| Owner | Filings | Most Recent |
|---|---|---|
| 2022 A N J CONSTRUCTION | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/28/2023 | $960K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| YOU GAO | 3 | 06/16/2026 |
| FANG ARCHITECT | 3 | 12/26/2024 |
| ZHENG & ASSOCIATES LLC | 1 | 08/24/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| INDESIGN STUDIO | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| W.JAKE CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| 2022 A N J CONSTRUCTION * | General Contractor | 2 | 04/09/2026 |
| VILLAGE P & H NY INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| YAN GAO | 6619 | 3 | 06/16/2026 |
| FANG ARCHITECT | 5513 | 2 | 12/26/2024 |
| ZHENG & ASSOCIATES LLC | 7330 | 1 | 08/24/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | VILLAGE P & H NY INC | 06/10/2026 |
| DOB NOW | Construction Fence | Permit Issued | 2022 A N J CONSTRUCTION | 07/11/2025 |
| DOB NOW | Plumbing | Permit Issued | VILLAGE P & H NY INC | 02/25/2025 |
| DOB NOW | General Construction | Permit Issued | 2022 A N J CONSTRUCTION | 09/24/2024 |
| DOB NOW | Construction Fence | Permit Issued | W.JAKE CONSTRUCTION CORP | 10/25/2023 |
| DOB NOW | Full Demolition | Signed-off | W.JAKE CONSTRUCTION CORP | 10/24/2023 |
| BIS | OT | ISSUED | M. INT'L ENGINEERING PLLC | 10/22/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/26/2024 | Permit Issued | 2022 A N J CONSTRUCTION * | Heating Systems, Ventilation Systems | Heating Navien NCB-240 199,900 BTU · Boiler ×1 Ventilation Panasonic ×6 Greentek ×4 Kitchenaid ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | — | — | 24 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | Permit Issued | PARAMOUNT SERVICES, LLC | Gas, Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2025 | Complete | KJK ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/16/2023 | Permit Issued | 2022 A N J CONSTRUCTION | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/26/2024 | Permit Issued | 2022 A N J CONSTRUCTION * | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/11/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/06/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/06/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/17/2026 | HVAC-R and service water piping design and insulation | YAN GAO | energy_progress |
| 06/17/2026 | HVAC-R and service water heating equipment | YAN GAO | energy_progress |
| 06/17/2026 | HVAC-R and service water heating system controls | YAN GAO | energy_progress |
| 06/17/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | YAN GAO | special |
| 06/17/2026 | Fire-Resistant Penetrations and Joints | YAN GAO | special |
| 06/17/2026 | Energy Code Compliance Inspections | YAN GAO | progress |
| 11/01/2023 | Fire-Resistance Rated Construction | DEZHANG FANG | progress |
| 11/01/2023 | Structural Wood Frame | DEZHANG FANG | progress |
| 11/01/2023 | Air barrier — testing | DEZHANG FANG | energy_progress |
| 11/01/2023 | Air barrier - visual inspection | DEZHANG FANG | energy_progress |
| 11/01/2023 | HVAC-R and service water heating system controls | DEZHANG FANG | energy_progress |
| 11/01/2023 | Maintenance information | DEZHANG FANG | energy_progress |
| 11/01/2023 | Duct leakage testing, insulation and design | DEZHANG FANG | energy_progress |
| 11/01/2023 | Fenestration air leakage | DEZHANG FANG | energy_progress |
| 11/01/2023 | Concrete - Cast-In-Place | DEZHANG FANG | special |
| 11/01/2023 | Fenestration areas | DEZHANG FANG | energy_progress |
| 11/01/2023 | Metering | DEZHANG FANG | energy_progress |
| 11/01/2023 | HVAC-R and service water heating equipment | DEZHANG FANG | energy_progress |
| 11/01/2023 | Electric vehicle service equipment requirements | DEZHANG FANG | energy_progress |
| 11/01/2023 | HVAC-R and service water piping design and insulation | DEZHANG FANG | energy_progress |
| 11/01/2023 | Interior lighting power | DEZHANG FANG | energy_progress |
| 11/01/2023 | Insulation placement and R values | DEZHANG FANG | energy_progress |
| 11/01/2023 | Permanent certificate | DEZHANG FANG | energy_progress |
| 11/01/2023 | Protection of exposed foundation insulation | DEZHANG FANG | energy_progress |
| 11/01/2023 | Ventilation and air distribution system | DEZHANG FANG | energy_progress |