1954Year Built
1Stories
E9Building Class
M2-1Zoning
30,228 sfGross Floor Area
1Units
LL97 Covered0 Open Violations
Miscellaneous warehouse · Owner of record: GOTTLIEB MONCHER (LIC), LLC · 57,300 sf lot · 0.53 FAR built · Flood zone X500
Locations of Work
MechanicalPlumbing
Roof3p · 3 filings · 20 docs
Floor 13p · 3 filings · 20 docs
Cellar2p · 3 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GOTTLIEB MONCHER (LIC) LLC2103/22/2026
ABCO REFRIGERATION SUPPLY CO,2103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAZINI ENGINEERING, P.C.612/16/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MID COUNTY MECHANICAL CORGeneral Contractor603/21/2026
ECONOMY P & H CO.,INCPlumbing207/08/2026
MID-COUNTY ELECTRIC INC.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BAZINI ENGINEERING, P.C.1808512/16/2024
Building Lifecycle
All (50)Filed (6)Permit Issued (5)Signed Off (4)Violation (23)Inspection (5)Special Inspection (7)
01/14/2025
Signed off — Alteration
REPLACE FIVE (5) ROOFTOP HVAC UNITS ON EXISTING DUNNAGE, INSTALL FOUR (4) HEATING AND VENTILATING UNITS, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00839921-I1
01/13/2025
Signed off — Alteration
INSTALL REPLACEMENT GAS PIPING TO CONNECT TO FIVE (5) ROOFTOP HVAC UNITS, FOUR (4) HEATING AND VENTILATING UNITS AND REPLACEMENT HOT WATER BOILER AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00839934-I1
01/13/2025
Signed off — Alteration
Q00839983-I1
12/29/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/16/2024
Filed — Alteration
INSTALL REPLACEMENT GAS PIPING TO CONNECT TO FIVE (5) ROOFTOP HVAC UNITS, FOUR (4) HEATING AND VENTILATING UNITS AND REPLACEMENT HOT WATER BOILER AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00839934-P1
11/15/2024
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
10/31/2024
Permit issued — Boiler Equipment
Q00839983-I1-BE
10/15/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/30/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/18/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
08/20/2024
Signed off — Alteration
Q01021779-I1
06/20/2024
Permit issued — Plumbing
Q00839934-I1-PL
05/21/2024
Permit issued — Mechanical Systems
Q00839921-I1-GC-CX
05/21/2024
Permit issued — Mechanical Systems
Q01021779-I1-MS
05/21/2024
Special inspection requirement — Mechanical Systems
Joseph Bazini
05/21/2024
Special inspection requirement — Final
Joseph Bazini
05/20/2024
Filed — Alteration
Q01021779-I1
05/20/2024
Filed — Alteration
REPLACE FIVE (5) ROOFTOP HVAC UNITS ON EXISTING DUNNAGE, INSTALL FOUR (4) HEATING AND VENTILATING UNITS, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00839921-P1
05/20/2024
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Bazini
03/19/2024
Special inspection requirement — Final
Joseph Bazini
03/19/2024
Special inspection requirement — Mechanical Systems
Joseph Bazini
03/18/2024
Special inspection requirement — Final
Joseph Bazini
03/18/2024
Special inspection requirement — Mechanical Systems
Joseph Bazini
10/31/2023
Permit issued — Mechanical Systems
Q00839921-I1-GC-CX
10/26/2023
Filed — Alteration
REPLACE FIVE (5) ROOFTOP HVAC UNITS ON EXISTING DUNNAGE, INSTALL FOUR (4) HEATING AND VENTILATING UNITS, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00839921-I1
10/26/2023
Filed — Alteration
INSTALL REPLACEMENT GAS PIPING TO CONNECT TO FIVE (5) ROOFTOP HVAC UNITS, FOUR (4) HEATING AND VENTILATING UNITS AND REPLACEMENT HOT WATER BOILER AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00839934-I1
10/26/2023
Filed — Alteration
Q00839983-I1
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/01/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/29/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/08/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/15/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/03/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/19/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/06/2006
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/19/2003
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/19/2003
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/26/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/26/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offECONOMY P & H CO.,INC10/31/2024
DOB NOWPlumbingSigned-offECONOMY P & H CO.,INC06/20/2024
DOB NOWMechanical SystemsSigned-offMID COUNTY MECHANICAL COR05/21/2024
DOB NOWMechanical SystemsSigned-offMID COUNTY MECHANICAL COR05/21/2024
DOB NOWMechanical SystemsSigned-offMID COUNTY MECHANICAL COR10/31/2023
BISPLISSUEDECONOMY P & H CO.,INC08/22/2017
BISOTISSUEDJOHN GALLIN & SON, INC02/27/2013
BIS—ISSUEDPAUL SIGNS, INC12/12/2012
BIS—ISSUEDPAUL SIGNS, INC12/12/2012
BIS—ISSUEDPAUL SIGNS, INC12/12/2012
BIS—ISSUEDPAUL SIGNS, INC12/12/2012
BISMHISSUEDARISTA AIR CONDITIONING CORP03/26/2012
BIS—ISSUEDABCO REFRIGERATION SUPPLY CORP07/12/2011
BISOTISSUEDP VERARDI CONSTRUCTION09/02/2005
BISPLISSUEDADVANCED PLUMBING MECH08/01/2005
BISMHISSUEDP VERARDI CONSTRUCTION07/27/2005
BISPLISSUEDADVANCED PLUMBING HEATING SPRINK12/01/2004
