/20/2019
Objection raised — Fire_Protection
11/20/2019
Objection resolved — Addressed
11/20/2019
Objection raised — Inspections
11/20/2019
Objection resolved — Addressed
Latest 60 of 79 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedH BRONNER & SON PLBG & HT12/09/2020
DOB NOWSprinklersPermit IssuedSAFETY FIRE SPRINKLER CORP07/20/2020
DOB NOWPlumbingPermit IssuedH BRONNER & SON PLBG & HT01/21/2020
DOB NOWPlumbingPermit IssuedH BRONNER & SON PLBG & HT12/19/2019
BISOTISSUEDDEBONO BROS. BUILDERS & D10/17/2019
BISOTISSUEDROSS SOLAR GROUP LLC11/17/2011
BISOTISSUEDCOOK AND KRUPA, INC11/18/1999
BISOTISSUEDJDLB PLUMBING & HEATING CORP.01/30/1997
BISPLISSUEDJDLB PLUMBING & HEATING CORP.01/30/1997
1 project · most recent 07/16/2020
Air Conditioning Systems Heating Systems Refrigeration Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/16/2020——Air Conditioning Systems, Heating Systems, Refrigeration Systems, Ventilation Systems
Cooling
Friedrich WET12A33A 12,000 BTU · Ptac ×2
Daikin MPS-061-FLA 732,000 BTU ×1
Heating
Friedrich WET1233A 11,000 BTU · Ptac ×1
WET12A33A 11,000 BTU · Ptac ×1
Daikin MPS-061-FLA 790,000 BTU ×1
Ventilation
Captiveaire USB136DD-RM 5,600 CFM · Exhaust Fan ×3
USB124DD-RM 5,042 CFM · Exhaust Fan ×2
A4-D1.000-30D 7,500 CFM · Makeup Air ×1
A5-D.200-36D 12,458 CFM · Makeup Air ×1
Refrigeration
Trenton TESA100H8-HT3C 96,748 BTU · Rooftop Unit ×17
TESA077H8-HT3C 72,790 BTU · Rooftop Unit ×2
TESA220L6-HT3C 88,000 BTU · Condensing Unit ×2
1 project · most recent 06/08/2020
FiledStatusContractorScope
06/08/2020Permit IssuedSAFETY FIRE SPRINKLER COR—
1 project · most recent 07/28/2020
Gas Water/Sanitary
FiledStatusContractorScope
07/28/2020Permit IssuedH BRONNER & SON PLBG & HTGas, Water/Sanitary
2 projects · most recent 09/19/2021
General Wiring
FiledStatusContractorScope
09/19/2021Permit IssuedKGB ELEC'L CONTR'G CORPGeneral Wiring
11/27/2019Permit IssuedAMRA ELECTRICAL CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
08/16/2020Fire-Resistance Rated Construction—progress
08/16/2020Energy Code Compliance Inspections—progress
08/04/2020Energy Code Compliance InspectionsGene Huprogress
08/04/2020Fire-Resistant Penetrations and JointsGene Huspecial
08/04/2020Post-installed AnchorsGene Huspecial
07/25/2020Post-installed AnchorsGene Huspecial
07/25/2020Fire-Resistant Penetrations and JointsGene Huspecial
07/25/2020Energy Code Compliance InspectionsGene Huprogress
04/28/2020Fire-Resistant Penetrations and JointsGene Huspecial
04/28/2020Post-installed AnchorsGene Huspecial
04/28/2020Energy Code Compliance InspectionsGene Huprogress
01/16/2020Energy Code Compliance InspectionsGene Huprogress
01/16/2020Post-installed AnchorsGene Huspecial
01/16/2020Fire-Resistant Penetrations and JointsGene Huspecial
01/08/2020Mechanical SystemsGene Huspecial
01/08/2020HVAC and service water heating system controls Gene Huenergy_progress
01/08/2020Heating SystemsGene Huspecial
01/08/2020Shutoff dampersGene Huenergy_progress
01/08/2020Maintenance informationGene Huenergy_progress
01/08/2020HVAC and service water heating equipment Gene Huenergy_progress
01/08/2020FinalGene Huprogress
01/08/2020Fire-Resistant Penetrations and JointsGene Huspecial
▾Documents — 80 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch - Plumbing4
08/15/2026Q00265618-I1Request digital key ↗
08/15/2026Q00265618-P2Request digital key ↗
08/15/2026Q00265618-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/15/2026Q00293249-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
08/15/2026Q00353636-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
08/28/2026Q00267132-I1Request digital key ↗
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION5
06/18/2020440594858Open ↗
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION2
10/16/2019440569886Open ↗
11/18/2011420505439Open ↗
▸Seals & Professional Certifications36
▸DOB NOWSpecial Inspector Seal & Signature11
09/01/2026Q00265618-P1Open ↗
09/01/2026Q00265618-P1Open ↗
09/01/2026Q00265618-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026Q00265618-P1Open ↗
09/01/2026Q00265618-I1Open ↗
09/01/2026Q00265618-P2Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/13/2026Q00353636-I1Open ↗
08/13/2026Q00265618-P1Open ↗
08/13/2026Q00293249-I1Open ↗
Showing 3 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
11/18/2011420505439Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
11/18/2011420505439Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
11/18/2011420505439Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/13/2026Q00265618-P3Open ↗
08/13/2026Q00267132-I1Open ↗
08/13/2026Q00265618-P2Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
11/18/2011420505439Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/22/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISTECHNICAL REPORT: ENERGY1
11/18/2011420505439Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
07/22/2020440594858Open ↗
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION2
02/09/2012420505439Open ↗
02/09/2012420505439Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
11/18/2011420505439Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
06/16/2012420505439Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION2
07/22/2020440594858Open ↗
06/16/2012420505439Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
05/18/2020440594858Open ↗
10/16/2019440569886Open ↗
▸BISEFILING COVER SHEET1
11/18/2011420505439Open ↗