BISMHISSUEDGOTTLIEB & MONCHER11/04/2004
BISMHISSUEDP. VERARDI CONSTRUCTION10/13/2004
BISOTISSUEDP. VERARDI CONSTRUCTION10/13/2004
BISOTISSUEDP. VERARDI CONSTRUCTION10/13/2004
BISMHISSUEDPENGUIN AIR CONDITIONING02/23/2001
BISOTISSUEDCOLUX INC.10/23/2000
1 project · most recent 03/20/2023
General Wiring
FiledStatusContractorScope
03/20/2023Permit IssuedMID-COUNTY ELECTRIC INC.General Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
12/29/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/15/2024Pass-Final Boiler Equipment InspectionPassView ↗
10/15/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/18/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
05/21/2024Mechanical SystemsJoseph Bazinispecial
05/21/2024FinalJoseph Baziniprogress
05/20/2024HVAC-R and service water heating equipmentJoseph Bazinienergy_progress
03/19/2024FinalJoseph Baziniprogress
03/19/2024Mechanical SystemsJoseph Bazinispecial
03/18/2024FinalJoseph Baziniprogress
03/18/2024Mechanical SystemsJoseph Bazinispecial
▾Documents — 152 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/23/2026Q00839983-I1Request digital key ↗
08/22/2026Q00839921-P1Request digital key ↗
08/22/2026Q00839921-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits21
▸BISPLAN / WORK APPROVAL APPLICATION13
10/02/2025440703918Open ↗
02/14/2022440703918Open ↗
10/07/2021420319060Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION8
08/25/2017420556133Open ↗
03/04/2013420556133Open ↗
12/13/2012420792994Open ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications35
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION11
12/31/2012420792994Open ↗
12/31/2012420792985Open ↗
12/31/2012420792976Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/23/2026Q00839983-I1Open ↗
08/22/2026Q00839921-P1Open ↗
08/22/2026Q00839921-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
12/10/2012420793010Open ↗
12/10/2012420792994Open ↗
12/10/2012420792985Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
12/10/2012420792994Open ↗
12/10/2012420792985Open ↗
12/10/2012420792976Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/26/2026Q00839921-P1Open ↗
08/26/2026Q00839921-I1Open ↗
08/25/2026Q01021779-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/26/2026Q00839921-P1Open ↗
08/26/2026Q00839921-I1Open ↗
08/25/2026Q01021779-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/14/2022440703918Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/14/2022440703918Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/14/2022440703918Open ↗
▸Trade Schedules & Equipment24
▸BISEQUIPMENT USE PERMITS19
03/30/2012420538118Open ↗
03/30/2012420538118Open ↗
03/30/2012420538118Open ↗
Showing 3 of 19 on file for this type
▸BISSCHEDULE B - PLUMBING2
08/07/2012420600558Open ↗
04/16/2012420556133Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT2
03/30/2012420538118Open ↗
03/30/2012420538118Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
08/07/2012420600558Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
07/13/2011420319060Open ↗
▸Environmental & Asbestos13
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
12/10/2012420792994Open ↗
12/10/2012420792985Open ↗
12/10/2012420792976Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/23/2026Q00839983-I1Open ↗
08/22/2026Q00839921-P1Open ↗
08/22/2026Q00839921-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
04/16/2012420556133Open ↗
02/29/2012420538118Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
01/26/2011420319060Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY4
03/30/2012420538118Open ↗
02/29/2012420538118Open ↗
07/08/2011420319060Open ↗
Showing 3 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections1
03/12/2013420556133Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/30/2012420538118Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
09/04/2012420600558Open ↗
▸Inspections & Test Reports2
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)2
06/30/2022440703918Open ↗
02/14/2022440703918Open ↗
▸Approvals, Objections & Sign-offs17
▸BISADMINISTRATIVE OBJECTIONS8
12/10/2012420792994Open ↗
12/10/2012420792976Open ↗
12/10/2012420793010Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
12/31/2012420792985Open ↗
12/31/2012420792976Open ↗
12/31/2012420792994Open ↗
Showing 3 of 5 on file for this type
▸BISFINAL2
06/22/2022440703918Open ↗
02/14/2022440703918Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
03/18/2011420319060Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
03/30/2012420538118Open ↗
▸Cost, Insurance & Ownership15
▸BISCOST AFFIDAVIT14
02/14/2022440703918Open ↗
12/31/2012420792994Open ↗
12/31/2012420792976Open ↗
Showing 3 of 14 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT1
03/04/2013420556133Open ↗
▸Filing & Intake Forms9
▸BISEFILING COVER SHEET8
12/10/2012420792994Open ↗
12/10/2012420792976Open ↗
12/10/2012420793010Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
02/14/2022440703918Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM2
03/22/2011420319060Open ↗
01/26/2011420319060Open ↗